Programs and Manuals l
~~~~~~~~~~~~~~~
5.5 Programs and Manuals 5.5.9 Emergency Diesel Generator Fuel Oil Testing Program (continued)
- b.
Within 31 days following addition of new fuel oil to storage tanks, verify that the properties.of the new fuel oil, other than those addressed in a., above, are within limits for ASTM 2D fuel oil: and
- c.
Total particulate concentration of the fuel oil is
< 10 mg/il when tested every 31 days in accordance with ASTM D-2276, Method A.
The provisions of SR 3.0.2 and SR 3.0.3 are applicable to the'Emergency Diesel Generator Fuel Oil Testing Program testing frequencies.
5.5.10 Technical Specifications (TS) Bases Control Program This program provides a means for processing changes to the Bases of these Technical Specifications.
- a.
Changes to the Bases of the TS shall be made under appropriate administrative controls and reviews:
- b. Licensees may make changes to Bases without prior NRC approval provided the changes do not require either of the following:
- 1.
a change in the TS incorporated in the license; or
- 2.
a change to the UFSAR or Bases that requires NRC approval pursuant to 10 CFR 50.59.
- c.
The Bases Control Program shall contain provisions to ensure that the Bases are maintained consistent with the UFSAR.
- d.
Proposed changes that meet the criteria of Specification 5.5.10b above shall be reviewed and approved by the NRC prior to implementation. Changes to the Bases implemented without prior NRC approval shall be provided to the NRC on a frequency consistent with 10 CFR 50.71(e).
(continued)
FERMI - UNIT 2 5.0-16 Amendment No. AK 156