Draft Submittal
(Pink Paper)
FARLEY EXAM
50-348 & 50-364/2003-301
MAY 19 - 26,2003
1.
Operating Test Simulator Scenarios
Appendix D
Scenario Outline
Form ES-D-1
2
Facility:
Farlev
Scenario No.:
1
Op-Test No.:
1
Examiners:
Operators:
Initial Conditions:
Maintainina Load at 100% Dower, BOL.
C (BOP)
Turnover:
20 oDd Tube Leak in A SIG.
B MDAFW TI0 for Motor bearina oil chanoe out.
7
M (ALL)
C (ALL) *
L
(N)ormal, (R)eactivity,
(I
Event
Description
Perform STP-20.2, Penetration Room Filtration System
Train A Monthly Operability Test, Section 5.2.
"A" SIG PORV fails full open, (controller failure) Unable to
close from MCB. Isolated in MSVR. (Power should exceed
Ramp down in response to Open PORV.
1A Charging Pump trips (Standby pump fails to auto start).
PCV-145 transmitter fails HIGH.
PT-508 fails high (no ramp 1200,0,0) causing SGFPs to roll
back to minimum speed.
Feedwater break inside containment.(lnitiate upon
completion of regaining feed control 1 E6 lbmlhr 600sec
ramp.
One Phase A containment isolation valve fails to close.
Strument, (C)omponent, (M)ajor
40of 41
NUREG-1021, Draft Revision 9
Appendix D
Scenario Outline
Form ES-D-1
Facility:
Farlev
Scenario No.:
2
Op-Test No.:
1
Examiners:
Operators:
Initial Conditions:
Motor bearino oil chanae out
trip.
Turnover: .
breaker after maintenance. Leave 16 pumu runnina so next shift can work on 1A wrnu
breaker.
100% Power BOL 20 aud Tube Leak in A S/G.
B MDAFW TI0 for
LT-496 is failed hiah I&C to work durina shift. Bistables in
1A charaina pumu runnina Swals to 16 runnina to verify operabilitv of
Event
Description
Swap Charging pump from 1A to 1B per FNP-I-SOP-2.1
MSS card failure causing C FRV to close. (Default level
transmiter).
LT-459 spikes low (causing a loss of letdown). TIS.
VCT LT-115 fails low. (Causes an auto make up)
Tube leak on A S/G increases, Ops manager directs ramp
down. (Initiate next event when satisfied with ramp).
Condensate pump trip with a failure of the auto start for the
third condensate pump.
B Train LOSP with an " A
SGTR @ 600 gpm 120 sec, 0.
6 Charging Pump fails due to breaker trip. 1A pump cannot
be started.
jtrument,
(C)omponent, (M)ajor
40 of 41
NUREG-1021, Draft Revision 9
Appendix D
Scenario Outline
Form ES-D-1
Facility:
Farlev
Scenario No.:
3
Op-Test No.:
1
Examiners:
Operators:
Initial Conditions:
25% Power, EOL
~
~
Turnover:
20 aod Tube Leak in A SIG.
B MDAFW T/O for Motor bearincl oil chanae out.
Event
No.
1
2
3
4
5
6
7
(N)orm,
-
-
-
Malf.
No. -
Event
Type*
N (BOP)
C (BOP)
"
L
(RO/BOP)
c (RO)
M (ALL)
C (ALL)
Event
Description
1B DG Operability test to parallel to grid.
Load swings on the Diesel while tied to grid. Declare DG
INOP.(or High temp alarm)
Controlling Turbine Is'
stage pressure xmtr fails high.
Ramp increase in load to 50% Power.
Loss of " C Vital Instrument bus (Supply Breaker trip)
PT-444 fails high (2500, 5,O).
Small break LOCA 250gpm from PT-444 instrument line
requiring a Reactor Trip and SI.
" A
CCW pump fails to start and cannot be started from the
Control Room.
, (R)eactivity, (Qnstrument, (C)omponent, (M)ajor
40 of 41
NUREG-1021, Draft Revision 9