7/16/03 Callaway-Request for Withholding Info. from Public Disclosure-Application for Amd. Related to Steam Generator Tube Surveillance Program (CAW-03-1649/CAW-03-1650) (Tac. MB6478)
ML031980099
Person / Time
Site: Callaway Ameren icon.png
Issue date: 07/16/2003
From: Donohew J
NRC/NRR/DLPM/LPD4
To: Sepp H
Westinghouse
Donohew J N, NRR/DLPM,415-1307
References
CAW-03-1649, CAW-03-1650, TAC MB6478
Download: ML031980099 (4)


Text

July 16, 2003 Mr. H. A. Sepp, Manager Regulatory and Licensing Engineering Westinghouse Electric Company Nuclear Services P.O. Box 355 Pittsburgh, PA 15230-0355

SUBJECT:

REQUEST FOR WITHHOLDING INFORMATION FROM PUBLIC DISCLOSURE FOR CALLAWAY PLANT - APPLICATION FOR AMENDMENT RELATED TO STEAM GENERATOR TUBE SURVEILLANCE PROGRAM (CAW-03-1649 AND CAW-03-1650) (TAC NO. MB6478)

Dear Mr. Sepp:

By letter dated June 5, 2003 (ULNRC-04861), the Union Electric Company (UEC) submitted information related to its request to revise Technical Specification 5.5.9, "Steam Generator (SG) Tube Surveillance Program," to clearly delineate the scope of the tube inspection required in the SG tubesheet region for the rotating pancake coil (RPC). UEC requested that the following documents be withheld from public disclosure pursuant to Title 10 of the Code of Federal Regulations (10 CFR) Section 2.790:

LTR-SGDA-03-129, "Transmittal of Responses to NRC RAIs on Partial-Length RPC Inspection of the Tubesheet Region of the Callaway Plant Steam Generators to Ameren UE Callaway," dated June 2, 2003.

WCAP-15932-P, Revision 1, "Improved Justification of Partial-Length RPC Inspection of Tube Joints of Model F Steam Generators of Ameren-UE Callaway Plant," dated May 2003.

Nonproprietary copies of the documents have been placed in the Nuclear Regulatory Commission's (NRC's) Public Document Room and added to the Agencywide Documents Access and Management System Public Electronic Reading Room.

The affidavits dated June 3, 2003, executed by you, stated that the submitted information should be considered exempt from mandatory public disclosure for the following reasons:

(a)

The information reveals the distinguishing aspects of a process (or component, structure, tool, method, etc.) where prevention of its use by any of Westinghouse's competitors without license from Westinghouse constitutes a competitive economic advantage over other companies.

(c)

Its use by a competitor would reduce his expenditure of resources or improve his competitive position in the design, manufacture, shipment, installation, assurance of quality, or licensing a similar product.

H. Sepp (e)

It reveals aspects of past, present, or future Westinghouse or customer funded development plans and programs of potential commercial value to Westinghouse.

We have reviewed your application and the material in accordance with the requirements of 10 CFR 2.790 and, on the basis of your statements, have determined that the submitted information sought to be withheld contains proprietary commercial information and should be withheld from public disclosure.

Therefore, the document entitled, "Transmittal of Responses to NRC RAIs on Partial-Length RPC Inspection of the Tubesheet Region of the Callaway Plant Steam Generators to Ameren UE Callaway," and WCAP-15932-P, Revision 1, "Improved Justification of Partial-Length RPC Inspection of Tube Joints of Model F Steam Generators of Ameren-UE Callaway Plant," marked as proprietary, will be withheld from public disclosure pursuant to 10 CFR 2.790(b)(5) and Section 103(b) of the Atomic Energy Act of 1954, as amended.

Withholding from public inspection shall not affect the right, if any, of persons properly and directly concerned to inspect the information. If the need arises, we may send copies of this information to our consultants working in this area. If this is done, we will, of course, ensure that the consultants have signed the appropriate agreements for handling proprietary information.

If the basis for withholding this information from public inspection should change in the future such that the information could then be made available for public inspection, you should promptly notify the NRC of this fact. You should also understand that the NRC may have cause to review this determination in the future, for example, if the scope of a Freedom of Information Act request includes this information. In all review situations, if the NRC makes a determination adverse to the above determination, you will be notified in advance of any public disclosure.

If you have any questions regarding this matter, please contact me at 301-415-1307, or through the internet at jnd@nrc.gov.

Sincerely,

/RA/

Jack Donohew, Senior Project Manager, Section 2 Project Directorate IV Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-483 cc: See next page

H. Sepp (e)

It reveals aspects of past, present, or future Westinghouse or customer funded development plans and programs of potential commercial value to Westinghouse.

We have reviewed your application and the material in accordance with the requirements of 10 CFR 2.790 and, on the basis of your statements, have determined that the submitted information sought to be withheld contains proprietary commercial information and should be withheld from public disclosure.

Therefore, the document entitled, "Transmittal of Responses to NRC RAIs on Partial-Length RPC Inspection of the Tubesheet Region of the Callaway Plant Steam Generators to Ameren UE Callaway," and WCAP-15932-P, Revision 1, "Improved Justification of Partial-Length RPC Inspection of Tube Joints of Model F Steam Generators of Ameren-UE Callaway Plant," marked as proprietary, will be withheld from public disclosure pursuant to 10 CFR 2.790(b)(5) and Section 103(b) of the Atomic Energy Act of 1954, as amended.

Withholding from public inspection shall not affect the right, if any, of persons properly and directly concerned to inspect the information. If the need arises, we may send copies of this information to our consultants working in this area. If this is done, we will, of course, ensure that the consultants have signed the appropriate agreements for handling proprietary information.

If the basis for withholding this information from public inspection should change in the future such that the information could then be made available for public inspection, you should promptly notify the NRC of this fact. You should also understand that the NRC may have cause to review this determination in the future, for example, if the scope of a Freedom of Information Act request includes this information. In all review situations, if the NRC makes a determination adverse to the above determination, you will be notified in advance of any public disclosure.

If you have any questions regarding this matter, please contact me at 301-415-1307, or through the internet at jnd@nrc.gov.

Sincerely,

/RA/

Jack Donohew, Senior Project Manager, Section 2 Project Directorate IV Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-483 DISTRIBUTION:

PUBLIC RBaum, OGC cc: See next page PDIV-2 Reading LLund RidsNrrDlpmLpdiv (HBerkow)

JTsao

  • For previous concurrences RidsNrrPMJDonohew see attached ORC RidsNrrLAEPeyton RidsRgn4MailCenter (DGraves)

Adams Accession No.: ML031980099 NRR-084 OFFICE PDIV-2/PM PDIV-2/LA EMCB/SC*

OGC*

PDIV-2/SC NAME JDonohew EPeyton LLund DHassell SDembek DATE 7/15/03 7/14/03 7/10/03 7/11/03 7/16/03 OFFICE RECORD COPY DOCUMENT NAME: G\\PDIV-2\\Callaway\\ProprietaryLetter-SGtubeInspection-MB6478.cw.wpd

Callaway Plant, Unit 1 cc:

Professional Nuclear Consulting, Inc.

19041 Raines Drive Derwood, MD 20855 John ONeill, Esq.

Shaw, Pittman, Potts & Trowbridge 2300 N. Street, N.W.

Washington, D.C. 20037 Mr. Mark A. Reidmeyer, Regional Regulatory Affairs Supervisor /

Regulatory Affairs AmerenUE P.O. Box 620 Fulton, MO 65251 U.S. Nuclear Regulatory Commission Resident Inspector Office 8201 NRC Road Steedman, MO 65077-1302 Manager, Quality Assurance AmerenUE P.O. Box 620 Fulton, MO 65251 Manager - Electric Department Missouri Public Service Commission 301 W. High P.O. Box 360 Jefferson City, MO 65102 Regional Administrator, Region IV U.S. Nuclear Regulatory Commission 611 Ryan Plaza Drive, Suite 400 Arlington, TX 76011-4005 Mr. Ronald A. Kucera Deputy Director for Public Policy Department of Natural Resources P.O. Box 176 Jefferson City, Missouri 65102 Mr. Rick A. Muench President and Chief Executive Officer Wolf Creek Nuclear Operating Corporation P.O. Box 411 Burlington, KA 66839 Mr. Dan I. Bolef, President Kay Drey, Representative Board of Directors Coalition for the Environment 6267 Delmar Boulevard University City, MO 63130 Mr. Lee Fritz, Presiding Commissioner Callaway County Court House 10 East Fifth Street Fulton, MO 65151 Mr. David E. Shafer Superintendent, Licensing Regulatory Affairs AmerenUE P.O. Box 66149, MC 470 St. Louis, MO 63166-6149 Manager, Regulatory Affairs AmerenUE P.O. Box 620 Fulton, MO 65251 Mr. Scott Clardy, Director Section for Environmental Public Health P.O. Box 570 Jefferson City, MO 65102-0570 Mr. Garry L. Randolph Vice President and Chief Nuclear Officer Union Electric Company Post Office Box 620 Fulton, MO 65251