Summary of Public Meetings to Discuss the Licensee'S Plans to Address Engineering Design Issue Resolution for Davis-Besse Nuclear Power Station
ML031900388
Person / Time
Site: Davis Besse Cleveland Electric icon.png
Issue date: 07/07/2003
From: Christine Lipa
NRC/RGN-III/DRP/RPB4
To:
References
Download: ML031900388 (5)


Text

July 7, 2003 LICENSEE: FirstEnergy Nuclear Operating Company FACILITY: Davis-Besse Nuclear Power Station, Unit 1

SUBJECT:

SUMMARY

OF THE MAY 7, 2003, PUBLIC MEETINGS TO DISCUSS THE LICENSEES PLANS TO ADDRESS ENGINEERING DESIGN ISSUE RESOLUTION FOR DAVIS-BESSE NUCLEAR POWER STATION On May 7, 2003, the Nuclear Regulatory Commission (NRC) held a public meeting at the NRC Region III office in Lisle, Illinois. The meeting was between the NRC Davis-Besse Oversight Panel and FirstEnergy Nuclear Operating Company (FENOC) to discuss the licensees plans to address Engineering Design Issue Resolution for Davis-Besse Nuclear Power Station. The meeting notice, transcript, and the FENOC presentation can be found in ADAMS as ML031150606, ML031710231, and ML031770429; respectively. A list of NRC and licensee meeting participants can be found in Enclosure 1.

These documents and many others related to the reactor vessel head degradation can also be found on the NRCs website at http://www.nrc.gov/reactors/operating/ops-experience/vessel-head-degradation.html.

/RA DPassehl Acting for/

Christine A. Lipa, Chief Branch 4 Division of Reactor Projects Docket No. 50-346 License No. NPF-3 See Attached Distribution Enclosure

DOCUMENT NAME: C:\ORPCheckout\FileNET\ML031900388.wpd To receive a copy of this document, indicate in the box: "C" = Copy without attachment/enclosure "E" = Copy with attachment/enclosure "N" = No copy OFFICE RIII RIII NAME DPassehl:klg /RA DPassehl Acting for/ CLipa DATE 07/07/03 07/07/03 OFFICIAL RECORD COPY

FirstEnergy Nuclear Operating Company cc w/encls: The Honorable Dennis Kucinich B. Saunders, President - FENOC Plant Manager Manager - Regulatory Affairs M. OReilly, FirstEnergy Ohio State Liaison Officer R. Owen, Ohio Department of Health Public Utilities Commission of Ohio D. Lochbaum, Union Of Concerned Scientists S. Arndt, President, Ottawa County Board of Commissioners C. Emahiser, Ottawa County Sheriff J. P. Greer, Director, Ottawa County Emergency Management Agency H. Barlos, President, Lucas County Board of Commissioners J. Telb, Lucas County Sheriff B. Halsey, Director, Lucas County Emergency Management Agency G. Adams, Village Administrator, Genoa The Honorable John Weber The Honorable Lowell C. Krumnow The Honorable Joseph Verkin The Honorable Thomas Leaser The Honorable Jack Ford The Honorable Thomas Brown The Honorable Joe Ihnat, Jr.

INPO

FirstEnergy Nuclear Operating Company cc w/encls: The Honorable Dennis Kucinich B. Saunders, President - FENOC Plant Manager Manager - Regulatory Affairs M. OReilly, FirstEnergy Ohio State Liaison Officer R. Owen, Ohio Department of Health Public Utilities Commission of Ohio D. Lochbaum, Union Of Concerned Scientists S. Arndt, President, Ottawa County Board of Commissioners C. Emahiser, Ottawa County Sheriff J. P. Greer, Director, Ottawa County Emergency Management Agency H. Barlos, President, Lucas County Board of Commissioners J. Telb, Lucas County Sheriff B. Halsey, Director, Lucas County Emergency Management Agency G. Adams, Village Administrator, Genoa The Honorable John Weber The Honorable Lowell C. Krumnow The Honorable Joseph Verkin The Honorable Thomas Leaser The Honorable Jack Ford The Honorable Thomas Brown The Honorable Joe Ihnat, Jr.

INPO ADAMS Distribution:

AJM DFT H. Nieh (HKN), OEDO Project Director, NRR Project Mgr., NRR RidsNrrDipmlipb JLC1 GEG HBC RML2 SRI Davis-Besse DRPIII DRSIII PLB1 JRK1

Enclosure 1 Meeting Participants NRC J. Grobe, Chairman, Davis-Besse Oversight Panel C. Lipa, Branch Chief, RIII C. Pederson, Division Director, Department of Reactor Safety, RIII R. Gardner, Senior Project Manager, Department of Reactor Safety, RIII D. Hills, Branch Chief, Department of Reactor Safety, RIII D. Passehl, Project Engineer, RIII M. Farber, Reactor Engineer, RIII FirstEnergy Nuclear Operating Company L. Myers, Chief Operating Officer R. Schrauder, Director - Support Services J. R. Fast, Plant Manager J. Powers, III, Director - Nuclear Engineering L. W. Pearce, Vice President, Quality Oversight M. Stevens, Director - Work Management C. Price, Manager - FENOC Business Services (Restart Action Plan Building Block Owner)