ML031710279
| ML031710279 | |
| Person / Time | |
|---|---|
| Site: | Davis Besse |
| Issue date: | 06/16/2003 |
| From: | Christine Lipa Division Reactor Projects III |
| To: | Myers L FirstEnergy Nuclear Operating Co |
| References | |
| Download: ML031710279 (3) | |
Text
June 16, 2003 Mr. Lew Myers Chief Operating Officer FirstEnergy Nuclear Operating Company Davis-Besse Nuclear Power Station 5501 North State Route 2 Oak Harbor, OH 43449-9760
Dear Mr. Myers:
This letter confirms the discussion between members of our staffs to discuss plant performance and progress on your Return to Service Plan for the Davis-Besse Nuclear Power Station, as part of the implementation of NRCs Inspection Manual Chapter (IMC) 0350 Oversight of Operating Reactor Facilities in a Shutdown Condition with Performance Problems. The meeting will be held July 9, 2003, from 2:00 p.m. to 5:00 p.m. (EDT) at the Oak Harbor High School. This meeting is open to the public.
The Davis-Besse Oversight Panel will also be conducting a separate meeting beginning at 7:00 p.m. (EDT) with the local public at the Oak Harbor High School to present the status of the NRCs activities in these areas and to answer any questions from members of the public.
We will gladly discuss any questions you may have concerning this matter.
Sincerely,
/RA/
Christine A. Lipa, Chief Branch 4 Division of Reactor Projects Docket No. 50-346 License No. NPF-3 See Attached Distribution
Mr. Lew Myers Chief Operating Officer FirstEnergy Nuclear Operating Company Davis-Besse Nuclear Power Station 5501 North State Route 2 Oak Harbor, OH 43449-9760
Dear Mr. Myers:
This letter confirms the discussion between members of our staffs to discuss plant performance and progress on your Return to Service Plan for the Davis-Besse Nuclear Power Station, as part of the implementation of NRCs Inspection Manual Chapter (IMC) 0350 Oversight of Operating Reactor Facilities in a Shutdown Condition with Performance Problems. The meeting will be held July 9, 2003, from 2:00 p.m. to 5:00 p.m. (EDT) at the Oak Harbor High School. This meeting is open to the public.
The Davis-Besse Oversight Panel will also be conducting a separate meeting beginning at 7:00 p.m. (EDT) with the local public at the Oak Harbor High School to present the status of the NRCs activities in these areas and to answer any questions from members of the public.
We will gladly discuss any questions you may have concerning this matter.
Sincerely, Christine A. Lipa, Chief Branch 4 Division of Reactor Projects Docket No. 50-346 License No. NPF-3 DOCUMENT NAME: C:\\ORPCheckout\\FileNET\\ML031710279.wpd To receive a copy of this document, indicate in the box: "C" = Copy without attachment/enclosure "E" = Copy with attachment/enclosure "N" = No copy OFFICE RIII RIII RIII RIII NAME CLipa/klg DPassehl DATE 06/16/03 06/10/03 OFFICIAL RECORD COPY
L. Myers cc w/encl:
The Honorable Dennis Kucinich B. Saunders, President - FENOC Plant Manager Manager - Regulatory Affairs M. OReilly, FirstEnergy Ohio State Liaison Officer R. Owen, Ohio Department of Health Public Utilities Commission of Ohio D. Lochbaum, Union Of Concerned Scientists S. Arndt, President, Ottawa County Board of Commissioners C. Emahiser, Ottawa County Sheriff J. P. Greer, Director, Ottawa County Emergency Management Agency H. Barlos, President, Lucas County Board of Commissioners J. Telb, Lucas County Sheriff B. Halsey, Director, Lucas County Emergency Management Agency G. Adams, Village Administrator, Genoa The Honorable John Weber The Honorable Lowell C. Krumnow The Honorable Joseph Verkin The Honorable Thomas Leaser The Honorable Jack Ford The Honorable Thomas Brown The Honorable Joe Ihnat, Jr.
AJM DFT H. Nieh (HKN), OEDO Project Director, NRR Project Mgr., NRR RidsNrrDipmlipb JLC1 GEG HBC RML2 SRI Davis-Besse DRPIII DRSIII PLB1 JRK1 DB0350