E-mail from S. Long to A. Hiser Et Al., Regarding Items for Today 2:00 Pm Davis Besse CallML031530399 |
Person / Time |
---|
Site: |
Davis Besse ![Cleveland Electric icon.png](/w/images/7/78/Cleveland_Electric_icon.png) |
---|
Issue date: |
04/15/2002 |
---|
From: |
Long S Office of Nuclear Reactor Regulation |
---|
To: |
Andruszkiewicz E, Bateman W, Steven Bloom, Chan T, Chung J, Stephanie Coffin, Jay Collins, Cullen W, Allen Hiser, Karwoski K, Albert Lee, Anthony Mendiola, Carol Moyer, Pickett D, Sands S, Steingass T, Switzer M, Wetzel B, Wichman K Office of Nuclear Reactor Regulation |
---|
References |
---|
FOIA/PA-2003-0018 |
Download: ML031530399 (2) |
|
|
---|
Category:E-Mail
MONTHYEARML23128A1612023-05-0808 May 2023 NRR E-mail Capture - Comanche Peak Nuclear Power Plant, Units 1 and 2, Beaver Valley Power Station, Unit Nos. 1 and 2, Davis-Besse Nuclear Power Station, Unit 1, and Perry Nuclear Power Plant, Unit No. 1 - Acceptance of Requested Licensing ML23086B9862023-03-27027 March 2023 NRR E-mail Capture - Davis-Besse, Unit No. 1 - Acceptance Review Results for Davis-Besse, Unit No. 1 - Proposed Alternative Request RP-5 ML23033A0322023-02-0101 February 2023 NRR E-mail Capture - Request for Additional Information for Davis-Besse's 2022 Steam Generator Inspection Report (L-2022-LRO-0115) ML22266A1102022-09-23023 September 2022 NRR E-mail Capture - Davis-Besse Nuclear Power Station, Unit No. 1 - Request for Additional Information Regarding July 21, 2022, Request for Withholding Information from Public Disclosure ML22164A8572022-06-13013 June 2022 NRR E-mail Capture - Davis-Besse Nuclear Power Station, Unit No. 1 - Request for Additional Information Regarding License Amendment Request to Revise the Emergency Plan ML22118A6862022-04-28028 April 2022 NRR E-mail Capture - Davis-Besse Nuclear Power Station, Unit No. 1 - Request for Additional Information Regarding Alternative to Extend the Steam Generator Weld Inspection Interval ML22112A1092022-04-22022 April 2022 NRR E-mail Capture - Davis-Besse Nuclear Power Station, Unit No. 1 - Request for Additional Information Regarding License Amendment Request to Revise the Design Basis for the Shield Building ML22090A1692022-03-30030 March 2022 Re_ Action Tracking Item 2022 SST - 335 - Tom Gurdziel, E-mail Re_ Event Number 55734 at Davis Besse, a Matter of Interpretation ML22080A2512022-03-18018 March 2022 NRR E-mail Capture - (External_Sender) ASME OM Code Case OMN-27, Alternative Requirements for Testing Category a Valves (Non- Piv/Civ) ML22055B0382022-02-24024 February 2022 NRR E-mail Capture - Davis-Besse Nuclear Power Station, Unit No. 1 - Upcoming Steam Generator Tube Inservice Inspection ML22055A0872022-02-23023 February 2022 NRR E-mail Capture - Davis-Besse Nuclear Power Station, Unit No. 1 - Request for Additional Information Regarding Relief Request RP-3 ML22045A4962022-02-14014 February 2022 NRR E-mail Capture - Davis-Besse Nuclear Power Station, Unit No. 1 - Acceptance of License Amendment Request to Revise the Emergency Plan ML22040A1832022-02-0707 February 2022 LTR-22-0033 Tom Gurdziel, E-mail Event Number 55734 at Davis Besse, a Matter of Interpretation ML22034A9472022-02-0303 February 2022 NRR E-mail Capture - Davis-Besse Nuclear Power Station, Unit No. 1 - Revised Review Estimates for Proposed Alternative to Extend the Steam Generator Weld Inspection Interval ML22033A0632022-02-0101 February 2022 NRR E-mail Capture - Davis-Besse Nuclear Power Station, Unit No. 1 - Acceptance of License Amendment Request to Revise the Design Basis for the Shield Building Containment Structure ML21321A3782021-11-16016 November 2021 NRR E-mail Capture - Energy Harbor Fleet, Beaver Valley Units 1 and 2 and DAVIS-BESSEL Unit 1 - Acceptance of License Amendment Request Adoption of TSTF-554 EPID-L-2021-LLA-0193 ML21321A3792021-11-16016 November 2021 NRR E-mail Capture - Davis-Besse Nuclear Power Station, Unit No. 1 - Request for Additional Information Regarding Alternative to Extend the Steam Generator Weld Inspection Interval ML21287A0382021-10-14014 October 2021 NRR E-mail Capture - Davis-Besse Nuclear Power Station, Unit No. 1 - Acceptance of Requests for Relief from Certain Inservice Testing Requirements ML21271A1332021-09-28028 September 2021 NRR E-mail Capture - Davis-Besse Nuclear Power Station, Unit No. 1 - Acceptance of Proposed Alternative RR-A2 for Certain Steam Generator Weld Inspections ML21119A2152021-04-28028 April 2021 NRR E-mail Capture - Energy Harbor Fleet, Beaver Valley Units 1 and 2 and DAVIS-BESSE Unit 1 - Acceptance of Relief Request Proposed Alternative to Use ASME OM Code Case OMN-27 ML21041A5452021-02-10010 February 2021 NRR E-mail Capture - Davis-Besse Nuclear Power Station, Unit No. 1 - Request for Additional Information Regarding Steam Generator Tube Inspection Reports ML21007A3732021-01-0707 January 2021 NRR E-mail Capture - (External_Sender) (External) Request for Additional Information Regarding License Amendment Request to Incorporate the Applicable Standard Technical Specification 5.2.2, Unit Staff, ML21004A1442020-12-30030 December 2020 NRR E-mail Capture - Request for Additional Information Regarding License Amendment Request to Incorporate the Applicable Standard Technical Specification 5.2.2, Unit Staff ML20329A3832020-11-24024 November 2020 NRR E-mail Capture - Davis Besse Nuclear Power Station, Unit No. 1 - Request for an Exemption from the 2020 Force-on-Force Exercises ML20304A2842020-10-29029 October 2020 50.59 Inspection 2nd Request for Information ML20289A0992020-10-0505 October 2020 NRR E-mail Capture - Energy Harbor Fleet, Results of Acceptance Review Request to Use Provision in Later Edition of the ASME Boiler and Pressure Vessel Code, Section XI, EPID-l-2020-LLR-0132 ML20281A3692020-10-0505 October 2020 Energy Harbor Fleet, Results of Acceptance Review Request to Use Provision in Later Edition of the ASME Boiler and Pressure Vessel Code, Section XI, EPID-l-2020-LLR-0132 ML20239A7942020-08-25025 August 2020 NRR E-mail Capture - Energy Harbor Fleet, Beaver Valley Units 1 and 2 and DAVIS-BESSEL Unit 1 - Acceptance of License Amendment Request Incorporation of Applicable Standard in TS 5.2.2.e ML20203M3712020-07-21021 July 2020 Ultimate Heat Sink Request for Information Part 1 ML20203M3722020-07-21021 July 2020 Ultimate Heat Sink Request for Information Part 1 and Part 2 L-20-183, Response to Request for Additional Information Regarding License Amendment Request for Adoption of TSTF-425, Revision 3, Relocate Surveillance Frequencies to Licensee Control - Risk Informed Technical Specification Task Force2020-06-23023 June 2020 Response to Request for Additional Information Regarding License Amendment Request for Adoption of TSTF-425, Revision 3, Relocate Surveillance Frequencies to Licensee Control - Risk Informed Technical Specification Task Force ML20154K7642020-06-0202 June 2020 NRR E-mail Capture - Davis-Besse Nuclear Power Station, Unit No. 1 - Request for Additional Information Regarding License Amendment Request to Adopt TSTF-425 ML20127H8672020-05-0606 May 2020 NRR E-mail Capture - Beaver Valley, Davis-Besse, and Perry - Request for Additional Information Regarding Request for Exemptions from Part 73 Security Requalification Requirements ML20058D3152020-02-27027 February 2020 Completion of License Transfer for the Beaver Valley, Davis-Besse and Perry Nuclear Units ML20024E0092020-01-23023 January 2020 NRR E-mail Capture - FENOC License Transfer - January 23, 2020 Call Summary ML20021A3162020-01-21021 January 2020 NRR E-mail Capture - Davis-Besse Nuclear Power Station - Request for Additional Information Regarding License Amendment Request to Revise Containment Leakage Rate Testing ML19346B3972019-12-11011 December 2019 NRR E-mail Capture - Davis-Besse Nuclear Power Station, Unit No. 1 - Acceptance of License Amendment Request to Adopt TSTF-425 ML19273A1132019-09-27027 September 2019 NRR E-mail Capture - Davis-Besse Nuclear Power Station - Acceptance of License Amendment Request to Extend Containment Leakage Rate Test Interval ML19179A1382019-06-28028 June 2019 NRR E-mail Capture - Davis-Besse - Request for Additional Information Regarding the Decommissioning Quality Assurance Program ML19164A1532019-06-13013 June 2019 NRR E-mail Capture - Davis-Besse Nuclear Power Station - Request for Additional Information Regarding License Amendment Request for Post-Shutdown Emergency Plan ML19162A3922019-06-11011 June 2019 NRR E-mail Capture - Davis-Besse Nuclear Power Station - Request for Additional Information Regarding License Amendment Request for Permanently Defueled Technical Specifications ML19161A2132019-06-0606 June 2019 NRR E-mail Capture - Results of Acceptance Review - FENOC Fleet - Request for Approval of Request for Approval of Lrradiated Fuel Management Plans, EPID L-2019-LRO-0016 ML19149A6202019-05-29029 May 2019 NRR E-mail Capture - Davis-Besse Nuclear Power Station, Unit No. 1 - Request for Approval of the Decommissioning Quality Assurance Program ML19130A2082019-05-0808 May 2019 Email - NRC Email to FEMA Dated May 8, 2019: NRC Response to Comment on FEMA Review of Proposed Changes to DBNPS Emergency Plan for Permanently Defueled Condition ML19106A2512019-04-16016 April 2019 NRR E-mail Capture - Davis-Besse - Proposed License Condition and Draft Safety Evaluation for the License Amendment Request to Adopt NFPA 805 ML19073A1112019-03-14014 March 2019 NRR E-mail Capture - Davis-Besse - Acceptance of License Amendment Request for Permanently Defueled License and Technical Specifications ML19043A6962019-02-0808 February 2019 NRR E-mail Capture - Davis-Besse License Amendment Request for the Post-Shutdown Emergency Plan ML18320A1272018-11-16016 November 2018 NRR E-mail Capture - Davis-Besse LAR to Change TS Definitions and Administrative Controls for Permanently Defueled Conditions ML18282A1482018-10-0909 October 2018 NRR E-mail Capture - Results of Acceptance Review - FENOC Fleet - Request for Exemption Related to the Suspension of Security Measures in an Emergency or During Severe Weather, EPID L-2018-LLL-0016 ML18282A2422018-10-0808 October 2018 OEDO-18-00160, FENOC Fleet, 2.206 Petition, Submission of Supplement Dated October 8, 2018, from the Petitioners - PRB and Petitioners (Elpc), Includes Email, Cover Letter from Elpc, and the Attachments to the Email 2023-05-08
[Table view] |
Text
S,~ i6h 2 Re: m r&Today's2:O0 pm. Dais-Bes e Call Pag i .
From: 1JQ1L'Steven Long To: Allen Hiser; Andrea Lee; Anthony Mendiola; Beth Wetzel; Bill Bateman; Carol Moyer; Douglas Pickett; Edward Andruszkiewicz; Jay Collins; Jin Chung; Keith Vvichman; Kenneth Karwoski; Michael Switzer; Stephanie Coffin; Stephen Sands; Steven Bloom; Terence Chan; Timothy Steingass; William Cullen Date: 4/15/02 7:15AM
Subject:
Re: Items for Today's 2:00 p.m. Davis-Besse Call I basically agree with Bill on the necessary sequencing of the detailed root cause investigations and the repair activities. But, since that means that the root cause will be rather speculative at the time that the i
- repair is made, I strongly believe that the repair strategy must be sufficient for all potential causes that have not been definitively ruled out by data or experiment at the time the repairs are made. At this point, the data are insufficient to fully support or completely dismiss the "best guess" degradation process that the licensee is pushing. Similarly, the data have not yet been shown to rule out corrosion of the cavity while the reactor is shut down and "cold." Since leakage onto the upper head is not likely to be completely prevented in the future, I suggest that the repair be designed with that in mind. The current plan to form an unclad "pothole" in the head material seems unwise, especially if the licensee expects us to really approve that repair for 15 years of future operation.
Steve Long
-S-e-e-nL-6n-':R-~Irfor Today's 200 pU. Davis-B-- Cal- v^^3J Mail Stop: T-10 E10 Ph: 301 - 415 - 6754 FAX: 301 - 415 - 5151 whc@nrc.gov
>>> Douglas Pickett 04/12/02 10:26AM >>>
I've informed the licensee that we need the final Root Cause report on the docket at least one week before we hold the Root Cause public meeting as required by the CAL. The licensee began to question whether the chemical analysis to be performed on the boron samples needs to be complete prior to the public meeting. In addition, once the 13-inch diameter hole is cut, there will be much more to analyze. We need to consider whether we can conduct a legitimate root cause public meeting without the chemical and failure analyzes being complete.
I also informed the licensee that a Commission meeting is being planned for Tuesday, May 28. In addition to the expected discussion on root cause and repairs, the licensee will be expected to provide their "get-well" program (i.e., a convincing argument as to why FirstEnergy is capable of safely operating Davis-Besse).
CC: - Christine Lipa; Edwin Hackett; John Grobe; John Jacobson; Laura Collins; Laura Gerke; Melvin Holmberg; Nilesh Chokshi; Ronald Gardner; Victor Dricks