Attachment 2 - PSEG Nuclear LLC Presentation Hope Creek Extended Power Uprate for 05/08/2003 Meeting with PSEG Nuclear, LLC and General Electric Nuclear Energy, Regarding Hope Creek Generating Station Proposed Extended Power Uprate
ML031530141
Person / Time
Site: Hope Creek PSEG icon.png
Issue date: 05/08/2003
From:
Public Service Enterprise Group
To:
Office of Nuclear Reactor Regulation
References
TAC MB8905
Download: ML031530141 (17)


Text

Attachment 2 v

Ds

-I i~7 uE EIAG Hope Creek Extended Power

prate, NRC / PSEG Nuclear Meeting Rockville Maryland May 8, 2003 1

" PSEG ANuclear LLC Introductions/Meetin2 Obiectives

  • Introduction
  • Meeting Objectives

- Provide overview of Hope Creek EPU

- Discuss licensing approach

- Gain NRC insights from previous uprates 2

Ol"z PSEG Nuclear LLC Agenda

  • Project Overview - R. Moore/D. McHugh
  • GE14 Transition - D. Notigan
  • EPU Licensing Approach - G. Salamon
  • Technical Quality Assurance - D. Garchow
  • Open Discussion 3

Nuclar LLC Project Overview 15% Licensed Power Uprate (to 3787 MWt)

- Evaluations performed for 120% OLTP

-I0% implemented in 2004

- Remaining increases in subsequent operating cycles

- No increase in Rx pressure 4

Auclear LLC Project Overview ELTR Process CLTR Process I

I i

I

-Reactor core and fuel performance (0200)

-Thermal-hydraulic stability (0202)

-ECCS LOCA performance (0407)

-Transient analyses (0900)

-ATWS (0902)

Fuel Dependent Evaluations Non-Fuel Dependent Evaluations PUSAR (GE14 equilibrium Core) 5

PSEG Nuclear LLC Project Overview Feasibility/Scoping study completed September, 2001 Company project approval April, 2002 Project team formed May, 2002 Major evaluation areas

  • Environmental (PSEG)

Project oversight

  • Grid stability (Independent system operator) 6

TtNclear LLC Pro ject Overview

  • Upgrades and Replacements RF1 1 (in progress)
  • 500 kV breaker indication Cycle 12 online
  • 500 kV breaker installation RF12 (Fall 2004)
  • Turbine moisture separators
  • FW heater & turbine moisture separator level controls
  • Isophase bus duct cooling 7

PSEG Nudlear LLC.

Pro'ect Overview Licensing Topical Areas

- ARTS/MELLLA

- EPU

  • Core Thermal Power (3787 MWt)
  • Tech Spec Changes
  • Possible Containment Over Pressurization Credit

- Revised Rx Pressure / Temperature Limits

- GEXL Correlation

- SLMCPR 8

Nucear LLC Project Overview

  • Current Status

- ARTS/IMELLLA project in progress

  • Cycle specific evaluations included

- EPU project in progress

- GE14 fuel transition in progress 9

PSEG; Nu c lear LLC GE14 Fuel Transition

  • Critical power calculations performed using GNF GEXL correlation Same process as Dresden/Quad Cities Cycle specific core limits from the reload process SRLR analysis from the reload process 10

uSEG Nuaxl6ee LLGC GE14 Fuel Transition

  • Submittals

- GEXL - August 2003

- Cycle specific SLMCPR and associated Tech Spec changes - October 2003

- SRLR report - February 2004 11

1~

l L

Nuaclear LLC GE14 Fuel Transition - GESTAR II 3-D Neutronic Simulation AL Complete b,~TilH SLMCPR Services Support Storage Rack Criticality T/M Modeling Transient/LOCA Lattice Physics Modeling GE14 FSAR /Tech Specs 12

GEXL for SVEA-96+ fuel ANuclear LLC GNF

[

PSEG PSEG GNF GNF PSEG PSEG uiat fine Critical Power i Collection Matrix

. Generate CP data Using ABB method Fit critical power data to GEXL Generate pin-to-pin peaking for data collection Submit GEXL coffelation to NRC GNF SLMCPR Calc Determine additive constants and bundle R-factors Statistical Comparison l

to ABB Test Data Qualify GEXL correlation bias and uncertainties 13

D PSECa Nldear LL C GE14 Fuel Transition Independent reviews/validations Design review of GEXL test matrix (PSEG/GE)

FMEA for GEXL correlation/calculations (PSEG/GE)

Engineering design reviews planned (PSEG/GE)

  • Nuclear design
  • T/H model
  • T/M model
  • RLP Independent validation using W computer codes 14

Schedule 10/04 RFO t

+

1-4 I

I I

I I

I I

I I

I I

8/03 9/03 10/03 NucSEa M3u dearz. LLGC MELLLA LCR EPU LCR GEXL Correlation Cycle Specific Reload Analysis (SRLR)

SLMCPR/

GE14 Transition LCR 6/03 02/04 15 I

I

PSEG Auclear LLCTechnical Quality Assurance Industry proven project management approach Integrated team Work to the schedule Regular communications Expeditious RAI resolutions Industry benchmarking/OE

  • Independent verification
  • Vendor quality assessments

Nuclear LLC Open Discussion

  • Comments
  • Questions and Answers 17