April 2003 Monthly Operating Report for Susquehanna Units 1 & 2
ML031480537
Person / Time
Site: Susquehanna  Talen Energy icon.png
Issue date: 05/15/2003
From: Richard Anderson
Susquehanna
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
PLA-005626, R41-2A
Download: ML031480537 (7)


Text

Richard L. Anderson Vice President - Nuclear Operations PPL Susquehanna, LLC 769 Salem /Boulevard Berwick, PA 18603 Tel. 570.542.3883 Fax 570.542.1504 RLAnderson@pplweb.com I

I pp*

- u r n -

I, P. 4% :I TM May 15, 2003 U. S. Nuclear Regulatory Commission Attn: Document Control Desk Mail Station OP1-17 Washington, D.C. 20555 SUSQUEHANNA STEAM ELECTRIC STATION MONTHLY OPERATING REPORTS Docket Nos. 50-387/NPF-14 and 50-388/NPF-22 PLA-005626 R41-2A The April 2003 Monthly Operating Reports for Susquehanna SES Units 1 and 2 are attached.

Very truly yours, Richard L. Anderson JJHI/cmm cc: NRC Region 1 NRC Sr. Resident Inspector, Mr. S. Hansell NRC Project Manager, Mr. R V. Guzman

/'

o.

OPERATING DATA REPORT DOCKET NO.

UNIT DATE COMPLETED BY TELEPHONE 50-387 One 05/15/2003 J. J. Hennings (570) 542-3747 OPERATING STATUS

1. Unit Name:

Susquehanna Steam Electric Station (U 1)

2.

Reporting Period:

April 2003

3.

Design Electrical Rating (Net MWe):

1115

4.

Maximum Dependable Capacity (Net MWe):

1105

5.

Hours in Reporting Period

6.

Number of Hours Reactor Was Critical

7.

Hours Generator On-Line

8.

Unit Reserve Shutdown Hours

9.

Net Electrical Energy Generated (MWH)

This Month 719 719 719 0

800,613 NOTES:

Page 1 of 1 Yr.-to-Date 2879 2879 2879 0

3,185,797 Cumulative 74,408 144,743.5 142,532.8 0

146,439,326

UNIT SHUTDOWNS DOCKET NO.

UNIT DATE COMPLETED BY TELEPHONE 50-387 One 05/15/03 J. J. Hennings (570) 542-3747 REPORT MONTH April 2003 No.

Date Type Duration Reason Method of Cause & Corrective Action I

(Hours) 2 Shutting To Prevent Recurrence Down Reactor 3 No Shutdowns this month.

ISummary: No significant power reductions were performed during April.

2.

Reason:

A - Equipment Failure (Explain)

B - Maintenance or Test C - Refueling D - Regulatory Restriction E - Operator Training & Licensee Exam F - Administrative G - Operational Error (Explain) 3.

Method:

1 - Manual 2 - Manual Scram 3 - Automatic Scram 4 - Continuation from previous month 5 - Other 1.

F. Forced S. Scheduled Page 1 of 1

SUSQUEHANNA STEAM ELECTRIC STATION Docket Number:

50-387 Date:

5115/03 Completed by: J. J. Hennings Telephone:

(570) 542-3747 Challenzes to Main Steam Safety Relief Valves None.

1S.

OPERATING DATA REPORT DOCKET NO.

UNIT DATE COMPLETED BY TELEPHONE 50-388 Two 05/15/03 J. J. Hennings (570) 542-3747 OPERATING STATUS

1. Unit Name:

Susquehanna Steam El

2.

Reporting Period:

April 2003

3.

Design Electrical Rating (Net MWe):

4.

Maximum Dependable Capacity (Net MWe):

lctric Station (U2) 1117*

1111*

5.

Hours in Reporting Period

6.

Number of Hours Reactor Was Critical

7.

Hours Generator On-Line

8.

Unit Reserve Shutdown Hours

9.

Net Electrical Energy Generated (MWH)

This Month 719 280.8 236.92 0

224,793 Yr.-to-Date 2,879 1,865.4 1820.9 0

1,897,817 Cumulative 159,648 138,014.8 136,027.6 0

142,008,811 NOTES:

During the U2 1 1 Refueling Outage, the Main Turbine was replaced with a newly designed HP and three LP turbines. The Design Rating and Maximum Dependable Capacity Rating will change following the completion of the official Performance/Acceptance Test in early June.

Page 1 of 1

UNIT SHUTDOWNS DOCKET NO.

UNIT DATE COMPLETED BY TELEPHONE 50-388 Two 05/15/03 J. J. Hennings (570) 542-3747 REPORT MONTH Anril 2003 Summary: The reactor mode switch was placed in startup on 4/19103. The Unit 2 Cycle 11 Refueling Outage ended on 1 4/21/03 and reactor power reached 100% on 4/24/03. No other significant power changes occurred in April.

2.

3.

Reason:

A - Equipment Failure (Explain)

B - Maintenance or Test C - Refueling D - Regulatory Restriction E - Operator Training & Licensee Exam F - Administrative G - Operational Error (Explain)

Method:

1 - Manual 2 - Manual Scram 3 - Automatic Scram 4 - Continuation from previous month 5 - Other No.

Date Type Duration Reason Method of Cause & Corrective Action I

(Hours) 2 Shutting to Prevent Recurrence Down Reactor 3

1 3/8/03 S

1058 C

4 Continued planned Refueling ouitage that began on 3/8/03.

1.

F. Forced S. Scheduled Page of I

SUSOUEHANNA STEAM ELECTRIC STATION Docket Number:

50-388 Date- -.05/15103 Completed by:

J. J. Hennings Telephone:

(570) 542-3747 Challenges to Main Steam Safety Relief Valves None.