Tennessee Valley Authority, Post Office Box 2000, Decatur, Alabama 35609-2000 May 13, 2003 U.S. Nuclear Regulatory Commission ATTN:
Document Control Desk Mail Stop:
OWFN, Pl-35 Washington, D.C. 20555-0001 Gentlemen:
Docket Nos.
In the Matter of Tennessee Valley Authority 50-259 50-260 50-2 96 BROWNS FERRY NUCLEAR PLANT (BFN) -
APRIL 2003 MONTHLY OPERATING REPORT The enclosure provides the April 2003 Monthly Operating Report (MOR) as required by BFN Technical Specifications, Section 5.6.4.
If you have any questions concerning this report, please call me at (256) 729-2636.
.. 1 D.
Z 1
U Lv v
Managert -I-censi-g-
-ndIndustry Affai s Enclosure cc:
See page 2 Pnnt.d on -ocyded paper 4
)
U.S. Nuclear Regulatory Commission Page 2 May 13, 2003 Enclosure cc (Enclosure):
(Via NRC Electronic Distribution)
Mr. Kahtan N. Jabbour, Senior Project Manager U.S. Nuclear Regulatory Commission One White Flint, North (MS 08G9)
Office of Nuclear Reactor Regulation 11555 Rockville Pike Rockville, Maryland 20852-2738 NRC Resident Inspector Browns Ferry Nuclear Plant 10833 Shaw Road Athens, Alabama 35611-6970 Regional Administrator U.S. Nuclear Regulatory Commission Region II Sam Nunn Atlanta Federal Center 61 Forsyth Street, S.W., Suite 23T85 Atlanta, Georgia 30303-8931
ENCLOSURE TENNESSEE VALLEY AUTHORITY BROWNS FERRY NUCLEAR PLANT (BFN)
MONTHLY OPERATING REPORT APRIL 2003 UNIT 1 DOCKET NUMBER 50-259 LICENSE NUMBER DPR-33 UNIT 2 DOCKET NUMBER 50-260 LICENSE NUMBER DPR-52 UNIT 3 DOCKET NUMBER 50-296 LICENSE NUMBER DPR-68
OPERATING DATA REPORT Docket No.
50-259 Unit Name BFN Unit I Date May 4, 2003 Completed By J. E. Wallace Telephone (256) 729-7874 Reporting Period April 2003
- 1. Design Electrical Rating (Net MWe):
- 2.
Maximum Dependable Capacity (MWe-Net)
- 3.
Number of Hours Reactor was Critical
- 4.
Hours Generator On-Line
- 5.
Unit Reserve Shutdown Hours
- 6.
Net Electrical Energy Generated (MWh)
Month Yr-to-Date Cumulative*
0 0
59521 0
0 58267 o
o 0
0 0
53,796,427
- Excludes hours under Administration Hold (June 1, 1985 to Present)
OPERATING DATA REPORT Docket No.
50-260 Unit Name BFN Unit 2 Date May 4, 2003 Completed By J. E. Wallace Telephone (256) 729-7874 Reporting Period April 2003
- 1. Design Electrical Rating (Net MWe):
- 2.
Maximum Dependable Capacity (MWe-Net) 1120 1118 Yr-to-Date Cumulative
- 3.
Number of Hours Reactor was Critical
- 4.
Hours Generator On-Line
- 5.
Unit Reserve Shutdown Hours
- 6.
Net Electrical Energy Generated (MWh) 719 2293 150,700 719 2265 148,027 0
0 0
773,535 2,108,104 147,260,831 E-2 1065 0
Month
OPERATING DATA REPORT Docket No.
50-296 Unit Name BFN Unit 3 Date May 4, 2003 Completed By J. E. Wallace Telephone (256) 729-7874 Reporting Period April 2003
- 1. Design Electrical Rating (Net MWe):
- 2.
Maximum Dependable Capacity (MWe-Net)
- 3.
Number of Hours Reactor was Critical
- 4.
Hours Generator On-Line
- 5.
Unit Reserve Shutdown Hours
- 6.
Net Electrical Energy Generated (MWh)
Month Yr-to-Date Cumulative 719 2879 108,127 719 2879 106,703 0
0 0
811,956 3,164,646 109,147,517 E-3 1120 1118
UNIT SHUTDOWNS REPORT MONTH: APRIL 2003 DOCKET NO:
UNIT NAME:
DATE:
COMPLETED BY:
TELEPHONE:
50-259 BFN-1 May 4, 2003 J. E. Wallace (256) 729-7874 Administrative iioi to resoive various I VA ana NKtl concerns.
1Rason:
A-Equipment Failure (Explain)
B-Maintenance or Test C-Refueling D-Regulatory Restriction E-Operator Training and License Examination F-Administrative G-Operational Error (Explain)
H-Other (Explain) 2Method 1-Manual 2-Manual Scram 3-Automatic Scram 4-Continuation of Existing Outage 5-Reduction 9-Other
SUMMARY
Unit 1 has been on administrative hold since June 1, 1985.
E-4 1
6/01/85 S
719 4
UNIT SHUTDOWNS REPORT MONTH: APRIL 2003 DOCKET NO:
UNIT NAME:
DATE:
COMPLETED BY:
50-260 BFN-2 May 4, 2003 J. E. Wallace
{94\\7')O-7Q7A N/A I1
' Reason:
A-Equipment Failure (Explain)
B-Maintenance or Test C-Refueling D-Regulatory Restriction E-Operator Training and License Examination F-Administrative G-Operational Error (Explain)
H-Other (Explain) 2 Method I-Manual 2-Manual Scram 3-Automatic Scram 4-Continuation of Existing Outage 5-Reduction 9-Other SUMM4ARY:
Unit 2 has operated at or near 100 percent available power with no significant power reductions.
E-5
,I UNIT SHUTDOWNS REPORT MONTH: APRIL 2003 DOCKET NO:
UNIT NAME:
DATE:
COMPLETED BY:
TF.T EP-TOWN 50-296 BFN-3 May 4, 2003 J. E. Wallace (256) 729-7874 N/A I ____________
L I
iReason:
A-Equipment Failure (Explain)
B-Maintenance or Test C-Refueling D-Regulatory Restriction E-Operator Training and License Examination F-Administrative G-Operational Error (Explain)
H-Other (Explain) 2 Method I-Manual 2-Manual Scram 3-Automatic Scram 4-Continuation of Existing Outage 5-Reduction 9-Other
SUMMARY
Unit 3 has operated at or near 100 percent available power.
E-6