April 2003 Monthly Operating Report for R.E. Ginna Nuclear Power Plant
ML031400677
Person / Time
Site: Ginna Constellation icon.png
Issue date: 05/09/2003
From: Widay J
Rochester Gas & Electric Corp
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
Download: ML031400677 (3)


Text

An Energy East Company ROCHESTER GAS AND ELECTRIC CORPORATION 89 EASTAVENUE, ROCHESTER, N.Y 14649-0001

  • 585 546-2700 www.rge.com May 9, 2003 US Nuclear Regulatory Commission Document Control Desk Attn:

Robert Clark Project Directorate 1-1 Washington, DC 20555

Subject:

Monthly Report for April 2003 Operating Status Information R.E. Ginna Nuclear Power Plant Docket No. 50-244

Dear Mr. Clark:

Pursuant to Ginna Improved Technical Specifications Section 5.6.4, attached is the monthly operating status report for Ginna Station for the month of April 2003.

Very truly yours, J seph A. Widay Plant Manager xc:

U.S. Nuclear Regulatory Commission Mr. Robert Clark (Mail Stop O-8E9)

Project Directorate 1-1 Washington, D.C. 20555 U.S. Nuclear Regulatory Commission Region I 475 Allendale Road King of Prussia, PA 19406 U.S. NRC Ginna Senior Resident Inspector Attachments

OPERATING DATA REPORT 50-244 May 10, 2003 COMPLETED BY:

1$0& _

John V. Walden TELEPHONE (585) 771-3588 OPERATING STATUS

1. Unit Name:

R.E. GINNA NUCLEAR

2. Reporting Period:

April, 2003

3. Design Electric Rating (Net MWe):
4. Maximum Dependable Capacity (Net MWe):

POWER PLANT 470 480 This Month

- Yr.-to-Date Cumulative**

5. Number of hours Reactor Was Critical
6. Hours Generator On-line
7. Unit Reserve Shutdown Hours
8. Net Electrical Energy Generated (MWH) 719.0 719.0 0.0 357063.0 2879.0 2868.1 0.0 1417761.4 241895.9 238727.2 8.5
  • 108746670.4 N
  • CUMULATIVE TOTAL COMMENCING NOVEMBER 8,1969 Notes:

r

DOCKET NO: 50-244 UNIT NAME: R.E. GINNA NUCLEAR POWER PLANT DATE: May 9, 2003 COMPLETED BY: John V. Walden

-- TELEPHONE: (585) 771-3588 UNIT SHUTDOWN REPORTING PERIOD:

April 2003 (MonthNear)

SUMMARY

The unit operated at full power for the entire of the month of April. Average power for the month of April was 99.7%.

(1) Reason A - Equipment Failure (Explain)

B - Maintenance or Test C - Refueling D - Regulatory Restriction E - Operator Training/License Examination F-Administrative G - Operational Error (Explain)

H - Other (Explain)

(2) Method 1 - Manual 2 - Manual Trip/Scram 3 - Automatic Trip/Scram 4 - Continuation 5 -Other (Explain)

NO.

DATE TYPE DURATION REASON(')

METHOD OF CAUSE/CORRECTIVE ACTIONS F: FORCED (HOURS)

SHUTTING S: SCHEDULED DOWN 2)

COMMENTS