Kevin J. Nietmann Plant General Manager Calvert Cliffs Nuclear Power Plant Constellation Generation Group, LLC 1650 Calvert Cliffs Parkway Lusby, Maryland 20657 410 495-4101 410 495-4787 Fax Constellation Energy Group May 15, 2003 U. S. Nuclear Regulatory Commission Washington, DC 20555 ATTENTION:
SUBJECT:
Document Control Desk Calvert Cliffs Nuclear Power Plant Unit Nos. 1 & 2; Docket Nos. 50-317 & 50-318 April 2003 Operating Data Reports The subject reports are being sent to you as required by Technical Specification 5.6.4.
Should you have questions, please contact Mr. Thomas S. O'Meara at (410) 495-6940.
Very truly yours, X~/
KJN/CAN/bjd Attachments cc:
J. Petro, Esquire J. E. Silberg, Esquire Director, Project Directorate I-1, NRC G. S. Vissing, NRC H. J. Miller, NRC Resident Inspector, NRC R. I. McLean, DNR J. Wright, INPO K. N. Larson, ANI
tf c-IP
OPERATING DATA REPORT Docket No. 50-317 Calvert Cliffs Unit 1 May 2, 2003 Prepared by Herman 0. Olsen Telephone:(410)495-6734 REPORTING PERIOD DESIGN ELECTRICAL RATING (NET MWe)
MAXIMUM DEPENDABLE CAP'Y (NET MWe)
APRIL 2003 845 825
- This month
- 1. NUMBER OF HOURS REACTOR WAS CRITICAL
- 2. HOURS GENERATOR ON LINE
- 3. UNIT RESERVE SHUTDOWN HOURS
- 4. NET ELECTRICAL ENERGY GENERATED(MWH) 719.0 719. 0
- 0. 0 624,199 Year-to-Date 2,879.0 2,879.0 0.0 2,502,975 Cumulative to Date 186,168.4 183,004.7 0.0 149,670,238
UNIT SHUTDOWNS DOCKET NO.
50-317 UNIT NAME Calvert Cliffs - Ul DATE May 2, 2003 COMPLETED BY Herman 0. Olsen TELEPHONE (410) 495-6734 REPORTING MONTH April 2003 l Reason:
A - Equipment Failure B - Maintenance or Test C - Refueling D - Regulatory Restriction E - Operator Training & License Examination F - Administrative G - Operational Error H - Other 2 Method:
I - Manual 2 - Manual Scram.
3 - Automatic Scram.
4 - Continued 5 - Other NO.
DATE TYPE DURATION REASON' METHOD OF CAUSE/CORRECTIVE ACTIONS F:
FORCED (HOURS)
SHUTTING S:
SCHEDULED DOWN 2 COMMENTS There were no shutdowns this month. I I~~~~~~~~~~
DOCKET NO. 50-317 CALVERT CLIFFS - UNIT 1 May 2, 2003
SUMMARY
OF OPERATING EXPERIENCE April 2003 The unit operated at 100% power for the entire month.
OPERATING DATA REPORT Docket No. 50-318 Calvert Cliffs Unit 2 May 2, 2003 Prepared by Herman 0. Olsen Telephone:(410)495-6734 REPORTING PERIOD DESIGN ELECTRICAL RATING (NET MWe)
MAXIMUM DEPENDABLE CAP'Y (NET MWe)
APRIL 2003 845 835
- This month
- 1. NUMBER OF HOURS REACTOR WAS CRITICAL
- 2. HOURS GENERATOR ON LINE
- 3. UNIT RESERVE SHUTDOWN HOURS
- 4. NET ELECTRICAL ENERGY GENERATED(MWH)
Year-Cumulative to-Date to Date 233.7 1,313.1 178,872.9 204.8 1,284.0 176,988.7 0.0 160,285 0.0 1,093,882
- 0. 0 145,680,312
DOCKET NO.
UNIT NAME DATE COMPLETED BY TELEPHONE 50-318 Calvert Cliffs-U2 May 2, 2003 Herman 0. Olsen (410) 495-6734 REPORT MONTH April 2003 Reason:
A - Equipment Failure B - Maintenance or Test C - Refueling D - Regulatory Restriction E - Operator Training & License Examination F - Administrative G - Operational Error H - Other 2 Method:
I - Manual 2 - Manual Scram.
3 - Automatic Scram.
4 - Continued 5 - Other UNIT SHUTDOWNS NO.
DATE TYPE DURATION REASON' METHOD OF CAUSE/CORRECTIVE ACTIONS F:
FORCED (HOURS)
SHUTTING S:
SCHEDULED DOWN 2 COMMENTS03-001 030214 S
515.2 C
1 The unit was defueled in a planned refueling outage at the beginning of the month. Refueling was completed and the outage ended on 04/22/03 at Ill lwhen the unit was paralleled to the grid.
Jt
DOCKET NO. 50-318 CALVERT CLIFFS - UNIT 2 May 2, 2003
SUMMARY
OF OPERATING EXPERIENCE April 2003 The unit began the month defueled in a planned refueling outage.
The following significant work was completed or in progress during the month:
Steam Generator replacement.
Main Transformer replacement.
Refueling.
Physics testing.
The unit was heated up and taken critical on 04/21/03 at 0620. Power was increased and the unit was paralleled to the grid on 04/22/03 at 1111.
The unit reached 100% power on 04/25/03 at 1630 and continued to operate at 100% power for the remainder of the month.