ML030980434

From kanterella
Jump to navigation Jump to search
Letter to A. Marion from B. Sheron PWR Materials Reliability Project Interim Alloy 600 Safety Assessment for U.S. PWR Plants (MRP-44), Part 1: Alloy 82/182 Pipe Butt Welds
ML030980434
Person / Time
Issue date: 04/22/2003
From: Sheron B
NRC/NRR/ADPT
To: Marion A
Nuclear Energy Institute
Wichman K, EMCB/DE, 415-2785
References
Download: ML030980434 (4)


Text

April 22, 2003 Mr. Alex Marion, Director of Engineering Nuclear Energy Institute 1776 I Street, N.W., Suite 400 Washington, D.C. 20006-3708

SUBJECT:

PRESSURIZED-WATER REACTOR (PWR) MATERIALS RELIABILITY PROJECT INTERIM ALLOY 600 SAFETY ASSESSMENT FOR U.S. PWR PLANTS (MRP-44), PART 1: ALLOY 82/182 PIPE BUTT WELDS

Dear Mr. Marion:

By letter dated April 27, 2001, the Nuclear Energy Institute (NEI), as the regulatory interface for the Electric Power Research Institute (EPRI) Materials Reliability Project (MRP) submitted the proprietary (TP-1001491, Part 1) and non-proprietary (TP-1001491-NP, Part 1) versions of the EPRI report, PWR Materials Reliability Project Interim Alloy 600 Safety Assessment for U.S.

PWR Plants (MRP-44), Part 1: Alloy 82/182 Pipe Butt Welds, for staff information.

The U.S. Nuclear Regulatory Commission (NRC) staff reviewed this report and transmitted its findings in my letter to you dated June 14, 2001. In addition, the enclosure to the letter contained a discussion of the issues that the final report should address. That discussion and the issues that were identified, still remain the focus of the staffs concerns. The report contained a number of main conclusions many of which the staff accepted pending further information. Of particular note, one of the reports conclusions is, There is no concern with boric acid corrosion as a result of the relatively low leakage rates from the [primary water stress-corrosion cracking] PWSCC cracks and the high temperatures of the components.

Knowledge gained from leakage events subsequent to the submittal of this report has proven that conclusion to be invalid. We expect that the information gained since April 27, 2001,will be considered in a reevaluation of the reports conclusions.

I recognize that after the submittal of this report, industry worked to improve their nondestructive examination capabilities with respect to examining large bore Alloy 82/182 butt welds and both industry and staff resources have been diverted to addressing the safety significant issues resulting from PWR upper head penetration cracking. Reflective of the PWR upper head penetration cracking issues, three NRC Bulletins and an NRC Order were issued by the staff and the MRP, on behalf of the industry, authored numerous reports and participated in many technical meetings on this problem. At this point, however, it is important to finalize report MRP-44, Part 1 to address resolution of the issues related to potential PWSCC of Alloy 82/182 pipe butt welds. This will allow a comprehensive reevaluation of priorities so that available resources can be appropriately allocated.

A. Marion 2 In response to this letter, I would appreciate if you could please identify the schedule for submission of the final report for staff review. If you have any questions regarding this letter, please contact Dr. Richard Barrett of my staff on (301) 415-3298.

Sincerely,

/RA/

Brian W. Sheron, Associate Director for Project Licensing & Technical Analysis Office of Nuclear Reactor Regulation cc: See next page

A. Marion 2 In response to this letter, I would appreciate if you could please identify the schedule for submission of the final report for staff review. If you have any questions regarding this letter, please contact Dr. Richard Barrett of my staff on (301) 415-3298.

Sincerely,

/RA/

Brian W. Sheron, Associate Director for Project Licensing & Technical Analysis Office of Nuclear Reactor Regulation cc: See next page Distribution:

EMCB R/F WDTravers JAZwolinski MEMayfield WDLanning, R1 SDuraiswamy WFKane SBlack NCChokshi CCasto, R2 JLarkins SJCollins DBMatthews AHiser CPederson, R3 BWSheron AThadani BABoger PCWen DChamberlain, R4 TChan SBloom WCullen Accession No.: ML030980434 OFFICE EMCB:DE EMCB:DE D:DE D:ADPT NAME K Wichman W Bateman R Barrett B Sheron DATE 4 / 8 / 03 4 / 9 / 03 4 / 10 / 03 4 / 22 / 03 OFFICIAL RECORD COPY

cc:

Marvin Fertel, Senior Vice President Leslie Hartz, Chair, MRP and Chief Nuclear Officer Vice President - Nuclear Engineering Nuclear Energy Institute Dominion Energy Suite 400 5000 Dominion Blvd.

1776 I Street, NW Glan Allen, VA 23060 Washington, DC 20006-3708 Larry Mathews, MRP Craig Harrington, Technical Chair Southern Nuclear Operating Company RPV Head Working Group Manager, Inspection and Testing Services TXU Corporation P. O. Box 1295 Comanche Peak Plant Birmingham, AL 35201 PO Box 1002 Glan Rose, TA 76043 - 1002 Frank Ammirato, EPRI C. Thomas Alley, Jr., Technical Chair Inspection Manager Inspection Working Group EPRI NDE Center Duke Power Company P. O. Box 217097 Nuclear General Office 1300 W. T. Harris Blvd. 526 South Church Street Charlotte, NC 28221 Mail Code EC09O PO Box 1006 Charlotte NC 28201 David Steininger, EPRI MRP Manager John Wilson, Technical Chair Chuck Welty, EPRI MRP Manager Repair/Mitigation Working Group Christine King, EPRI MRP Manager Exelon Corporation Electric Power Research Institute Cornerstone II at Cantera P. O. Box 10412 4300 Winfield Ave.

3412 Hillview Ave. Warrenville, IL 60555 - 4012 Palo Alto, CA 94303