Tennessee Valley Authority, 1101 Market Street, Chattanooga, Tennessee 37402-2801 March 20, 2003 Mr. Frank Congel, Director Office of Enforcement U.S. Nuclear Regulatory Commission One White Flint North 11555 Rockville Pike Rockville, Maryland 20852-2739

Dear Mr. Congel:

In the Matter of ) Docket Nos. 50-390 Tennessee Valley Authority )

WATTS BAR NUCLEAR PLANT - PAYMENT OF CIVIL PENALTY - ENFORCEMENT ACTION EA-98-327 This letter responds to Bruce J. Mallett's letter to John A. Scalice dated October 15, 2001 that transmitted the subject Notice of Violation and Civil Penalty.

Payment of the proposed civil penalty in the amount of $88,000 has been made by electronic fund transfer No. 9000119400.

If you have any questions regarding this response, please contact me at (423) 751-2508.

Sincerely, urzynski "

Manager Nuclear Licensing cc: See page 2 Printed on recycled paper

Mr. Frank Congel Page 2 March 20, 2003 cc: Mr. K. N. Jabbour, Senior Project Manager U.S. Nuclear Regulatory Commission MS 09G9 One White Flint, North 11555 Rockville Pike Rockville, Maryland 20852-2739 U.S. Nuclear Regulatory Commission Region II Sam Nunn Atlanta Federal Center 61 Forsyth St., SW, Suite 23T85 Atlanta, Georgia 30303-8931 NRC Senior Resident Inspector Watts Bar Nuclear Plant 1260 Nuclear Plant Road Spring City, Tennessee 37381

Tennessee Valley Authority, 1101 Market Street, Chattanooga, Tennessee 37402-2801 March 20, 2003 U.S. Nuclear Regulatory Commission ATTN: Chief, Emergency Preparedness Section Region II Sam Nunn Atlanta Federal Center 61 Forsyth Street, SW, Suite 23T85 Atlanta, Georgia 30303-8931 Gentlemen:

In the Matter of ) Docket Nos. 50-259 Tennessee Valley Authority ) 50-260 50-296 BROWNS FERRY NUCLEAR PLANT (BFN) - UNITS 1, 2, AND 3 - GOALS AND OBJECTIVES FOR THE JUNE 2003 RADIOLOGICAL EMERGENCY PLAN (REP) EXERCISE Enclosed are TVA's goals and objectives for the June 2003 BFN REP exercise. These goals and objectives are being submitted in accordance with a July 22, 1994 NRC letter which specified the objectives be submitted seventy-five days prior to the exercise. The BFN REP exercise is currently scheduled for the week of June 2, 2003.

If you have any questions, please telephone Susan Ferrell at (423) 751-7737.

Sincerely, ark. Burzynski Manager Nuclear Licensing Enclosure cc: See page 2 Pnnted on recycled paper

U.S. Nuclear Regulatory Commission Page 2 March 20, 2003 cc: /Mr. K. N. Jabbour, Senior Project Manager U.S. Nuclear Regulatory Commission MS 08 G9 One White Flint North 11555 Rockville Pike Rockville, Maryland 20852-2739 NRC Resident Inspector Browns Ferry Nuclear Plant 10833 Shaw Road Athens, Alabama 35611