Updated List of Procedures for AFW Issue as of 11/01/2002
ML030800211
Person / Time
Site: Point Beach  NextEra Energy icon.png
Issue date: 11/01/2002
From: Sokol K
Nuclear Management Co
To: Schoon D
- No Known Affiliation, Office of Nuclear Reactor Regulation
References
FOIA/PA-2003-0094
Download: ML030800211 (2)


Text

.,4 To: Duane Schoon Procedure that are being changed via Temp Change Process to address the AFW recirc orifice issue.

Procedure # Applicable unit EOP 0 1 &2 EOP 0.0 1 &2 EOP 0.1 1 &2 EOP 0.2 1 &2 EOP 0.3 1 &2 EOP 0.4 1 &2 EOP 1.0 1 &2 EOP 1.1 1 &2 EOP 1.2 1 &2 EOP 1.3 1 &2 EOP 1.4 EOP 2 1 &2 1 &2 Lke SyAr6O EOP 3 1 &2 EOP 3.1 EOP 3.2 1&2 1 &2 LU T EOP 3.3 1 &2 ECA 0.0 1 &2 ECA0.1 1&2 ECA 0.2 1 &2 ECA 1.1 1 &2 ECA 1.2 1 &2 ECA 2.1 1 &2 ECA 3.1 1 &2 ECS 3.2 1 &2 ECA 3.3 1 &2 CSP S.1 1 &2 CSP S.2 1 &2 jw5 CSP C.1 1 &2 CSP C.2 1 &2 CSP C.3 1 &2 CSP H.5 1 &2 CSP H.2 1 &2 CSP H.3 1 &2 CSP H.4 1 &2 CSP H.5 1 &2 CSP P.1 1 &2 CSP P.2 1 &2 3

CSP Z.1 1 &2 CSP Z.2 1 &2 CSP Z.3 1 &2 CSP I.1 I &2 CSP 1.2 1 &2 CSP 1.3 1 &2 SEP 2.1 1 &2 SEP 2.2 1 &2 SEP 3.0 1 &2 AOP 3.0 1 &2 AOP 10 Common to both units AOP 1OA Common to both units AOP 23 1 &2 01 62A Common to both units 01 62B Common to both units Total procedures being changed = 100 procedures Ken Sokol 10/30/2002 11/1/2002 update The original count of procedures was off by 2 because I had listed CSP H.3 twice in this list. that has been corrected.

Additional procedures that we are revising are AOP 10B 1 &2 IT 8A 1 IT9A 2 IT 10 common IT I1A common IT 1OB common Ken Sokol 1111/2002