NMC Preliminary Event Timeline
ML030790354
Person / Time
Site: Point Beach  NextEra Energy icon.png
Issue date: 10/23/2002
From:
Nuclear Management Co
To:
Office of Nuclear Reactor Regulation
References
FOIA/PA-2003-0094
Download: ML030790354 (13)


Text

PRELIMINARY 2

EVENT TIMELINE 10/23/02 S0400

- P-38A OOS for scheduled maintenance - TSAC entered SDay Shift - Maintenance performed on P 38A AFW Pump m AF-38 valve replacement n AF-4012-O diaphragm change

  • P-38A seal replacement m ICP 6.086 flow calibration Committed to Nuclear Excellence B

EVENT TIMELINE 10/24/02 S0110

- Commenced IT-10 S0159

- Started P-38A S0212

- Secured P-38A

  • Indicated flow was 64.5 gpm

"* Acceptance criteria was 70 gpm S0215-0500

- I&C contacted and flow transmitter was revented and recalibrated; ran P-38A and flow still only 65 gpm Committed to Nuclear Excellence 2

.M EVENT TIMELINE 10/24/02 0323 - CAP029908 initiated on inadequate recirculation flow

> 0400 - Engineering contacted; Operations informed pump is OK and investigation will begin

> 0500-0700 - Engineering postulated potential failure modes

> 0630 - BOP/NSSS Engineering Supervisor designated lead for issue NuMClrce Committed to Nuclear Excellence 3

EVENT TIMELINE 10/24/02 0830 - Meeting with Engineering, Maintenance, Shift Manger m Action plan established to investigate S1030

- Installed UT flow meter on recirc line and ran P-38A; installed FE indicates 65 gpm and UT indicates 60 gpm S1100-1300 - RO disassembled and found to have rust-like particles blocking some orifice holes (24 of 54 outer holes had

, some degree of blockage)

Committed to Nuclear Excellenc 4

P

EVENT TIMELINE 10/24/02 1100-1300 cont. - Boroscope inspection of upstream piping shows no evidence of FME S1700

- 50.59 screening completed for temp change to IT-10 acceptance criteria S1830 Meeting with Shift Manager, Maintenance, and Engineering to review plans Committed to Nuclear Excetlence 5

liiu

EVENT TIMELINE 10/24/02 S>2115-2117

- Ran P-38A per OI-62A m Flow was 75 gpm

  • Evening - CST/AFW samples normal Nucl Committed to Nuclear Excellencr 6

I

EVENT TIMELINE 10/25/02

  • 0008-0050 - Ran P-38A per IT-10
  • 0155 - Commenced IT-10C for P-38A
  • 0216 - P-38A RTS and TSAC exitied
  • 0300-1255 - Additional tests run on other AFW pumps; all SAT

> 1030 - ACE initiated to evaluate inadequate flow

  • 1600- Operations requests short term action plan from Engineering by 11/1 NMcr Committed to Nuclear Excellence 7

EVENT TIMELINE 10/28102 1100 - Engineering held meeting to brainstorm problem

"* What is material

"* Origin, of material

"* Pump tolerances

"* SW strainer size

"* Need for OD for SW issue

"* Previous silt study

"* Obtain details of RO Afternoon - Operations and Engineering Committed to Nuclear Excellenc$ management briefed on issue 8

EVENT TIMELINE 10/29/02

> 0900 - Meeting with Engineering Director

"* Conclude system operation would be adversely affected by SW plugging RO

"* Licensing and Operations briefed

> 0945 - Management Meeting identified immediate actions to be taken

"* Crew briefings

"* NRC notifications

.* Procedure changes (102)

NMC-r-C9 Commf oo Nuclea,.r*

Exelnc Temporary information tags 9

EVENT TIMELINE 10/29/02 S1027

- Declared all 4 AFW pumps OOS S1110

- Crew briefed on AFW recirc flow issue S1210

- Posted temporary information tags for all 4 AFW pumps Secure pumps if rmn flow not maintained S1241

- CAP029952 initiated on potential common mode failure of AFW recirc lines S1305

- All 4 AFW pumps RTS based on NMC compensatory measures taken Committed to Nuclear Excellene 10 r s

EVENT TIMELINE 10/29/02 me NMCl Commire'ed to Nucle E*cefence 1410 - Engineering Director forms RCE Team

"* RCE expertise

"* AFW System Engineer

"* KNPP Design Engineer S1525

- Need for OD discussed between Engineering and Operations S1530-1630

- Simulator runs performed to evaluate effect of compensatory measures on risk lp 11

EVENT TIMELINE 10/29/02

  • 1711 - NRC 8 hour9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> notification made

> 1830 - Operations request an operability determination for CAP029952

)-2030 - Safety Monitor transitions to Yellow based on PRA Group input NMcc1 Committed to Nuclear Excellence*

12

r EVENT TIMELINE 10/30/02

> 0700 - Initial RCE Team Meeting S1030

- Qualifications suspended for 3 individuals

> 1100- Notified on NRC Special inspection

> 1250 - RCE Charter Approved

> 1850- Operability Determination approved and accepted by Operations Committed to Nuclear Excellence 13