February 2003 Monthly Operating Report for R.E. Ginna Nuclear Power Plant
ML030770454
Person / Time
Site: Ginna Constellation icon.png
Issue date: 03/10/2003
From: Widay J
Rochester Gas & Electric Corp
To: Clark R
Document Control Desk, NRC/NRR/DLPM/LPD1
References
Download: ML030770454 (3)


Text

R-"An Energy East Company ROCHESTER GAS AND ELECTRIC CORPORATION

  • 89 EAST AVENUE, ROCHESTER, N.Y 14649-0001
  • 585 546-2700 www rge corn March 10, 2003 US Nuclear Regulatory Commission Document Control Desk Attn:

Robert Clark Project Directorate I-1 Washington, DC 20555

Subject:

Monthly Report for February 2003 Operating Status Information R.E. Ginna Nuclear Power Plant Docket No. 50-244

Dear Mr. Clark:

Pursuant to Ginna Improved Technical Specifications Section 5.6.4, attached is the monthly operating status report for Ginna Station for the month of February 2003.

Very truly yours, 0

t.)

  • h A. Widayýýn Plant Manager xc:

U.S. Nuclear Regulatory Commission Mr. Robert Clark (Mail Stop O-8E9)

Project Directorate I-1 Washington, D.C. 20555 U.S. Nuclear Regulatory Commission Region I 475 Allendale Road King of Prussia, PA 19406 U.S. NRC Ginna Senior Resident Inspector Attachments

OPERATING DATA REPORT 50-244 March 10, 2003 COMPLETED BY:

/

John V. Walden TELEPHONE (585) 771-3588 OPERATING STATUS

1.
2.
3.

4.

Unit Name:

R.E. GINNA NUCLEAR POWER PLANT Reporting Period:

February, 2003 Design Electric Rating (Net MWe):

470 Maximum Dependable Capacity (Net MWe):

480 Notes:

Number of hours Reactor Was Critical Hours Generator On-line Unit Reserve Shutdown Hours Net Electrical Energy Generated (MWH)

This Month 672.0 672.0 0.0 333039.0 Yr.-to-Date 1416.0 1416.0 0.0 702195.0 Cumulative**

240432.9 237275.1 8.5

  • 108031104.0
  • CUMULATIVE TOTAL COMMENCING NOVEMBER 8,1969
5.
6.
7.

8.

"1' DOCKET NO: 50-244 UNIT NAME: R.E. GINNA NUCLEAR POWER PLANT DATE: March 10, 2003 COMPLETED BY: John V. Walden TELEPHONE: (585) 771-3588 UNIT SHUTDOWN REPORTING PERIOD:

February 2003 (Month/Year)

NO.

DATE TYPE DURATION REASONO 1 )

METHOD OF CAUSE/CORRECTIVE ACTIONS F: FORCED (HOURS)

SHUTTING

&: SCHEDULED DOWN(2)

COMMENTS The unit operated at full power for the entire month of February. Average power for the month of February was 99 8%

(1) Reason A - Equipment Failure (Explain)

B - Maintenance or Test C - Refueling D - Regulatory Restriction E - Operator Training/License Examination F - Administrative G - Operational Error (Explain)

H - Other (Explain)

(2) Method 1 - Manual 2 - Manual Trip/Scram 3 - Automatic Trip/Scram 4 - Continuation 5 - Other (Explain)

SUMMARY

-