March 14, 2003 Gregory M. Rueger, Senior Vice President, Generation and Chief Nuclear Officer Pacific Gas and Electric Company Diablo Canyon Power Plant P.O. Box 3 Avila Beach, California 93424

SUBJECT:

DIABLO CANYON POWER PLANT - NOTIFICATION OF NRC INITIAL OPERATOR LICENSING EXAMINATION NOTIFICATION (EXAMINATION REPORT 50-275;323/03-301)

In a telephone conversation on March 13, 2003, between Mr. David Burns, Lead, Operator Training and Mr. Anthony T. Gody, Chief, Operations Branch, arrangements were made for the administration of a retake licensing examination at the Diablo Canyon Nuclear Power Plant on May 8, 2003.

As agreed during the telephone conversation, your staff will prepare the examinations based on the guidelines in Revision 8, Supplement 1, of NUREG-1021, "Operator Licensing Examination Standards for Power Reactors." The NRC regional office will discuss with your staff any changes that might be necessary before the examinations are administered. In addition, your support for onsite validation of the examinations may be required during the week of April 28, 2003.

To meet the above schedule, it will be necessary for your staff to furnish the applicable operating tests and the supporting reference materials identified in Attachment 2 of ES-201 and as specified by the chief examiner will be due by April 1, 2003. Pursuant to 10 CFR 55.40(b)(3), an authorized representative of the facility licensee shall approve the tests before they are submitted to the NRC for review and approval. All materials shall be complete and ready-to-use. Any delay in receiving the required reference materials, or the submittal of inadequate or incomplete materials, may cause the examinations to be rescheduled.

In order to conduct the requested operating tests, it will be necessary for your staff to provide adequate space and accommodations in accordance with ES-402, and to make the simulation facility, if needed, available on the dates noted above. In accordance with ES-302, your staff should retain the original simulator performance data (e.g., system pressures, temperatures, and levels) generated during the dynamic operating tests until the examination results are final.

Appendix E of NUREG-1021 contains a number of NRC policies and guidelines that will be in effect while the operating tests are being administered.

To permit timely NRC review and evaluation, your staff should submit the preliminary senior reactor operator license application (Office of Management and Budget (OMB) approval

Pacific Gas and Electric Company number 3150-0090), medical certification (OMB approval number 3150-0024), and waiver requests (if any)(OMB approval number 3150-0090) at least 30 days before the examination date. If the application are not received at least 30 days before the examination date, a postponement may be necessary. The signed application certifying that all training has been completed should be submitted at least 14 days before the examination date.

This letter contains information collections that are subject to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). These information collections were approved by the Office of Management and Budget, approval number 3150-0018, which expires on April 30, 2003.

The public reporting burden for this collection of information is estimated to average 50 hours5.787037e-4 days <br />0.0139 hours <br />8.267196e-5 weeks <br />1.9025e-5 months <br /> per response, including the time for reviewing instructions, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments on any aspect of this collection of information, including suggestions for reducing the burden, to the Information and Records Management Branch (T-6 F33), U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, or by Internet electronic mail at BJS1@NRC.GOV; and to the Desk Officer, Office of Information and Regulatory Affairs, NEOB-10202, (3150-0018), Office of Management and Budget, Washington, DC 20503.

The NRC may not conduct or sponsor, and a person is not required to respond to, a collection of information unless it displays a currently valid OMB control number.

In accordance with 10 CFR 2.790 of the NRCs "Rules of Practice," a copy of this letter, its enclosure(s), and your response will be made available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRCs document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Thank you for your cooperation in this matter. Mr. David Burns has been advised of the policies and guidelines referenced in this letter. If you have any questions regarding the NRC's examination procedures and guidelines, please contact Tom McKernon at (817) 860-8153, or myself at (817) 860-8159.

Sincerely,

/RA/

Anthony T. Gody, Chief Operations Branch Division of Reactor Safety Dockets: 50-275; 50-323 Licenses: DPR-80; DPR-82

Pacific Gas and Electric Company cc:

David H. Oatley, Vice President and General Manager Diablo Canyon Power Plant P.O. Box 56 Avila Beach, California 93424 Lawrence F. Womack, Vice President, Power Generation & Nuclear Services Diablo Canyon Power Plant P.O. Box 56 Avila Beach, California 93424 James R. Becker, Vice President Diablo Canyon Operations and Station Director, Pacific Gas and Electric Company Diablo Canyon Power Plant P.O. Box 3 Avila Beach, California 93424 Dr. Richard Ferguson Energy Chair Sierra Club California 1100 11th Street, Suite 311 Sacramento, California 95814 Nancy Culver San Luis Obispo Mothers for Peace P.O. Box 164 Pismo Beach, California 93448 Chairman San Luis Obispo County Board of Supervisors Room 370 County Government Center San Luis Obispo, California 93408 Truman Burns\Mr. Robert Kinosian California Public Utilities Commission 505 Van Ness, Rm. 4102 San Francisco, California 94102 Robert R. Wellington, Esq.

Legal Counsel Diablo Canyon Independent Safety Committee 857 Cass Street, Suite D Monterey, California 93940

Pacific Gas and Electric Company Ed Bailey, Radiation Control Program Director Radiologic Health Branch State Department of Health Services P.O. Box 942732 (MS 178)

Sacramento, California 94234-7320 Christopher J. Warner, Esq.

Pacific Gas and Electric Company P.O. Box 7442 San Francisco, California 94120 City Editor The Tribune 3825 South Higuera Street P.O. Box 112 San Luis Obispo, California 93406-0112 James D. Boyd, Commissioner California Energy Commission 1516 Ninth Street (MS 34)

Sacramento, California 95814

Pacific Gas and Electric Company Electronic distribution by RIV:

Regional Administrator (EWM)

DRP Director (ATH)

DRS Director (DDC)

Senior Resident Inspector (DLP)

Branch Chief, DRP/E (WBJ)

Senior Project Engineer, DRP/E (VGG)

Staff Chief, DRP/TSS (PHH)

RITS Coordinator (NBH)

C:\ORPCheckout\FileNET\ML030760505.wpd C:OB ATGody/lah

/RA/

03/14/03 OFFICIAL RECORD COPY T=Telephone E=E-mail F=Fax