ML030730734

From kanterella
Jump to navigation Jump to search
Alarm Response Procedure ARP Col a 1-9, Instrument Air Header Pressure Low
ML030730734
Person / Time
Site: Point Beach  NextEra Energy icon.png
Issue date: 02/14/2002
From:
Nuclear Management Co
To:
Office of Nuclear Reactor Regulation
References
FOIA/PA-2003-0094 ARP C01 A 1-9, Rev 1
Download: ML030730734 (1)


Text

POINT BEACH NUCLEAR PLANT ARP CO1 A 1-9 MINOR ALARM RESPONSE PROCEDURE Revision 1 February 14, 2002 INSTRUMENT AIR HEADER PRESSURE LOW I UNIT 0 I I J[f INITIATING DEVICES AND SETPOINTS INSTRUMENT Annunciator C01D Window 1-2 Reflash AIR HEADER

.F PRESSURE LOW TERMINAL STRIP LOCATION UXE-10 1.0 AUTOMATIC ACTIONS None gG 3LQ&-

2.0 POSSIBLE CAUSES 2.1 Alarm on Window 1-2 at rear of panel C01

)'-20 -1S3b 3.0 OPERATOR ACTIONS 3.1 Perform the following:

3.1.1 IF any AFW pump mini-recitc valve falls shut in conjunction with this alarm,

) THEN monitor and maintain minimum AFW flow OR stop the affected AFW pump as necessary to control S/G levels.

3.1.2 Respond per ARP COI D 1-2, INSTRUMENT AIR HEADER PRESS LO.

4.0 SUPPLEMENTAL ACTIONS 4.1 Refer to AOP 5B, Loss of Instrument Air.

5.0 REFERENCES

5.1 Westinghouse drawing 499B666, Sheet 1667; Service/Instrument Air Alarms Main Control Board C01 5.2 ARP C01 D 1-2, INSTRUMENT AIR HEADER PRESS LO 5.3 AOP 5B, Loss of Instrument Air ft Iý Page I of I REFERENCE USE