Changes in Requested Review Dates for Kewaunee Nuclear Power Plant Submittals Supporting Power Uprates
ML030700437
Person / Time
Site: Kewaunee Dominion icon.png
Issue date: 02/27/2003
From: Coutu T
Nuclear Management Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
NRC-03-019
Download: ML030700437 (2)


Text

NMC Committed to Nuc/ea~rExce//ence Kewaunee Nuclear Power Plant Operated by Nuclear Management Company, LLC NRC-03-019 February 27, 2003 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555 KEWAUNEE NUCLEAR POWER PLANT DOCKET 50-305 LICENSE No. DPR-43 CHANGES IN REQUESTED REVIEW DATES FOR KEWAUNEE NUCLEAR POWER PLANT SUBMITTALS SUPPORTING POWER UPRATES

References:

1) Meeting Summary, "Meeting Summary of August 8, 2002, Between the Nuclear Regulatory Commission Staff and Nuclear Management Company, LLC, Concerning Upcoming Power Uprate and Associated Submittals For Kewaunee Nuclear Power Plant," dated August 20, 2002.
2) Letter NRC-03-004 from Thomas Coutu to Document control Desk, "License Amendment Request 193, Measurement Uncertainty Recapture Power Uprate for Kewaunee Nuclear Power Plant, " dated January 13, 2003 (TAC No. MB7225).
3) Letter NRC-02-082 from Thomas Coutu to Document Control Desk, "Kewaunee Nuclear Power Plant Request for Use of GOTHIC 7 in Containment Design Basis Accident Analyses," dated September 30, 2002 (TAC No. MB6408).

The Nuclear Regulatory Commission (NRC) staff has requested that the Kewaunee Nuclear Power Plant (KNPP) review the current submittals being reviewed by the NRC for any changes in the review end dates. The KNPP has reviewed its submittals associated with the measurement uncertainty recapture (MUR) power uprate and the expected stretch power uprate. The following table lists the current and revised review dates for two submittals. No other review date changes are requested.

N490 Highway 42 T Kewaunee, Wisconsin 54216-9510 Telephone: 920 388 2560 ADO(

4 Docket 50-305 NRC-03-019 February 27, 2003 Page 2 Submittal Description Submittal Requested Revised Date Finish Date Requested Finish Date Request for Use of GOTHIC 7 in 09/30/2002 03/03/2003 08/01/2003 Containment Design Basis (TAC No. MB 6408)

Request for Measurement Uncertainty 01/13/2003 05/09/2003 05/14/2003 Recapture Power Uprate (TAC No. MB 7225)

This letter contains no new commitments and no revisions to existing commitments. In accordance with 10 CFR 50.91, a copy of this application is being provided to the designated Wisconsin Official.

Thomas Coutu Site Vice-President, Kewaunee Plant LMG cc US NRC, Region III US NRC, Senior Resident Inspector Electric Division, PSCW