Surry Inspection / Activity Plan 03/01/2003 - 03/31/2004 Inspection Type Inspection Activity Planned Dates Start End No. of Staff on Site Title Unit Number Page 1 of 2 03/04/2003 13:22:27 Report 22 2
- REQUAL INSPECTION Baseline Inspections 03/10/2003 03/14/2003 Licensed Operator Requalification IP 7111111B 1, 2 2
RX HEAD
- REACTOR HEAD LIFTING PROCEDURES Other Routine 04/21/2003 04/23/2003 Reactor Vessel Head Replacement Inspection IP 71007 1
2 EB2-ISI
- INSERVICE INSPECTION-U1 Baseline Inspections 04/28/2003 05/02/2003 Inservice Inspection Activities - PWR IP 7111108P 1
1 S/G-ISI
- S/G INSERVICE INSPECTION-U1 Baseline Inspections 05/05/2003 05/07/2003 Inservice Inspection Activities - PWR IP 7111108P 1
1 RX HEAD
- REACTOR HEAD REPLACEMENT Other Routine 05/12/2003 05/16/2003 Reactor Vessel Head Replacement Inspection IP 71007 1
2 CONT REP
- CONTAINMENT REPAIR Other Routine 05/19/2003 05/23/2003 Reactor Vessel Head Replacement Inspection IP 71007 1
1 PS-RP
- RAD PROTECTION AND HEAD REPLACEMENT Other Routine 06/02/2003 06/06/2003 Reactor Vessel Head Replacement Inspection IP 71007 1, 2 Baseline Inspections 06/02/2003 06/06/2003 Access Control to Radiologically Significant Areas IP 7112101 1, 2 Baseline Inspections 06/02/2003 06/06/2003 ALARA Planning and Controls IP 7112102 1, 2 1
- ISFSI OPS Other Routine 06/16/2003 06/19/2003 Operation Of An ISFSI IP 60855 1
- EMERGENCY EXERCISE Baseline Inspections 07/14/2003 07/18/2003 Exercise Evaluation IP 7111401 1, 2 Baseline Inspections 07/14/2003 07/18/2003 Emergency Action Level and Emergency Plan Changes IP 7111404 1, 2 Baseline Inspections 07/14/2003 07/18/2003 Performance Indicator Verification IP 71151 1, 2 3
EB2-MODS
- MODIFICATIONS/10CFR50.59 Baseline Inspections 07/28/2003 08/01/2003 Evaluation of Changes, Tests, or Experiments IP 7111102 1, 2 Baseline Inspections 07/28/2003 08/01/2003 Permanent Plant Modifications IP 7111117B 1, 2 1
PS-RP
- RADIATION PROTECTION - ISFSI Baseline Inspections 09/08/2003 09/11/2003 Access Control to Radiologically Significant Areas IP 7112101 1, 2 1
EB2 HR
- REACTOR HEAD REPLACEMENT Other Routine 09/29/2003 10/03/2003 Reactor Vessel Head Replacement Inspection IP 71007 2
3 PS-RP
- RAD PROTECTION AND HEAD REPLACEMENT Other Routine 09/29/2003 10/03/2003 Reactor Vessel Head Replacement Inspection IP 71007 1, 2 Baseline Inspections 09/29/2003 10/03/2003 Access Control to Radiologically Significant Areas IP 7112101 1, 2 Baseline Inspections 09/29/2003 10/03/2003 ALARA Planning and Controls IP 7112102 1, 2 Baseline Inspections 09/29/2003 10/03/2003 Radioactive Material Processing and Transportation IP 7112202 1, 2 This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.
Surry Inspection / Activity Plan 03/01/2003 - 03/31/2004 Inspection Type Inspection Activity Planned Dates Start End No. of Staff on Site Title Unit Number Page 2 of 2 03/04/2003 13:22:27 Report 22 3
PS-RP
- RAD PROTECTION AND HEAD REPLACEMENT Baseline Inspections 09/29/2003 10/03/2003 Performance Indicator Verification IP 71151 1, 2 1
EB2-ISI
- INSERVICE INSPECTION-U2 Baseline Inspections 10/06/2003 10/10/2003 Inservice Inspection Activities - PWR IP 7111108P 2
1 S/G-ISI
- S/G INSERVICE INSPECTION-U2 Baseline Inspections 10/27/2003 10/30/2003 Inservice Inspection Activities - PWR IP 7111108P 2
2 PS-RP
- RAD PROTECTION AND HEAD REPLACEMENT Other Routine 10/27/2003 10/31/2003 Reactor Vessel Head Replacement Inspection IP 71007 1, 2 Baseline Inspections 10/27/2003 10/31/2003 Access Control to Radiologically Significant Areas IP 7112101 1, 2 Baseline Inspections 10/27/2003 10/31/2003 ALARA Planning and Controls IP 7112102 1, 2 Baseline Inspections 10/27/2003 10/31/2003 Radioactive Material Processing and Transportation IP 7112202 1, 2 Baseline Inspections 10/27/2003 10/31/2003 Performance Indicator Verification IP 71151 1, 2 1
RX HEAD
- CONTAINMENT REPAIR & HEAD REPLACEMENT Other Routine 11/10/2003 11/13/2003 Reactor Vessel Head Replacement Inspection IP 71007 2
3 PI&R
- PROBLEM IDENTIFICATION & RESOLUTION Baseline Inspections 11/17/2003 11/21/2003 Identification and Resolution of Problems IP 71152B 1, 2 Baseline Inspections 12/01/2003 12/05/2003 Identification and Resolution of Problems IP 71152B 1, 2 1
EB2-HS
- HEAT SINK Baseline Inspections 01/12/2004 01/16/2004 Heat Sink Performance IP 7111107B 1, 2 1
EB2-MR
- MAINTENANCE RULE Baseline Inspections 02/02/2004 02/06/2004 Maintenance Effectiveness IP 7111112B 1, 2 3
OL PREP
- INITIAL EXAM PREP Not Applicable 02/02/2004 02/06/2004 SURRY/EXAMS AT POWER FACILITIES V23210 1
3 OL EXAM
- INITIAL EXAM PREP Not Applicable 02/23/2004 02/27/2004 SURRY/EXAMS AT POWER FACILITIES V23210 1
2 EB1SSDPC - SSDPC PRE-INSPECTION VISIT Baseline Inspections 03/01/2004 03/05/2004 Safety System Design and Performance Capability IP 7111121 1, 2 3
OL EXAM
- INITIAL EXAM Not Applicable 03/08/2004 03/12/2004 SURRY/EXAMS AT POWER FACILITIES V23210 1
5 EB1SSDPC - SAFETY SYS DESIGN & PERFROMANCE CAPABILI Baseline Inspections 03/22/2004 03/26/2004 Safety System Design and Performance Capability IP 7111121 1, 2 This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.