Sequoyah Inspection / Activity Plan 03/01/2003 - 03/31/2004 Inspection Type Inspection Activity Planned Dates Start End No. of Staff on Site Title Unit Number Page 1 of 2 03/04/2003 13:52:03 Report 22 1
PB6-SUP
- IP 95001 SUPPLEMENTAL INSPECTION Supplemental Program 02/24/2003 03/21/2003 Supplemental Inspection For One Or Two White Inputs In A Strategic Performance Area IP 95001 2
1 EB2-SGRP
- SG REPLACEMENT PROJECT - UNIT 1 Other Routine 03/17/2003 03/21/2003 Steam Generator Replacement Inspection IP 50001 1
Other Routine 03/31/2003 04/04/2003 Steam Generator Replacement Inspection IP 50001 1
1 2515/150
- TI 2515/150 REV1 UNIT 1 Safety Issues 03/24/2003 03/28/2003 Reactor Pressure Vessel Head and Vessel Head Penetration Nozzles (NRC Bulletin 2002-02)
1 EB2-ISI
- INSERVICE INSPECTION-U1 Baseline Inspections 03/24/2003 03/28/2003 Inservice Inspection Activities - PWR IP 7111108P 1
2 PS-RP
- RAD PROTECTION & STEAM GENERATOR REPLMNT Other Routine 04/14/2003 04/18/2003 Steam Generator Replacement Inspection IP 50001 1
Baseline Inspections 04/14/2003 04/18/2003 Access Control to Radiologically Significant Areas IP 7112101 1, 2 Baseline Inspections 04/14/2003 04/18/2003 ALARA Planning and Controls IP 7112102 1, 2 Baseline Inspections 04/14/2003 04/18/2003 Radioactive Material Processing and Transportation IP 7112202 1, 2 Baseline Inspections 04/14/2003 04/18/2003 Performance Indicator Verification IP 71151 1, 2 1
EB2-SGRP
- SG REPLACEMENT PROJECT - UNIT 1 Other Routine 04/14/2003 04/18/2003 Steam Generator Replacement Inspection IP 50001 1
Other Routine 04/28/2003 05/02/2003 Steam Generator Replacement Inspection IP 50001 1
Other Routine 05/19/2003 05/23/2003 Steam Generator Replacement Inspection IP 50001 1
1 EB2-SGRP
- CONTAINMENT REPAIR Other Routine 04/23/2003 04/25/2003 Steam Generator Replacement Inspection IP 50001 1
2 PS-RP
- RAD PROTECTION & STEAM GENERATOR REPLMNT Other Routine 05/12/2003 05/16/2003 Steam Generator Replacement Inspection IP 50001 1
Baseline Inspections 05/12/2003 05/16/2003 Access Control to Radiologically Significant Areas IP 7112101 1, 2 Baseline Inspections 05/12/2003 05/16/2003 ALARA Planning and Controls IP 7112102 1, 2 Baseline Inspections 05/12/2003 05/16/2003 Radioactive Material Processing and Transportation IP 7112202 1, 2 Baseline Inspections 05/12/2003 05/16/2003 Performance Indicator Verification IP 71151 1, 2 1
- EP INSPECTION Baseline Inspections 06/23/2003 06/27/2003 Alert and Notification System Testing IP 7111402 1, 2 Baseline Inspections 06/23/2003 06/27/2003 Emergency Response Organization Augmentation Testing IP 7111403 1, 2 Baseline Inspections 06/23/2003 06/27/2003 Emergency Action Level and Emergency Plan Changes IP 7111404 1, 2 Baseline Inspections 06/23/2003 06/27/2003 Correction of Emergency Preparedness Weaknesses and Deficiencies IP 7111405 1, 2 Baseline Inspections 06/23/2003 06/27/2003 Performance Indicator Verification IP 71151 1, 2 This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.
Sequoyah Inspection / Activity Plan 03/01/2003 - 03/31/2004 Inspection Type Inspection Activity Planned Dates Start End No. of Staff on Site Title Unit Number Page 2 of 2 03/04/2003 13:52:03 Report 22 3
PS-SEC
- SECURITY - TI/ICM Safety Issues 06/23/2003 06/27/2003 Inspection of Nuclear Reactor Safeguards - Interim Compensatory Measures IP 2515/148 1, 2 1
- ISFSI CONSTRUCTION Other Routine 06/30/2003 07/03/2003 On-Site Fabrication Of Components And Construction On An ISFSI IP 60853 1
2 EB2-HS
- HEAT SINK Baseline Inspections 07/07/2003 07/11/2003 Heat Sink Performance IP 7111107B 1, 2 3
- IDENTIFICATION AND RESOLUTION OF PROBLEM Baseline Inspections 07/14/2003 07/18/2003 Identification and Resolution of Problems IP 71152 1, 2 3
- IDENTIFICATION AND RESOLUTION OF PROBLEM Baseline Inspections 07/28/2003 08/01/2003 Identification and Resolution of Problems IP 71152 1, 2 4
EB2-MODS - MODIFICATIONS/10CFR50.59 Baseline Inspections 08/25/2003 08/29/2003 Evaluation of Changes, Tests, or Experiments IP 7111102 1, 2 Baseline Inspections 08/25/2003 08/29/2003 Permanent Plant Modifications IP 7111117B 1, 2 2
- REQUAL INSPECTION Baseline Inspections 10/06/2003 10/10/2003 Licensed Operator Requalification IP 7111111B 1, 2 1
EB2-ISI
- INSERVICE INSPECTION-U2 Baseline Inspections 11/03/2003 11/07/2003 Inservice Inspection Activities - PWR IP 7111108P 2
1 S/G-ISI
- S/G INSERVICE INSPECTION-U2 Baseline Inspections 11/10/2003 11/12/2003 Inservice Inspection Activities - PWR IP 7111108P 2
1 2515/150
- TI 2515/150 REV 1 UNIT 2 Safety Issues 11/10/2003 11/14/2003 Reactor Pressure Vessel Head and Vessel Head Penetration Nozzles (NRC Bulletin 2002-02)
1 EB2-MR
- MAINTENANCE RULE Baseline Inspections 01/12/2004 01/16/2004 Maintenance Effectiveness IP 7111112B 1, 2 1
PB6-FP
- FLOOD PROTECTION Baseline Inspections 02/09/2004 02/13/2004 Flood Protection Measures IP 7111106 1, 2 This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.