Revision to Emergency Plan Implementing Procedure
ML030640253
Person / Time
Site: Ginna Constellation icon.png
Issue date: 02/25/2003
From: Watts R
Rochester Gas & Electric Corp
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
Download: ML030640253 (2)


Text

RI ANff An Energy East Company ROCHESTER GAS AND ELECTRIC CORPORATION - 89 EAST AVENUE, ROCHESTER, N Y 14649-0001

  • 585 546-2700 www rge com February 25, 2003 U.S. Nuclear Regulatory Commission Document Control Desk Washington, DC 20555 Attn: Mr. Robert Clark (Mail Stop O-8-E9)

Project Directorate I-1

Subject:

Revision to Emergency Plan Implementing Procedures R.E. Ginna Nuclear Power Plant Docket No. 50-244 Gentlemen:

In accordance with 10 CFR 50.4(b)(5), enclosed are revisions to Ginna Station Emergency Plan Implementing Procedures (EPIP).

We have determined, per the requirements of 10 CFR 50.54(q), that the procedure changes do not decrease the effectiveness of our Nuclear Emergency Response Plan.

Very truly yours, Richard J. Watts Manager, Nuclear Training Department Enclosures xc: USNRC Region 1 (2 copies of letter and 2 copies of each procedure)

Resident Inspector, Ginna Station (1 copy of letter and 1 copy of each procedure)

RG&E Nuclear Safety and Licensing (1 copy of letter)

Dr. Robert C. Mecredy (2 copies of letter only)

RJW/jtw

U.S. Nuclear Regulatory Commission February 25, 2003 Page 2 of 2 PROCEDURE REVISION NUMBER EPIP 1-5 52 EPIP 1-9 23 EPIP 1-11 29 EPIP 1-13 4 EPIP 1-16 5 EPIP 1-17 3 EPIP 2-6 12 EPIP 3-1 21 EPIP 3-4 9 EPIP 4-8 1 EPIP 4-9 1 EPIP 4-10 0 EPIP 4-11 0 EPIP 5-1 27 EPIP 5-2 30