March 26, 2003 Mr. Alexander Marion, Director Engineering Nuclear Energy Institute 1776 I Street, NW, Suite 400 Washington, D.C. 20006-3708
SUBJECT:
RESPONSE TO QUESTIONS CONCERNING NRC ORDER EA-03-009
Dear Mr. Marion:
This letter responds to your letter dated February 19, 2003, in which you submitted questions concerning the interpretation and implementation of U.S. Nuclear Regulatory Commission (NRC) Order EA-03-009. Enclosed is a copy of the meeting summary which addresses your questions as well as all other questions answered during the public meeting held on February 24, 2003. The meeting summary is also available under ADAMS accession number ML030780413.
If you have any further questions about issues related to the order, please do not hesitate to ask me or contact Mr. Steven Bloom at 301-415-1313.
Sincerely,
/RA/
Brian W. Sheron Associate Director of Project Licensing
& Technical Analysis Office of Nuclear Reactor Regulation
Enclosure:
As stated cc: See next page
cc: Larry Matthews, MRP Southern Nuclear Operating Company Manager, Inspection and Testing Services P. O. Box 1295 Birmingham, AL 35201
March 26, 2003 Mr. Alexander Marion, Director Engineering Nuclear Energy Institute 1776 I Street, NW, Suite 400 Washington, D.C. 20006-3708
SUBJECT:
RESPONSE TO QUESTIONS CONCERNING NRC ORDER EA-03-009
Dear Mr. Marion:
This letter responds to your letter dated February 19, 2003, in which you submitted questions concerning the interpretation and implementation of U.S. Nuclear Regulatory Commission (NRC) Order EA-03-009. Enclosed is a copy of the meeting summary which addresses your questions as well as all other questions answered during the public meeting held on February 24, 2003. The meeting summary is also available under ADAMS accession number ML030780413.
If you have any further questions about issues related to the order, please do not hesitate to ask me or contact Mr. Steven Bloom at 301-415-1313.
Sincerely,
/RA/
Brian W. Sheron Associate Director of Project Licensing
& Technical Analysis Office of Nuclear Reactor Regulation
Enclosure:
As stated cc: See next page Distribution:
PUBLIC PDII-2 R/F PDIII-2 R/F S. Bloom A. Mendiola OGC ACRS B. Sheron J. Zwolinski M. Case R. Borchardt NRR Mailroom (Y020030042)
P. Coates L. Cox S. Collins G. Grant, RIII W. Ruland RBarrett Accession Nos.: Incoming: ML030570132, Response: ML030570252, Package: ML030620762
- See previous concurrence OFFICE PDII-2/PM PDII-2/LA PDII-2/SC DE/D DLPM/D ADPT NAME SBloom BClayton AMendiola*
RBarrett*
JZwolinski*
BSheron DATE 3/25/2003 3/25/2003 3/4/2003 3/7/2003 3/7/2003 3/25/2003 OFFICIAL RECORD COPY