ML030550804

From kanterella
Jump to navigation Jump to search
Summary of Public Meeting Between NRC and Firstenergy Nuclear Operating Co to Discuss Firstenergy'S Corrective Action Plan for Management and Human Performance Improvement for Davis-Besse Nuclear Power Plant
ML030550804
Person / Time
Site: Davis Besse Cleveland Electric icon.png
Issue date: 02/24/2003
From: Christine Lipa
NRC/RGN-III
To:
NRC/RGN-III
References
Download: ML030550804 (5)


Text

February 24, 2003 LICENSEE: FirstEnergy Nuclear Operating Company FACILITY: Davis-Besse Nuclear Power Station, Unit 1

SUBJECT:

SUMMARY

OF THE SEPTEMBER 18, 2002, PUBLIC MEETING TO DISCUSS FIRSTENERGYS CORRECTIVE ACTION PLAN FOR MANAGEMENT AND HUMAN PERFORMANCE IMPROVEMENT On September 18, 2002, the Nuclear Regulatory Commission (NRC) held a public meeting at the Davis-Besse Nuclear Power Station Energy Education Center in Oak Harbor, Ohio. The meeting was between the NRC Davis-Besse Oversight Panel and FirstEnergy Nuclear Operating Company (FENOC) to discuss the licensees planned corrective actions to address the Davis-Besse organizational and human performance problems presented to the the NRC during the August 15, 2002, public meeting. The agenda, meeting notice, transcript and the FENOC presentation can be found in ADAMS as ML022560263, ML022600093, ML022880256, and ML022680286; respectively. A list of NRC and licensee meeting participants can be found in Enclosure 1.

These documents and many others related to the reactor vessel head degradation can also be found on the NRCs website at http://www.nrc.gov/reactors/operating/ops-experience/vessel-head-degradation.html.

/RA by D.Passehl Acting for/

Christine A. Lipa, Chief Branch 4 Division of Reactor Projects Docket No. 50-346 License No. NPF-3 See Attached Distribution Enclosure

DOCUMENT NAME: C:\ORPCheckout\FileNET\ML030550804.wpd To receive a copy of this document, indicate in the box: "C" = Copy without attachment/enclosure "E" = Copy with attachment/enclosure "N" = No copy OFFICE RIII RIII NAME DPassehl:klg CLipa /RA by D.Passehl Acting for/

DATE 02/24/03 02/24/03 OFFICIAL RECORD COPY

FirstEnergy Nuclear Operating Company cc w/encls: B. Saunders, President - FENOC Plant Manager Manager - Regulatory Affairs M. OReilly, FirstEnergy State Liaison Officer, State of Ohio R. Owen, Ohio Department of Health Ohio Public Utilities Commission C. Emahiser, Ottawa County Sheriff J. P. Greer, Director, Emergency Management Agency S. Isenberg, President, Lucas County Board of Commissioners J. Telb, Lucas County Sheriff B. Halsey, Director, Emergency Management Agency G. Adams, Village Administrator, Genoa The Honorable Robert Purney The Honorable Lowell C. Krumnow The Honorable Joseph Verkin The Honorable Thomas Leaser The Honorable Jack Ford The Honorable Thomas Brown S. Arndt, President, Ottawa County Board of Commissioners The Honorable Joe Ihnat INPO D. Lochbaum, Union of Concerned Scientists

FirstEnergy Nuclear Operating Company cc w/encls: B. Saunders, President - FENOC Plant Manager Manager - Regulatory Affairs M. OReilly, FirstEnergy State Liaison Officer, State of Ohio R. Owen, Ohio Department of Health Ohio Public Utilities Commission C. Emahiser, Ottawa County Sheriff J. P. Greer, Director, Emergency Management Agency S. Isenberg, President, Lucas County Board of Commissioners J. Telb, Lucas County Sheriff B. Halsey, Director, Emergency Management Agency G. Adams, Village Administrator, Genoa The Honorable Robert Purney The Honorable Lowell C. Krumnow The Honorable Joseph Verkin The Honorable Thomas Leaser The Honorable Jack Ford The Honorable Thomas Brown S. Arndt, President, Ottawa County Board of Commissioners The Honorable Joe Ihnat INPO D. Lochbaum, Union of Concerned Scientists ADAMS Distribution:

DFT S. Rosenberg, OEDO RidsNrrDipmlipb J. Caldwell, RIII B. Clayton, RIII DRPIII DRSIII PLB1 JRK1 DB0350

Enclosure 1 Meeting Participants NRC J. Grobe, Chairman, Davis-Besse Oversight Panel W. Dean, Deputy Director, Division of Engineering, NRR C. Lipa, Chief, Branch 4, Division of Reactor Projects A. Mendiola, Section Chief, Division of Licensing and Project Management, NRR C. Thomas, Senior Resident Inspector, Davis-Besse D. Simpkins, Resident Inspector, Davis-Besse G. Wright, Project Engineer, Region III FirstEnergy Nuclear Operating Company L. Myers, Chief Operating Officer R. Schrauder, Director - Support Services L. W. Pearce, Vice President, Quality Oversight D. Gudger, Manager, Performance Improvement corrective Action Process Owner S. Loehlein, Manager, Quality Assessment D. Eshelman, Director, Life Cycle Management