January 2003 Monthly Operating Report for Turkey Point Units 3 & 4
ML030550707
Person / Time
Site: Turkey Point  
Issue date: 02/13/2003
From: Jefferson W
Florida Power & Light Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
GL-97-002, L-2003-031
Download: ML030550707 (3)


Text

FPL U. S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, D. C. 20555 Re:

Turkey Point Units 3 and 4 Docket Nos. 50-250 and 50-251 Monthly Operating Report - January 2003 In accordance with the requirements of Turkey Point Units 3 and 4 Technical Specification 6.9.1.5, and the guidance of Generic Letter 97-02, attached are the January 2003 Operating Data Reports and Summaries of Operating Experience for Turkey Point Units 3 and 4.

Very truly yo ili n, Jr.

Vice -resid "nt Turkey Point Plant DRL Attachments NRC Regulatory Issue Summary 2001-05 waived the requirements that multiple copies of documents be submitted to the NRC.

an FPL Group company FEB 13 M903 L-2003-031 10 CFR 50.36

DOCKET NO.:

UNIT:

DATE:

COMPLETED BY:

TELEPHONE:

50-250 Turkey Point Unit 3 2/5/2003 David Lafleur (305) 246-7150 Reporting Period January. 2003 OPERATING DATA REPORT Design Electrical Rating (MWe-Net) 720 Maximum Dependable Capacity (MWe-Net) 693 Month Year-to-date Cumulative No. of hours reactor was critical 703.7 703.7 195243.5 No. of hours generator was on line (service hours) 698.1 698.1 192906.6 Unit reserve shutdown hours 0

0 121.8 Net Electrical Energy (MWH) 493484 493484 125852561 UNIT SHUTDOWNS (1) Reason (2) Method A - Equipment Failure (Explain)

B - Maintenance or Test C - Refueling D - Regulatory Restriction E - Operator Training/License Examination F - Administrative G - Operational Error (Explain)

H - Other 1 - Manual 2 - Manual Trip/Scram 3 - Automatic Trip/Scram 4 - Continuation 5 - Other (Explain)

Summary Of Monthly Operatingq Experience Unit 3 operated at essentially 100% until the unit was manually tripped on 1/27/03 at 8:44 AM due to low Steam Generator level as a result of low instrument air pressure. Repairs were completed and Unit 3 was returned to 100% power on 1/31/03 at 2:00 AM.

DOCKET NO.:

UNIT:

DATE:

COMPLETED BY:

TELEPHONE:

50-251 Turkey Point Unit 4 1/2/2003 David Lafleur (305) 246-7150 Reporting Period January. 2003 UNIT SHUTDOWNS (1) Reason (2) Method A - Equipment Failure (Explain)

B - Maintenance or Test C - Refueling D - Regulatory Restriction E - Operator Training/License Examination F - Administrative G - Operational Error (Explain)

H - Other 1 - Manual 2 - Manual Trip/Scram 3 - Automatic Trip/Scram 4 - Continuation 5 - Other (Explain)

Summary Of Monthly Operating Experience Unit 4 operated at essentially 100% power for the month until 1/13/03, when power was reduced to 40%

for Turbine Valve Testing. Power was subsequently returned to 100% on 1/15/03 and remained essentially at 100% for the rest of the month.

Design Electrical Rating (MWe-Net) 720 Maximum Dependable Capacity (MWe-Net) 693 Month Year-to-date Cumulative No. of hours reactor was critical 744 744 192106.7 No. of hours generator was on line (service hours) 744 744 187689.2 Unit reserve shutdown hours 0

0 577.2 Net Electrical Energy (MWH) 510899 510899 123469989