JAMES L. LOPES (No. 63678)
JULIE B. LANDAU (No. 162038)
HOWARD, RICE, NEMEROVSKI, CANADY, FALK & RABKIN A Professional Corporation Three Embarcadero Center, 7th Floor San Francisco, California 94111-4065 Telephone:
415/434-1600 Facsimile:
415/217-5910 1
2 3
4 5
6 7
8 9
10 11 12 HCAM 13
" c k raN
- 14 PUK
&R4.BAON A.A.-,W.- 15 16 In re PACIFIC GAS AND ELECTRIC COMPANY, a California corporation, Debtor.
Federal I.D. No. 94-0742640 Case No. 0 1-30923 DM Chapter 11 Case Date:
Time:
Place:
February 27, 2003 1:30 p.m.
235 Pine Street, 22nd Floor San Francisco, California DECLARATION OF MY NGUYEN IN SUPPORT OF FOURTH MOTION FOR AUTHORITY TO INCUR MISCELLANEOUS IMPLEMENTATION EXPENSES DECLARATION OF MY NGUYEN Attorneys for Debtor and Debtor in Possession PACIFIC GAS AND ELECTRIC COMPANY UNITED STATES BANKRUPTCY COURT NORTHERN DISTRICT OF CALIFORNIA SAN FRANCISCO DIVISION 17 18 19 20 21 22 23 24 25 26 27 28
,I-L?- "ý'
9 5'ýt" 44./
1 2
3 4
5 6
7 8
9 10 11 12 HOWARD 13 RKE
ýCNt 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 I, My Nguyen, declare:
- 1.
I am employed by Pacific Gas and Electric Company ("PG&E"), the debtor and debtor-in-possession in this Chapter 11 case. I hold the position of Principal Project Manager in PG&E's General Services Department. The General Services Department is responsible for PG&E's facilities, fleet and materials management. In this position, I am responsible for managing the implementation of PG&E's proposed Plan of Reorganization (as amended from time to time, the "Plan") with respect to General Services. I oversee and supervise the General Service teams assigned to Plan implementation, and coordinate and facilitate schedule and budget activities and tasks related thereto.
- 2.
This declaration is submitted in support of PG&E's Fourth Motion for Authority to Incur Miscellaneous Implementation Expenses (the "Motion"). Defined terms used herein shall have the meanings set forth in the Motion. I make this declaration based on personal knowledge, except where otherwise indicated, and if called as a witness, could and would testify competently to the matters set forth herein.
- 3.
In the Third Motion for Authority to Incur Miscellaneous Implementation Expenses (the "Third Miscellaneous Motion"), filed on October 18, 2002, PG&E explained that, in connection with implementation of the Plan, it anticipated: (i) leasing seven new buildings, which would need to be prepared for occupancy by the New Entities, and (ii) modifying 30 existing PG&E-owned buildings for use by PG&E and the New Entities.
PG&E obtained authority to incur $425,000 in connection with hiring construction project managers in order to prepare the new buildings for occupancy and to modify the existing PG&E buildings to serve multiple entities. PG&E explained that actual construction would not take place until after confirmation of the Plan, but that the construction project managers were needed in order to assess the construction needs and plan for the construction work.
Specifically, the preliminary work includes: (i) determining the scope of work for each building; (ii) preparing and submitting local building permit and conditional use permit applications; (iii) development of detailed site-specific work schedules; and (iv) preparing contract specifications, selecting qualified contractors, and negotiating contract terms. Set DECLARATION OF MY NGUYEN 1
2 3
4 5
6 7
8 9
10 11 12 HOVORD 13 RKE c
14 INK A,*
O..a 15 16 17 18 19 20 21 22 23 24 25 26 27 28 forth in Paragraph 6 below is a description of additional costs of approximately $535,000 that PG&E now anticipates will be incurred in connection with the construction project managers.
- 4.
Also in the Third Miscellaneous Motion, PG&E obtained authority to incur
$100,000 in pre-construction costs related to permits and engineering, noting: "Until the construction project managers.., begin work, PG&E will not have a precise estimate of the total pre-construction costs." (at p. 8:13-14). Set forth in Paragraphs 7 and 8 below are additional pre-construction projects for total additional expenses of approximately $91,300.
- 5.
PG&E also filed the Motion for Authority to Incur Lease Extension Fees on January 17, 2003 (the "Lease Extension Motion"), identifying six specific properties to be leased by the New Entities, for which PG&E requested authority to pay lease extension fees to retain the right to enter into long-term leases for these properties upon Plan confirmation.
- 6.
Additional Costs for Construction Project Managers. Since November 2002, PG&E has discovered that the pre-construction planning work will be more extensive and time-consuming than originally estimated at the project's inception. Now that PG&E has identified specific buildings to lease (as described in the Lease Extension Motion), and as planning has progressed in preparing existing PG&E buildings and sites for occupancy by the New Entities, it has become clear that more work will be required of the construction project managers. For example, instead of using trailers on existing PG&E sites to house certain employees and functions of the New Entities, as originally planned, six of the PG&E sites will require the construction of new metal buildings since PG&E has determined that the trailers cannot accommodate the space needs of the groups targeted to occupy them.
Furthermore, at many of the existing PG&E buildings, more substantial modifications will be required than originally anticipated to prepare these facilities to be shared by employees of PG&E and employees of the New Entities. Therefore, PG&E now estimates that an additional $535,000 will be required to enable the construction project managers to complete the pre-construction planning tasks.
DECLARATION OF MY NGUYEN 1
2 3
4 5
6 7
8 9
10 11 12 HOWARD 13 RIKE "CAD(
14 U¢RAMIN Ah,*-C.
15 16 17 18 19 20 21 22 23 24 25 26 27 28
- 7.
Woodland Site, At the Woodland site (described at page 7 of the Lease Extension Motion), PG&E has identified the need to obtain switching devices for telephone lines and telecommunications equipment for a total cost of approximately $36,300 (in the event that Plan implementation does not occur or the Woodland site is not ultimately leased by PG&E, PG&E anticipates that it will have other uses for the telecommunications equipment in the ordinary course of business). Although this property is not yet subject to a long-term lease by PG&E, it has been identified as a critical site to lease and was therefore included in the Lease Extension Motion. Orders must be placed promptly for the switching device ($6,300) and telecommunications equipment ($30,000) because several months' lead time is required to obtain the necessary equipment and allow time to install the telecommunications infrastructure. The telecommunications infrastructure must be in place by the time construction at the site begins, which is expected to occur promptly after Plan confirmation.
- 8.
Vaca-Dixon Substation. PG&E anticipates that the Vaca-Dixon Substation, an existing PG&E property, will be utilized by ETrans for materials storage. In order to prepare Vaca-Dixon Substation for use by ETrans, approximately $55,000 is needed to perform site grading and preparation to eliminate ponding in the storage area, to provide electrical service to the yard area, and to install safety barriers (removable bollards). This work must be completed before further construction can be performed at the site, in order to meet environmental and safety concerns, and to prepare the site for construction related to preparation of the site for the storage of materials and equipment. Even if Plan implementation does not occur, this work should be beneficial to PG&E in preparing the Vaca-Dixon Substation for additional storage uses by PG&E.
- 9.
PG&E's standard contractual provisions in place with the construction project managers do not guarantee future work or any minimum amount of revenue. PG&E also maintains the right to terminate the work at any time without cause, in which case PG&E is liable only for work performed to the date of termination plus costs reasonably incurred by the construction project managers in terminating any work in progress. The DECLARATION OF MY NGUYEN 1
2 3
4 5
6 7
8 9
10 11 12 HOMIM 13 PKE c"A1,W 14 B%1K
. 15 16 17 18 19 20 21 22 23 24 25 26 27 28 costs described in Paragraphs 7 and 8 above (i.e., once the equipment described in Paragraph 7 is purchased and the work described in Paragraph 8 commences) would not be recoverable or subject to early termination.
I declare under penalty of perjury of the laws of the United States that the foregoing is true and correct, and that this declaration was executed at San Francisco, California on February _7, 2003.
MY COENU DECLARATION OF MY NGUYEN