January 2003 Monthly Operating Report for Calvert Cliffs, Units 1 and 2
ML030500008
Person / Time
Site: Calvert Cliffs  Constellation icon.png
Issue date: 02/13/2003
From: Nietmann K
Constellation Energy Group
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
Download: ML030500008 (7)


Text

Kevin J. Nietmann Plant General Manager Calvert Cliffs Nuclear Power Plant Constellation Generation Group, LLC 1650 Calvert Cliffs Parkway Lusby, Maryland 20657 410 495-4101 410 495-4787 Fax Constellation Energy Group February 13, 2003 U. S. Nuclear Regulatory Commission Washington, DC 20555 ATTENTION:

SUBJECT:

Document Control Desk Calvert Cliffs Nuclear Power Plant Unit Nos. I & 2; Docket Nos. 50-317 & 50-318 January 2003 Operating Data Reports The subject reports are being sent to you as required by Technical Specification 5.6.4.

Should you have questions, please contact Mr. Thomas S. O'Meara at (410) 495-6940.

Very truly yours, KJN/CAN/bjd Attachments cc:

J. Petro, Esquire J. E. Silberg, Esquire Director, Project Directorate I-1, NRC D. M. Skay, NRC H. J. Miller, NRC Resident Inspector, NRC R. I. McLean, DNR J. Wright, INPO K. N. Larson, ANI

OPERATING DATA REPORT Docket No.

50-317 Calvert Cliffs Unit 1 February 3, 2003 Prepared by Herman 0. Olsen Telephone: (410)495-6734 REPORTING PERIOD DESIGN ELECTRICAL RATING (NET MWe)

MAXIMUM DEPENDABLE CAP'Y (NET MWe)

JANUARY 2003 845 825 This month Year to-Date Cumulative to Date NUMBER OF HOURS REACTOR WAS CRITICAL HOURS GENERATOR ON LINE UNIT RESERVE SHUTDOWN HOURS NET ELECTRICAL ENERGY GENERATED(MWH) 744.0 744.0 0.0 647,173 744.0 184,033.4 744.0 180,869.7 0.0 0.0 647,173 147,814,436

1.
2.
3.

4.

UNIT SHUTDOWNS DOCKET NO.

UNIT NAME DATE COMPLETED BY TELEPHONE 50-317 Calvert Cliffs - U1 February 5, 2003 Herman 0. Olsen (410) 495-6734 REPORTING MONTH January 2003

' Reason:

A - Equipment Failure B - Maintenance or Test C - Refueling D - Regulatory Restriction E - Operator Training & License Examination F - Administrative G - Operational Error H - Other 2 Method:

1 - Manual 2 - Manual Scram.

3 - Automatic Scram.

4 - Continued 5 - Other NO.

DATE TYPE DURATION REASON' METHOD OF CAUSE/CORRECTIVE ACTIONS F:

FORCED (HOURS)

SHUTTING S:

SCHEDULED DOWN 2 COMMENTS There were no shutdowns this month.

DOCKET NO. 50-317 CALVERT CLIFFS - UNIT I February 5, 2003

SUMMARY

OF OPERATING EXPERIENCE January 2003 The unit began the month at 100% reactor power.

On 01/31/03 at 2200, power was reduced to 85% for Main Turbine Valve Testing.

The unit remained at 85% power for the remainder of the month.

OPERATING DATA REPORT Docket No.

50-318 Calvert Cliffs Unit 2 February 3, 2003 Prepared by Herman 0. Olsen Telephone:(410)495-6734 REPORTING PERIOD DESIGN ELECTRICAL RATING (NET MWe)

MAXIMUM DEPENDABLE CAP'Y (NET MWe)

JANUARY 2003 845 835 This month

1. NUMBER OF HOURS REACTOR WAS CRITICAL
2. HOURS GENERATOR ON LINE
3. UNIT RESERVE SHUTDOWN HOURS
4. NET ELECTRICAL ENERGY GENERATED(MWH) 744.0 744.0 0.0 645,490 Year-Cumulative to-Date to Date 744.0 744.0 0.0 178,303.8 176,448.7 0.0 645,490 145,231,920

UNIT SHUTDOWNS DOCKET NO.

UNIT NAME DATE COMPLETED BY TELEPHONE 50-318 Calvert Cliffs-U2 February 5, 2003 Herman 0. Olsen (410) 495-6734 REPORT MONTH January 2003 SReason:

A - Equipment Failure B - Maintenance or Test C - Refueling D - Regulatory Restriction E - Operator Training & License Examination F - Administrative G - Operational Error H - Other 2 Method:

I - Manual 2 - Manual Scram.

3 - Automatic Scram.

4 - Continued 5 - Other 0)

NO.

DATE TYPE DURATION REASON' METHOD OF CAUSE/CORRECTIVE ACTIONS F:

FORCED (HOURS)

SHUTTING S:

SCHEDULED DOWN 2 COMMENTS There were no shutdowns this month.

DOCKET NO. 50-318 CALVERT CLIFFS - UNIT 2 February 5, 2003

SUMMARY

OF OPERATING EXPERIENCE January 2003 The unit began the month at 100% reactor power.

On 01/27/03 at 0605, power was reduced to 99% due to a temperature instrumentation problem. Power was returned to 100% at 2100.

The unit operated at 100% reactor power for the remainder of the month.