ML030450487

From kanterella
Jump to navigation Jump to search
Attachment 2 - TVA Handout During 02/10/03 Meeting, Tennessee Valley Authority Browns Ferry Nuclear Plant, Unit 1 Restart Status
ML030450487
Person / Time
Site: Browns Ferry Tennessee Valley Authority icon.png
Issue date: 02/10/2003
From:
Tennessee Valley Authority
To:
Office of Nuclear Reactor Regulation
References
Download: ML030450487 (19)


Text

TENNESSEE VALLEY AUTHORITY BROWNS FERRY NUCLEAR PLANT UNIT 1 RESTART STATUS 4 T>

14 A -

- 44TA

,-.44. 4 4 A

  • -4' -.-

4'- 4.-,-

& 4-' 4'4444

- 44.444**4 444.444-

. 4 . - - - -. .- ,,< - ' 4'4Z ,-...' ,

V3-2.C 4444 Z> -4 1L-4L4K..,..--4.-

444*

'4 -'-'44

-.

  • A - x-4 4'14'4 -4
  • 444'44.44 *4.4 - -. '4

- 4*4. 4-

  • 444 4444.444.',444 44. .44-444-4

.444.4- -

"4 44

'4-24.'

  • - '4.

i'if' I  ;*-.,. ..44.:4,44:i 4.

  • -.44-4

.4...- .4 -. 4-4-4

- .- ,: ,.. 4 4. 4 -4 4 4 4 j 4'4.

444 4 44 44444-4

4. - 4- 4..4 4 j$44 . 4 4

- 't4'

-. 4 4I4,44.4444 -r -

-444.44'.

--. 4 4-4444 / 4 4'4.4. 44 i6iiII

TENNESSEE VALLEY AUTHORITY BROWNS FERRY NUCLEAR PLANT UNIT 1 RESTART STATUS NRRfRegion II - Rockville, MD February 10, 2003

Agenda

"* Introduction - John Scalice

"* Background - Ashok Bhatnagar

  • Unit 1 Restart Project Objectives - Jon Rupert

"* Unit 1 Restart Organization - Jon Rupert

"* Unit 1 Project Overview and Schedule - Jon Rupert

"* Unit 1 Engineering Activities Status - Joe Valente

"* Impact on Operating Units - Rick Drake

"* Unit 1 Maintenance & Modifications Status - Rick Drake

"* Regulatory Activities Status - Tim Abney

  • Corrective Action Program/Self Assessments - Tim Abney
  • Nuclear Assurance Oversight - Steve Tanner
  • Summary and Conclusion - John Scalice 2

Background

"* All three BFN Units are essentially identical GE BWR4, Mark I Containment reactors

"*Designed and constructed by TVA

"*Units 1, 2, and 3 licensed in 1973, 1974, and 1976 respectively

"* All three BFN units voluntarily shutdown by TVA in March 1985, because of regulatory and management issues

- TVA committed to obtain NRC approval prior to restart of any BFN unit

- TVA submitted the Nuclear Performance Plan, Volume 3, in August 1986. It outlined the steps needed to recover the BFN units and was specifically directed to Unit 2 Ashok Bhatnagar 3

Background

"* TVA executed Unit 2 restart plan, obtained NRC approval, and restarted Unit 2 on May 24, 1991

"* TVA proposed regulatory framework for restart of Units 1 and 3 in July 1991, outlining improvements to the Unit 2 restart plan

"*NRC approved the regulatory framework proposed by TVA in April 1992

"* TVA executed the Unit 3 restart plan, obtained NRC approval, and restarted Unit 3 on November 19, 1995

"* TVA Board of Directors decided on May 16, 2002, to restart Unit I after detailed study and favorable Supplemental Environmental Impact Statement Ashok Bhatnagar 4

Unit 1 Restart Project Objectives

"* Unit Fidelity

- Return Unit 1 to service operationally the same as Units 2 and 3

- Utilize current design criteria

- Utilize existing TVA procedures, programs and processes

"* Project Integration

- Extensive integrated planning and scheduling which incorporated lessons learned from Units 2 and 3

- Touch each component, system, and plant area only once

"* Return Unit 1 in condition to operate safely, efficiently, and reliably Jon Rupert 5

Unit 1 Restart Organization

"* Dedicated resources for Unit 1 restart

"* TVA management team with experience on restart of Units 2 and 3

"* Bechtel is primary engineering contractor, Stone and Webster is primary maintenance and modifications contractor

"* Unit 1 team closely integrated with operating units' team

"* Organizational structure and strong team in place for restart effort Jon Rupert 6

Unit 1 Project Overview and Schedule Work Scope Required for Unit 1 Restart

- Nuclear Performance Plan Special Programs

- Engineering analyses

- Extensive design changes consistent with Units 2/3 restart

- Design changes implemented since Units 2/3 restart

- Future design changes in 5-year BFN Project Plan

- Corrective/Preventive maintenance

- Regulatory issues

- Licensing actions

- Inservice inspections

- Restart testing Jon Rupert 7

I 29O211 I3 2 1O 0 ".A i, 2- 1 02 1 29 1 t 0 044 I CZ 1 al I M0 1 03 1 4 1 01 1 Q 031 I..1 .1 1 -1 ..1 3 1 244 _I 01 1 1I 2 a2030 I aS I 0 BOARDAPPROVAL i AWARDMAJOR CONTRACTS ENGINEERINGPROGRAMSREO*DFOR DEDS ENGINEERINGISSUE UIRCBRIEF MOBILIZEMODIFICA SUPPORT "RAM LONGLEADMATERIAL-ORDER MODIFICATIONS-DEMOLITIONIN 4OCNACTIVITIES MAJiRIAL ORDER PREPARE tISSUE BULK ENGINEERING . CONTROL I BUILDINGDIC'S ENGINEERINGISSI REACTORBUILDINGOCws W LEADMATERIAL. DELIVER VrIFICATIONS IMPLEMENTDRYWELLDCW'S DESIGNENGINEERINGSUPPORT MODIFICATIONSRIMPLEMENT CONTROL BUILDINGDCN`S ENGINEERINGISSUETURBINEBU.ILDINGDCNW CRDR ENGINEERINGCOMPLETE MOOIFICATIONSIMPLEMENTREACTORBUILDING DCWS OPERA iONS PROGRAMS LCENSE RENEWALSUBMITTAL MODIFICATIONSIMPLEMENTTURBINE BUILDING DCNS RESTART TESTPROGRAM MAINTENANCEClI 9 PMV.

EPU SUBMITTAL JMRISKINFORMEDEl SUBMITTAL I *P OPERATOR TRAINING I SPAE*SPOCTURNOVER AREATURNOVER PLANT ACCEPTANCE OPERATIONALREADINESS REVIEW NRC TESTINGNOTIFICATION LICENSINGTO NOTIFYNRC OFFUEL LOAD FUEL LOAD

URBINE GENERATORON TURNINGGEAR
RC APPROVALFOR RESTART POWERASCENSIONTESTING BREAKERCLOSURE Ely Bar tSPT BIofI Pf.d B.Sit 29NOV01 P,*-W*

.02JULOT h rPo.ea,- WTVA BFN UNIT-1 ON. Dat.. WEBSCISm.aAct ivity MAJOR MILESTONES RB-. DON. I EB03 REV 2

Unit 1 Engineering Activities Status

  • Program Activities

- Design Criteria Documents - complete

- Safe Shutdown Analysis - complete

- Operation Mode Calculations - complete

- Generic Letter 89-10 Calculations - complete

- EQ Basis Calculations - complete

- Analytical Limits Calculations - complete

- Drywell Related Baseline Calculations - complete

- Reactor Building Baseline Calculations - in progress

- License Renewal Activities - in progress 9

Joe Valente

Unit 1 Engineering Activities Status

  • Design Change Packages

- Approximately 360 design change packages required for restart

- 60 design changes issued

- All design changes for the drywell are issued

- Currently, 70 design changes in progress and on schedule for Reactor Building, Control Bay and Turbine Building, and yard

  • Challenges

- Modifications interface

- Material supplier interactions Joe Valente 10

92 Impact on Operating Units 0 Access Control

- Physical access accommodations

- Personnel Identification I j

- Training Unit color codes Unit 1 equipment required for Unit 2/3 operation identification i4j 11 Rick Drake

Impact on Operating Units Work Control Reviews

- Experienced Work Control Personnel in Unit 1

- Work schedules evaluated by operating units' personnel Rick Drake 12

Unit 1 Maintenance & Modifications Status

"* Completed Activities

- Drywell piping removal

- Drywell cable determinations

- Drywell decontamination

"* Near-Term Planned Work

- Asbestos abatement

- Extraction steam piping removal

- Condenser retube preparation

- Modifications inside drywell

"* Challenges

- Human performance

- Industrial safety

- Constructability of designs 13 Rick Drake

Regulatory Activities Status

  • Proposed Regulatory Framework for Unit 1 Restart Submitted December 13, 2002
  • Licensing Actions

- Relief Requests PD-1 and PD-2 submitted October 25, 2002

- ISI Program update submitted November 8, 2002

- Detailed Schedules being developed for 18 license amendments Tim Abney 14

Corrective Action Program/Self Assessments Corrective Action Program Being Used to Monitor and Improve Quality

- Management Review Committee Subcommittee reviews all Unit 1 Problem Evaluation Reports (PERs)

- Extensive efforts to encourage contractors to write PERs

- Analysis of PER data to identify trends requiring further action Self Assessments Completed

- Drywell Disassembly

- Drywell Structural Steel Design

- Asbestos Abatement

- Contractor Control Tim Abney 15

Corrective Action Program/Self Assessments

  • Self Assessments Planned FY 03

- Mechanical Baseline Calculations

- Reactor Water Cleanup Design Change Notice

- Auxiliary Power System Analysis

- Appendix R Analysis

- Engineering Training

- Unit Barrier Separations

- Work Plan/Work Order

- Drywell Steel Modification Implementation

- Materials Process

- Drawing Improvement Program

- Corrective Action Program

- Work Control

- Rad Chem Activities

- Integrated Data base (ITEL)

Findings from PERs and Self Assessments Tim Abney 16

Nuclear Assurance Oversight

"* Nuclear Assurance Staffing

- Quality Control, Quality Programs, and Quality Assessments

- Inspections, Source Surveillances, Assessments, and Evaluation and Analysis

- Experienced Nuclear Assurance staff

"* Assessments

- Routine Observations

+ Drywell preparatory work

+ Program and support activities

- Formal Planned/Scheduled

+ Engineering Walkdown Program (Completed)

+ Vertical Slice of RHR System Design (In-progress)

+ Engineering, Maintenance & Modifications, Support, and Operations

"* Conclusions

- No significant issues identified to date

- Demonstrated ability to self-identify and resolve problems in Corrective Action Program Steve Tanner 17

-1 Summary, and Conclusion John Scalice is