January 28, 2003 Mr. Michael P. Gallagher Director-Licensing & Regulatory Affairs Exelon Corporation 200 Exelon Way Kennett Square, PA 19348
SUBJECT:
SCHEDULE REVISION FOR THE REVIEW OF THE PEACH BOTTOM ATOMIC POWER STATION, UNITS 2 AND 3 LICENSE RENEWAL APPLICATION
Dear Mr. Gallagher:
Enclosed is a revised schedule for the review of the Peach Bottom Atomic Power Station, Units 2 and 3, license renewal application. The revised schedule reflects a 22-month review.
If you have any questions regarding this matter, please contact me at 301-415-1973 Sincerely,
/RA/
David Solorio, Senior Reactor Systems Engineer License Renewal Section License Renewal and Environmental Impacts Program Division of Regulatory Improvement Programs Office of Nuclear Reactor Regulation Docket Nos.: 50-277 and 50-278
Enclosure:
As stated cc w/encl: See next page
Peach Bottom LRA Review Schedule MILESTONE TARGET DATE ACTUAL DATE Receive Peach Bottom License Renewal Application 07/02/01 07/02/01 FRN published for receipt and acceptability review 08/01/01 07/25/01 FRN published for acceptance/rejection/opportunity for hearing 08/31/01 08/31/01 FRN published for intent/environmental scoping meeting 09/24/01 09/24/01 Deadline for filing hearing requests and petitions for intervention 10/01/01 10/01/01 Environmental scoping meeting 11/07/01 11/07/01 Environmental scoping period ends 11/26/01 11/26/01 Scoping and screening methodology audit complete 12/14/01 12/07/01 Environmental Requests for Additional Information (RAIs) issued to applicant 12/28/01 12/20/01 Environmental RAI responses received by NRC 02/26/02 01/30/02 Safety RAIs issued by NRC 03/12/02 03/12/02 Safety RAIs responses received by NRC 05/27/02 05/22/02 Scoping inspection complete 06/24/02 05/31/02 Draft Supplemental Environmental Impact Statement (SEIS) to EPA 06/28/02 06/24/02 EPA publised FRN for availability/comments on draft SEIS 07/05/02 07/06/02 Public meeting to discuss draft SEIS 07/31/02 07/31/02 Aging management review inspection complete 08/09/02 07/25/02 Safety Evaluation Report (SER) with open items issued by NRC 09/16/02 09/13/02 End of draft SEIS comment period 09/26/02 09/17/02 ACRS Subcommittee meeting on SER with open items 10/30/02 10/30/02 ACRS Full Committee meeting on SER with open items 11/07/02 11/07/02 Responses to SER open items received by NRC 11/29/02 11/27/02 Optional final inspection complete 01/02/03 12/11/02 Final SEIS issued to EPA 01/31/03 1/22/03 SER issued by NRC 02/06/03 EPA published FRN for availability of final SEIS 02/07/03 Regional Administrators letter issued 02/19/03 ACRS Full Committee meeting on SER 03/06/03 ACRS letter issued 03/03 SER issued as NUREG 03/25/03 Staff Recommendations to Director, NRR 05/05/03 Decision - Director, NRR (license issued, if approved) 05/12/03 Enclosure
Mr. Michael P. Gallagher Director-Licensing & Regulatory Affairs Exelon Corporation 200 Exelon Way Kennett Square, PA 19348
SUBJECT:
SCHEDULE REVISION FOR THE REVIEW OF THE PEACH BOTTOM ATOMIC POWER STATION, UNITS 2 AND 3 LICENSE RENEWAL APPLICATION
Dear Mr. Gallagher:
Enclosed is a revised schedule for the review of the Peach Bottom Atomic Power Station, Units 2 and 3, license renewal application. The revised schedule reflects a 22-month review.
If you have any questions regarding this matter, please contact me at 301-415-1973 Sincerely,
/RA/
David Solorio, Senior Reactor Systems Engineer License Renewal Section License Renewal and Environmental Impacts Program Division of Regulatory Improvement Programs Office of Nuclear Reactor Regulation Docket Nos.: 50-277 and 50-278
Enclosure:
As stated DISTRIBUTION:
See next page G:\\RLEP\\Henry\\Peach Bottom\\22month schedule.wpd OFFICE RLEP:PM RLEP:LA RLEP:SC NAME DSolorio HBerilla SLee DATE 01/27/03 01/28/03 01/28/03 OFFICIAL RECORD COPY
DISTRIBUTION: Letter to Mr. Michael P. Gallagher, Dated: January 28, 2003 HARD COPY RLEP RF D. Solorio R. Hoefling E-MAIL:
PUBLIC W. Borchardt D. Matthews F. Gillespie RidsNrrDe R. Barrett E. Imbro G. Bagchi K. Manoly W. Bateman J. Calvo C. Holden H. Nieh G. Holahan H. Walker S. Black B. Boger D. Thatcher G. Galletti C. Li J. Moore R. Weisman M. Mayfield A. Murphy W. McDowell S. Smith (srs3)
T. Kobetz R. Assa C. Munson RLEP Staff J. Boska D. Lew M. Modes
Peach Bottom Atomic Power Station, Units 2 and 3 cc:
Vice President, General Counsel and Secretary Exelon Generation Company, LLC 300 Exelon Way Kennett Square, PA 19348 Site Vice President Peach Bottom Atomic Power Station Exelon Generation Company, LLC 1848 Lay Road Delta, PA 17314 Plant Manager Peach Bottom Atomic Power Station Exelon Generation Company, LLC 1848 Lay Road Delta, PA 17314 Regulatory Assurance Manager Peach Bottom Atomic Power Station Exelon Generation Company, LLC 1848 Lay Road Delta, PA 17314 Resident Inspector U.S. Nuclear Regulatory Commission Peach Bottom Atomic Power Station P.O. Box 399 Delta, PA 17314 Regional Administrator, Region I U.S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406 Mr. Roland Fletcher Department of Environment Radiological Health Program 1800 Washington Blvd.
Baltimore, MD 21230 Correspondence Control Desk Exelon Generation Company, LLC 200 Exelon Way, KSA 1-N-1 Kennett Square, PA 19348 Rich Janati, Chief Division of Nuclear Safety Bureau of Radiation Protection Department of Environmental Protection Rachel Carson State Office Building P.O. Box 8469 Harrisburg, PA 17105-8469 Board of Supervisors Peach Bottom Township 545 Broad Street Ext.
Delta, PA 17314-9203 Mr. Richard McLean Power Plant and Environmental Review Division Department of Natural Resources B-3, Tawes State Office Building Annapolis, MD 21401 Dr. Judith Johnsrud National Energy Committee Sierra Club 433 Orlando Avenue State College, PA 16803 Manager-Financial Control & Co-Owner Affairs Public Service Electric and Gas Company P.O. Box 236 Hancocks Bridge, NJ 08038-0236 Manager Licensing-Limerick and Peach Bottom Exelon Generation Company, LLC Nuclear Group Headquarters Correspondence Control P.O. Box 160 Kennett Square, PA 19348 Mr. Alan P. Nelson Nuclear Energy Institute 1776 I Street, N.W., Suite 400 Washington, DC 20006-3708 Peach Bottom Atomic Power Station, Units 2 and 3 cc:
Director - Licensing Mid-Atlantic Regional Operating Group Exelon Generation Company, LLC Nuclear Group Headquarters Correspondence Control P.O. Box 160 Kennett Square, PA 19348 Vice President-Licensing and Regulatory Affairs Exelon Generation Company, LLC 4300 Winfield Road Warrenville, IL 60555 Senior Vice President Mid-Atlantic Regional Operating Group Exelon Generation Company, LLC 200 Exelon Way, KSA 3-N Kennett Square, PA 19348 Senior Vice President, Nuclear Services Exelon Generation Company, LLC 4300 Winfield Road Warrenville, IL 60555 Vice President, Mid-Atlantic Operations Support Exelon Generation Company, LLC 200 Exelon Way, KSA 3-N Kennett Square, PA 19348 Manager License Renewal Exelon Generation Company, LLC 200 Exelon Way Kennett Square, PA 19348 Public Service Commission of Maryland Engineering Division Chief Engineer 6 St. Paul Center Baltimore, MD 21202-6806 Chief Operating Officer Exelon Generation Company, LLC 4300 Winfield Road Warrenville, IL 60555