December 2002 Monthly Operating Report for South Texas Project
ML030280519
Person / Time
Site: South Texas  STP Nuclear Operating Company icon.png
Issue date: 01/15/2002
From: Mallen F
South Texas
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
G02, NOC-AE-03001451, STI: 31541410
Download: ML030280519 (14)


Text

Nuclear Opverating wCompany SoidhkwPa~ Ak rqrVqCcffM POIAF 0&w 3

t akw77433 January 15, 2002 NOC-AE-03001451 File No.: G02 10CFR50.71 STI: 31541410 U. S. Nuclear Regulatory Commission Attention: Document Control Desk One White Flint North 11555 Rockville Pike Rockville, MD 20852 South Texas Project Units 1 and 2 Docket Nos. STN 50-498, STN 50-499 Monthly Operating Reports for December 2002 Pursuant to 10CFR50.71(a) and South Texas Project Electric Generating Station (STPEGS) Technical Specification 6.9.1.5, attached are the Monthly Operating Reports for December 2002. If you should have any questions on this matter, please contact R.L.

Hill at (361) 972-7667.

F.H. Mallen Manager, Planning &

Controls Attachments: 1)

STPEGS Unit 1 Monthly Operating Report - December 2002

2)

STPEGS Unit 2 Monthly Operating Report - December 2002

cc:

(paper copy)

(electronic copy)

Ellis W. Merschoff Regional Administrator, Region IV U.S. Nuclear Regulatory Commission 611 Ryan Plaza Drive, Suite 400 Arlington, Texas 76011-8064 U. S. Nuclear Regulatory Commission Attention: Document Control Desk One White Flint North 11555 Rockville Pike Rockville, MD 20852 Richard A. Ratliff Bureau of Radiation Control Texas Department of Health 1100 West 49th Street Austin, TX 78756-3189 Cornelius F. O'Keefe U. S. Nuclear Regulatory Commission P. 0. Box 289, Mail Code: MN116 Wadsworth, TX 77483 A. H. Gutterman, Esquire Morgan, Lewis & Bockius LLP M. T. Hardt/W. C. Gunst City Public Service Mohan C. Thadani U. S. Nuclear Regulatory Commission R. L. Balcom/D. G. Tees Texas Genco, LP A. Ramirez City of Austin C. A. Johnson/A. C. Bakken III AEP - Central Power and Light Company Jon C. Wood Matthews & Branscomb C. M. Canady City of Austin Electric Utility Department 721 Barton Springs Road Austin, TX 78704

SOUTH TEXAS PROJECT ELECTRIC GENERATING STATION UNIT 1 MONTHLY OPERATING REPORT DECEMBER 2002 STP NUCLEAR OPERATING COMPANY NRC DOCKET NO. 50-498 LICENSE NO. NPF-76 Approved By:

E.D. WCLPIN fate

MONTHLY

SUMMARY

South Texas Project Unit 1 operated during the reporting period at full power with no unit shutdowns or significant power reductions.

OPERATING DATA REPORT DOCKET NO.

50-498 UNIT I

DATE Jan. 8, 2003 COMPLETED BY R.L. Hill TELEPHONE 361.972.7667 OPERATING STATUS I.

REPORTING PERIOD: 12/1102-12/31/02 GROSS HOURS IN REPORTING PERIOD: 744

2.

CURRENTLY AUTHORIZED POWER LEVEL (Mwt): 3,853 MAXIMUM DEPENDABLE CAPACITY (MWe-Net): 1,5.

DESIGN ELECTRICAL RATING (MWe-Net): 1,250.6

3.

POWER LEVEL TO WHICH RESTRICTED (IF ANY) (MWe-Net): None

4.

REASONS FOR RESTRICTION (IF ANY): N/A

5.

6.

NUMBER OF HOURS REACTOR CRITICAL REACTOR RESERVE SHUTDOWN HOURS

7.

HOURS GENERATOR ON LINE

8.

UNIT RESERVE SHUTDOWN HOURS

9.

GROSS THERMAL ENERGY GENERATED (MWH)

10.

NET ELECTRICAL ENERGY GENERATED (MWH)

11.

REACTOR SERVICE FACTOR (%)

12.

REACTOR AVAILABILITY FACTOR (%)

13.

UNIT SERVICE FACTOR (%)

14.

UNIT AVAILABILITY FACTOR (%)

15.

UNIT CAPACITY FACTOR - Using MDC (%)

16.

UNIT CAPACITY FACTOR - Using DER (%)

17.

UNIT FORCED OUTAGE RATE (%)

THIS MONTH 744.0 0

744.0 0

2,839,848 953,549 1000 100.0 100.0 100 0 102.5 102.5 0.0 YR TO DATE 0

8,573.4 0

32,652,123 10,867,941 97.9 97.9 97.__99 97.9 99.2 99.2 2.1 CUMULATIVE 98,529.1 0

96,893.1 0

361,950,463 118,216,055 78.3 78.3 77.0 77.0 75.1 75.1 13.4

18. SHUTDOWNS SCHEDULED OVER NEXT 6 MONTHS (TYPE, DATE, & DURATION OF EACH):

Scheduled 22-day outage to allow scheduled refueling to begin on March 26, 2003.

19. IF SHUTDOWN AT END OF REPORT PERIOD, ESTIMATED DATE OF STARTUP: N/A

AVERAGE DAILY UNIT POWER LEVEL DOCKET NO.

50-498 UNIT I

DATE Jan 8, 2003 COMPLETED BY R.L. Hill TELEPHONE 361.972.7667 MONTH DECEMBER DAY DAY AVERAGE DAILY POWER LEVEL (MWe-Net) 1274 1273 1272 1272 1262 1270 1286 1284 1283 1285 1286 1283 1286 1286 1285 1284 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 AVERAGE DAILY POWER LEVEL (MWe-Net) 1284 1284 1272 1287 1286 1285 1283 1284 1286 1286 1285 1286 1285 1284 1285

UNIT SHUTDOWNS AND POWER REDUCTIONS DOCKET NO.

50-498 UNIT 1

DATE Jan. 8, 2003 COMPLETED BY R.L. Hill TELEPHONE 361.972.7667 REPORT MONTH DECEMBER 1

F: Forced S: Scheduled 2

Reason:

A-Equipment Failure (Explain)

B-Maintenance or Test C-Refueling D-Regulatory Restriction E-Operator Training & License Exam F-Administrative G-Operational Error (Explain)

H-Other (Explain) 3 Method:

1-Manual 2-Manual Scram 3-Automatic Scram 4-Cont. of Existing Outage 5-Reduction 9-Other 4

IEEE 805-1983 5

IEEE 803-1983 1

2 3

4 5

No.

Date Type Duration Reason Method of Licensee System Component Cause & Corrective Action to Prevent Recurrence (Hours)

Shutting Event Code Code Down Report #

Reactor THERE WERE NO UNIT SHUTDOWNS OR SIGNIFICANT POWER REDUCTIONS DURING THE REPORTING PERIOD II_

I I

III

PORVS AND SAFETY VALVE

SUMMARY

There were no PORV or Safety Valves challenged during the reporting period.

SOUTH TEXAS PROJECT ELECTRIC GENERATING STATION UNIT 2 MONTHLY OPERATING REPORT DECEMBER 2002 STP NUCLEAR OPERATING COMPANY NRC DOCKET NO. 50-499 LICENSE NO. NPF-80 Approved By:

-r t- /4

/

e E.D. VLPIN Date

MONTHLY

SUMMARY

South Texas Project Unit 2 began the reporting period shutdown for scheduled refueling and steam generator replacement. The unit was returned to service on December 6, at 0509 and full power was achieved on December 13, at 1114.

On December 15, at 1805 the reactor was manually tripped due to a sudden high main turbine vibration. After opening the turbine and condenser, one last row blade on low-pressure (LP) rotor 22 had separated from the rotor causing some collateral damage within LP 22. Numerous last row blade cracks were discovered during visual inspections of the blades on LP 22 and 23.

Additional damage was found on stationary blades in 22, the exhaust flow guide and some condenser tubes. Metallurgical examinations found the cracks as a result of high cycle fatigue.

The unit remained shutdown at the end of the reporting period with repairs ongoing.

OPERATING DATA REPORT DOCKETNO.

50-499 UNIT 2

DATE Jan. 8, 2003 COMPLETED BY R.L. Hill TELEPHONE 361.972.7667 OPERATING STATUS REPORTING PERIOD: 12/1/02-12/31/02 GROSS HOURS IN REPORTING PERIOD: 744 CURRENTLY AUTHORIZED POWER LEVEL (MWt): 3853 MAXIMUM DEPENDABLE CAPACITY (MWe-Net): 1,250.6 DESIGN ELECTRICAL RATING (MWe-Net): 1,250.6 POWER LEVEL TO WHICH RESTRICTED (IF ANY) (MWe-Net): None REASONS FOR RESTRICTION (IF ANY): N/A

5.

NUMBER OF HOURS REACTOR CRITICAL

6.

REACTOR RESERVE SHUTDOWN HOURS

7.

HOURS GENERATOR ON LINE

8.

UNIT RESERVE SHUTDOWN HOURS

9.

GROSS THERMAL ENERGY GENERATED (MWH)

10.

NET ELECTRICAL ENERGY GENERATED (MWH)

11.

REACTOR SERVICE FACTOR (%)

12.

REACTOR AVAILABILITY FACTOR (%)

13.

UNIT SERVICE FACTOR (%)

14.

UNIT AVAILABILITY FACTOR (%)

15.

UNIT CAPACITY FACTOR - Using MDC (%)

16.

UNIT CAPACITY FACTOR - Using DER (%)

17.

UNIT FORCED OUTAGE RATE (%)

THIS MONTH 263.4 0

237.9 0

795,432 257,429 35.4 35.4 32.0 32.0 27.7 27.7 62.1 YR TO DATE 6,743.7 0

6,664.7 0

25,253,119 8,219,846 77.0 77.0 76.1 76.1.

75.0 75.0 7.5 CUMULATIVE 94,557.7 0

92,292.4 0

344,413,651 112,177,967 79.7 79.7 77.8 77.8 75.6 75 6 13.5

18. SHUTDOWNS SCHEDULED OVER NEXT 6 MONTHS (TYPE, DATE, & DURATION OF EACH): N/A
19. IF SHUTDOWN AT END OF REPORT PERIOD, ESTIMATED DATE OF STARTUP: 01/18/03
1.
2.
3.

4.

AVERAGE DAILY UNIT POWER LEVEL DOCKETNO.

50-499 UNIT 2

DATE Jan. 8, 2003 COMPLETED BY R.L. Hill TELEPHONE 361.972.7667 MONTH DECEMBER DAY 1

2 3

4 5

6 7

8 9

10 11 12 13 14 15 16 AVERAGE DAILY POWER LEVEL (MWe-Net) 0 0

0 0

2 294 894 1110 1210 1261 1272 1244 1212 1272 954 0

DAY AVERAGE DAILY POWER LEVEL (MWe-Net) 17 0

18 0

19 0

20 0

21 0

22 0

23 0

24 0

25 0

26 0

27 0

28 0

29 0

30 0

31 0

UNIT SHUTDOWNS AND POWER REDUCTIONS DOCKET NO.

50-499 UNIT 2

DATE Jan. 8, 2003 COMPLETED BY R.L. Hill TELEPHONE 361.972.7667 REPORT MONTH DECEMBER 1

F: Forced S: Scheduled 2

Reason:

A-Equipment Failure (Explain)

B-Maintenance or Test C-Refueling D-Regulatory Restriction E-Operator Training & License Exam F-Administrative G-Operational Error (Explain)

H-Other (Explain) 3 Method:

1-Manual 2-Manual Scram 3-Automatic Scram 4-Cont. of Existing Outage 5-Reduction 9-Other 4

IEEE 805-1983 5

IEEE 803-1983 2

3 4

5 No.

Date Type Duration Reason Method of Licensee System Component Cause & Corrective Action to Prevent Recurrence (Hours)

Shutting Event Code Code Down Report #

Reactor 02-03 021002 5

116.3 C

1 N/A N/A N/A Scheduled outage to allow refueling and steam generator replacement.

02-04 021215 F

389.9 A

2 02-02-005 TA TRB Reactor manually tripped due to a sudden high main turbine vibration. After opening the turbine and condenser, one last row blade on low-pressure (LP) rotor 22 had separated from the rotor causing some collateral damage within LP 22. Numerous last row blade cracks were discovered during visual inspections of the blades on LP 22 and 23. Additional damage was found on stationary blades in 22, the exhaust flow guide and some condenser tubes. Metallurgical examinations found the cracks as a result of high cycle fatigue.

PORVS AND SAFETY VALVE

SUMMARY

There were no PORV or Safety Valves challenged during the reporting period.