FPL 3
JAN 1 3 200/
L-2003-003 10 CFR 50.36 U. S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, D. C. 20555 Re:
Turkey Point Units 3 and 4 Docket Nos. 50-250 and 50-251 Monthly Operating Report - December 2002 In accordance with the requirements of Turkey Point Units 3 and 4 Technical Specification 6.9.1.5, and the guidance of Generic Letter 97-02, attached are the December 2002 Operating Data Reports and Summaries of Operating Experience for Turkey Point Units 3 and 4.
Very truly yours, P.McElwaiI Vice President Turkey Point Plant DRL Attachments NRC Regulatory Issue Summary 2001-05 waived the requirements that multiple copies of documents be submitted to the NRC.
'1k '
an FPL Group company
DOCKET NO.:
UNIT:
DATE:
COMPLETED BY:
TELEPHONE:
50-250 Turkey Point Unit 3 1/2/2003 David Lafleur (305) 246-7150 Reporting Period December, 2002 OPERATING DATA REPORT Design Electrical Rating (MWe-Net) 720giS@> -1irl Maximum Dependable Capacity (MWe-Net) 693 Month Year-to-date Cumulative No. of hours reactor was critical 744 8760 194539.8 No. of hours generator was on line (service hours) 744 8760 192208.5 Unit reserve shutdown hours 0
0 121.8 Net Electrical Energy (MWH) 539129 6215430 125359077 UNIT SHUTDOWNS (1) Reason (2) Method A - Equipment Failure (Explain)
B - Maintenance or Test C - Refueling D - Regulatory Restriction E - Operator Training/License Examination F - Administrative G - Operational Error (Explain)
H - Other 1 - Manual 2 - Manual Trip/Scram 3 - Automatic Trip/Scram 4 - Continuation 5 - Other (Explain)
Summary Of Monthly Operating Experience Unit 3 operated at essentially 100% power for the month of December 2002.
DOCKET NO.:
UNIT:
DATE:
COMPLETED BY:
TELEPHONE:
50-251 Turkey Point Unit 4 1/2/2003 David Lafleur (305) 246-7150 Reporting Period December, 2002 Design Electrical Rating (MWe-Net) 720 j_________________
Maximum Dependable Capacity (MWe-Net) 693 Gobs:
GREttmRER Month Year-to-date Cumulative No. of hours reactor was critical 744 8393.2 191362.7 No. of hours generator was on line (service hours) 744 8370.1 186945.2 Unit reserve shutdown hours 0
0 577.2 Net Electrical Energy (MWH) 536078 5854079 122959090 UNIT SHUTDOWNS (1) Reason (2) Method A - Equipment Failure (Explain)
B - Maintenance or Test C - Refueling D - Regulatory Restriction E - Operator Training/License Examination F - Administrative G - Operational Error (Explain)
H - Other 1 - Manual 2 - Manual Trip/Scram 3 - Automatic Trip/Scram 4 - Continuation 5 - Other (Explain)
Summary Of Monthly Operating Experience Unit 4 operated at essentially 100% power for the month of December 2002.