Relief Request, ASME Section XI, Inservice Inspection Program, RR-IWE9 for Containment Testing
ML030150004
Person / Time
Site: North Anna Dominion icon.png
Issue date: 01/14/2003
From: John Nakoski
NRC/NRR/DLPM/LPD2
To: Christian D
Virginia Electric & Power Co (VEPCO)
Monarque S, NRR/DLPM, 415-1544
References
TAC MB6706
Download: ML030150004 (8)


Text

January 14, 2003 Mr. David A. Christian Senior Vice President - Nuclear Virginia Electric and Power Company 5000 Dominion Blvd.

Glen Allen, Virginia 23060

SUBJECT:

NORTH ANNA POWER STATION, UNIT 2 - ASME SECTION XI, INSERVICE INSPECTION PROGRAM, RELIEF REQUEST (RR) RR-IWE9 FOR CONTAINMENT TESTING (TAC NO. MB6706)

Dear Mr. Christian:

This letter grants the relief you requested in RR-IWE9 for North Anna Power Station, Unit 2.

By letter dated November 14, 2002, as supplemented by letter dated December 6, 2002, Virginia Electric and Power Company proposed an alternative to the containment test requirements of American Society of Mechanical Engineers Code,Section XI, subsections IWE and IWL.

Our evaluation and conclusion are contained in the enclosed Safety Evaluation. The NRC staff has concluded that your proposed alternative provides an acceptable level of quality and safety.

Therefore, pursuant to 10 CFR 50.55a(a)(3)(i), your proposed alternative is authorized on a one-time basis following replacement of the reactor vessel head at North Anna, Unit 2.

The NRC staff has completed its evaluation of this request; therefore, we are closing TAC No.

MB6706.

Sincerely,

/RA/

John A. Nakoski, Chief, Section 1 Project Directorate II Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-339

Enclosure:

As stated cc w/encl: See next page

ML030150004 OFFICE PM:PDII/S1 LA:PDII/S2 EMEB/SC SPLB/SC OGC SC/PDII-1 NAME SMonarque EDunnington DTerao* RLobel** RHoefling** JNakoski DATE 1/14/03 1/14/03 12/20/02 01/09/03 01/13/03 1/14/03 SAFETY EVALUATION BY THE OFFICE OF NUCLEAR REACTOR REGULATION RELIEF REQUEST RR-IWE9 NORTH ANNA POWER STATION, UNIT 2 VIRGINIA ELECTRIC AND POWER COMPANY DOCKET NUMBER 50-339

1.0 INTRODUCTION

By letter dated November 14, 2002 (Ref. 1), as supplemented by letter dated December 6, 2002 (Ref. 2), Virginia Electric and Power Company (the licensee) submitted a request for relief from certain inservice inspection (ISI) requirements of the American Society of Mechanical Engineers (ASME) Boiler and Pressure Vessel Code,Section XI, for North Anna Power Station, Unit 2.

In response to NRC Bulletin 2002-02, Reactor Pressure Vessel Head and Vessel Head Penetration Nozzle Inspection Programs, the licensee performed inspections of the reactor vessel head (RVH) and vessel head penetration (VHP) nozzles at North Anna, Unit 2. Based on the results of those inspections, the licensee decided to replace the RVH during the fall 2002 outage. In order to support the replacement of the RVH, the containment concrete and metallic liner will be cut because the existing equipment hatch is not large enough to accommodate the transfer of the RVHs. After the RVH replacement and containment repair have been completed, appropriate leakage testing is required by ASME Section XI to ensure the pressure integrity of the containment.

In lieu of a Type A test required by ASME Code,Section XI, Subsection IWE-5000, the licensee proposed an alternative of a system pressure test at peak calculated containment pressure (Pa) followed by a local leak rate test to verify the leaktight integrity of the containment repairs. The licensee, in its submittal, stated that a local leak rate test rather than a Type A test is the appropriate test to perform on the metallic liner repair. The licensee indicated that the pre-test and post-test activities associated with a Type A test are far more involved and time consuming than the proposed local leak rate test, and the Type A test provides no additional quality or accuracy.

2.0 REGULATORY EVALUATION

In the Federal Register dated August 8, 1996, the Commission amended Section 50.55a of Title 10 of the Code of Federal Regulations (10 CFR) Section 50.55a to incorporate by reference the 1992 Edition through the 1992 Addenda of the ASME Code,Section XI, Subsections IWE and IWL (Ref. 3). Subsection IWE provides the requirements for ISI of Class MC (metallic containment components) and the metallic liner of Class CC (concrete ENCLOSURE

containment components). Subsection IWL provides the requirements for ISI of Class CC components. The Code of record for North Anna, Unit 2, is the 1992 Edition with the 1992 Addenda.

The regulations require that ISI of certain Code Class MC and CC components be performed in accordance with Section XI of the ASME Code and applicable addenda, except where alternatives have been authorized or relief has been requested by the licensee and granted by the Commission pursuant to paragraphs (a)(3)(i), (a)(3)(ii), or (g)(6)(i) of 10 CFR 50.55a. In proposing alternatives or requesting relief, the licensee must demonstrate that (1) the proposed alternatives provide an acceptable level of quality and safety, (2) compliance would result in hardship or unusual difficulty without a compensating increase in the level of quality and safety, or (3) conformance is impractical for its facility.

By letter dated November 14, 2002, as supplemented by letter dated December 6, 2002, the licensee submitted an alternative to the ASME Code,Section XI ISI requirements pursuant to 10 CFR 50.55a(a)(3)(i). Specifically, in RR-IWE9, the licensee proposed an alternative to the leakage test requirements of ASME Code,Section XI, paragraph IWE-5221. In lieu of performing a Type A test following a major containment repair, the licensee proposed to perform an as-left local leak rate test on the containment liner repair following a containment system pressure test. The NRC staffs evaluation and findings on the licensees proposed alternatives are provided below.

3.0 TECHNICAL EVALUATION

In response to NRC Bulletin 2002-02, the licensee has performed inspections of the RVH and VHP nozzles. Based on the results of those inspections, the licensee decided to replace the RVH during the current outage. To accomplish the head replacement, a portion of the North Anna, Unit 2, containment concrete, reinforcing steel, and metallic liner will be removed. After the reactor heads are moved through the newly created containment access, the metallic liner section will be reattached by welding. Subsequent to reattaching the liner, the reinforcing steel and concrete will be replaced. Following the liner repair and concrete replacement, appropriate leakage testing in accordance with ASME Section XI is required to verify the integrity of the repairs and to return the containment and metallic liner to operable status. Specifically, paragraph IWL-5200 requires a system pressure test at Pa following concrete repair or replacement in order to verify the structure integrity of the concrete placement, and paragraphs IWE-5221 and IWL-5230 require an appropriate leakage test to verify the leaktight integrity of containment liner repair. Paragraph IWL-5230 requires testing as delineated in IWE-5221.

Paragraphs IWE-5221 and IWL-5230 state that repairs and any major modification, replacement of a component that is a part of the primary reactor containment boundary, or resealing a seal welded door, performed after the pre-operational leakage rate test shall be followed by either a Type A, Type B, or Type C test as applicable for the area affected by the modification. Depending on the containment area affected and extent of the repair or modification, the licensee must determine what type of leak rate test is appropriate. A review of containment repair activities at North Anna, Unit 2, indicates that a Type A test may be the most ENCLOSURE

appropriate leakage test because of the magnitude of repair and its potential impact on the containment structural integrity. In general, a Type A test provides useful information about the overall condition of containment and total leakage but would not provide the required information for the specific areas affected by the repair. In order to evaluate and demonstrate the effectiveness and leaktightness of liner repair and welds, a local leak rate test (Type B) may be necessary and sufficient.

However, in lieu of performing either a Type A or a Type B test as required by IWE-5221, the licensee proposes an alternative test that meets the intent of Code requirements to ensure the containment pressure and structural integrity are maintained following repairs, replacements, or modifications. The proposed alternative involves performing a system pressure test of the containment followed by a local leak rate test of the liner repair weld areas. The system pressure test will ensure the overall acceptability of the containment structural integrity and repaired welds. As a part of the proposed test, the licensee will perform a 100-percent visual (VT-1C) examination of the exterior surface of the new concrete prior to, during, and following pressurization. The section of metallic liner that was removed will be rewelded in place in accordance with the original owners requirements. As a minimum, 100-percent surface (liquid penetrant or magnetic particle) and spot volumetric examination will be performed on the pressure boundary containment metallic liner repair welds. In addition, a general and VT-3 visual examination of the new metallic liner pressure boundary weld will be performed in accordance with ASME Code Section XI requirements. Following the completion of the containment pressure test, the metallic liner repair weld will be tested by a local leakage test using a test channel over the new welds. The local leak rate test will be performed in accordance with the standard methods and acceptance criteria as delineated in American National Standards Institute (ANSI)/American Nuclear Society (ANS) 56.8, Containment System Leakage Testing Requirements (Ref. 4). Prior to the containment pressure test, the metallic liner repair weld will also be vacuum-boxed tested and the channel attachment welds will be snoop tested with soap bubbles. These local leakage tests will ensure the leaktightness of test channel and welds.

The NRC staff finds that the proposed system pressure test of the containment at Pa will satisfactorily structurally test the metallic liner repair weld and the newly placed concrete, and the associated inspections will demonstrate the acceptability of the general condition of the containment structure as well as the leaktight integrity of the repaired containment under a design-basis accident. The NRC staff also finds that the proposed local leak rate test and vacuum test will demonstrate the leaktight integrity of the liner repair weld and test channel.

4.0 CONCLUSION

On the basis of the above evaluation, the NRC staff concludes that the proposed alternative meets the intent of both IWE-5221 and IWL-5230, and will satisfactorily test the structure as well as ensure the leaktight integrity of the containment repair. Therefore, the NRC staff concludes that RR-IWE9 provides an acceptable level of quality and safety. Pursuant to 10 CFR 50.55a(a)(3)(i), RR-IWE9 is authorized on a one-time basis following replacement of the reactor vessel head at North Anna, Unit 2.

5.0 REFERENCES

1. Letter from E. Grechek (Dominion) to NRC, ASME Section XI Inservice Inspection Program Relief Request IWE9 Containment Testing, dated November 14, 2002.
2. Letter from E. Grechek (Dominion) to NRC, Request for Additional Information - ASME Section XI Inservice Inspection Program Relief Request IWE9 Containment Testing, dated December 6, 2002.
3. ASME Boiler and Pressure Vessel Code,Section XI, Subsections IWE and IWL, 1992 Edition, including the 1992 Addenda, New York, NY.
4. ANSI/ANS 56.8-1994, Containment System Leakage Testing Requirements.

Principal Contributor: Y. S. Huang Date: January 14, 2003

Mr. David A. Christian North Anna Power Station Virginia Electric and Power Company Units 1 and 2 cc:

Mr. C. Lee Lintecum Mr. David A. Heacock County Administrator Site Vice President Louisa County North Anna Power Station P. O. Box 160 P. O. Box 402 Louisa, Virginia 23093 Mineral, Virginia 23117-0402 Ms. Lillian M. Cuocco, Esq. Mr. Richard H. Blount, II Senior Nuclear Counsel Site Vice President Dominion Nuclear Connecticut, Inc. Surry Power Station Millstone Power Station Virginia Electric and Power Company Building 475, 5 th floor 5570 Hog Island Road Rope Ferry Road Surry, Virginia 23883-0315 Rt. 156 Waterford, Connecticut 06385 Mr. Robert B. Strobe, M.D., M.P.H.

State Health Commissioner Dr. W. T. Lough Office of the Commissioner Virginia State Corporation Virginia Department of Health Commission P. O. Box 2448 Division of Energy Regulation Richmond, Virginia 23218 P. O. Box 1197 Richmond, Virginia 23209 Mr. William R. Matthews Vice President-Nuclear Operations Old Dominion Electric Cooperative Virginia Electric and Power Company 4201 Dominion Blvd. Innsbrook Technical Center Glen Allen, Virginia 23060 5000 Dominion Boulevard Glen Allen, Virginia 23060-6711 Mr. Stephen P. Sarver, Director Nuclear Licensing & Operations Support Virginia Electric Power Company Innsbrook Technical Center 5000 Dominion Blvd.

Glen Allen, Virginia 23060-6711 Office of the Attorney General Commonwealth of Virginia 900 East Main Street Richmond, Virginia 23219 Senior Resident Inspector North Anna Power Station U. S. Nuclear Regulatory Commission 1024 Haley Drive Mineral, Virginia 23117