Summary of 12/11/02, Meeting with Florida Power & Light to Discuss Spent Fuel Pool Related Submittals for Turkey Point, Units 3 & 4 and St. Lucie, Units 1 & 2
ML030130002
Person / Time
Site: Saint Lucie, Turkey Point  NextEra Energy icon.png
Issue date: 01/13/2003
From: Ellen Brown
NRC/NRR/DLPM/LPD2
To:
Florida Power & Light Co
Brown E, NRR/DLPM, 415-2315
References
TAC MB6721, TAC MB6722, TAC MB6723, TAC MB6724
Download: ML030130002 (8)


Text

January 13, 2003 LICENSEE:

Florida Power & Light FACILITIES:

Turkey Point Units 3 and 4 and Saint Lucie Units 1 and 2

SUBJECT:

SUMMARY

OF DECEMBER 11, 2002, MEETING WITH FLORIDA POWER &

LIGHT TO DISCUSS SPENT FUEL POOL RELATED SUBMITTALS (TAC NOS. MB6721, MB6722, MB6723, MB6724)

On December 11, 2002, the U.S. Nuclear Regulatory Commission (NRC) staff met with representatives of Florida Power & Light (FPL) at the NRC Headquarters in Rockville, Maryland.

This meeting was held to discuss recently submitted license applications for Turkey Point Units 3 and 4 and Saint Lucie Units 1 and 2 concerning increased spent fuel pool (SFP) storage within the existing SFP cask areas, and the crediting of soluble boron along with fuel position to maintain reactivity within regulatory limits. The meeting was classified as a Category 2 meeting, which provided an opportunity for members of the public to communicate with the NRC staff after the business portion, but before the meeting was adjourned. Enclosure 1 is a list of attendees and Enclosure 2 is a copy of FPLs handout distributed during the meeting.

The licensee gave a presentation summarizing the current and future efforts for modifications to the SFP as well as the technical and licensing bases. The presentation covered the scope of modifications intended to be made to the SFPs at both facilities and how each submittal affected upcoming outages or influenced other licensing submittals. Additionally, the licensee discussed unique SFP design features. The licensee provided information regarding the timing of pending licensing submittals and their requested need dates for licensing submittals currently under review by the NRC staff. This presentation is included in the aforementioned licensee handout attached to this summary.

The NRC staff provided some editorial comments and asked several clarification questions regarding the Saint Lucie cask pit spent fuel storage rack submittal. The NRC staff indicated its intention to transmit more specific questions at a later date.

At the conclusion of the business meeting, comments were solicited from members of the public, but there were none. The staff noted that the above meeting was beneficial in gaining an understanding of FPLs plans and activities regarding SFP modifications for both facilities.

/RA/

Eva A. Brown, Project Manager, Section 2 Project Directorate II Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket Nos. 50-250 and 50-251 50-335 and 50-389

Enclosures:

As stated cc w/encls: See next page

ML030130002 OFFICE PDII-2\\PM PDII-2\\LA PDII-2\\SC NAME EBrown BClayton AHowe DATE 01/03/03 01/03/03 01/10/03

Distribution:

PUBLIC PDII-2 R/F JZwolinski/LMarsh HBerkow AHowe EBrown BClayton (hard copy)

OGC ACRS DJackson VKlein RGiardina RTaylor JOrtego-Luciano EForrest MKowal LWert, RII SRosenberg (e-mail)

MKotzalas

ATTENDANCE LIST NUCLEAR REGULATORY COMMISSION STAFF MEETING WITH FLORIDA POWER AND LIGHT AT NRC HEADQUARTERS DECEMBER 11, 2002 NRC FPL Allen Howe Carl Bible Eva Brown Ken Frehafer Diane Jackson Glen Adams Veronica Klein Yuan Kao Robert Giardina Carl OFarrill Mark Kowal Peter Sharp Ed Forrest Jonathan Ortego-Luciano Robert Taylor Others Norman Simms Stetam Anion Scott Pellet ENCLOSURE 1

Florida Power and Light Company ST. LUCIE PLANT TURKEY POINT PLANT cc:

Mr. J. A. Stall Senior Vice President, Nuclear and Chief Nuclear Officer Florida Power and Light Company P.O. Box 14000 Juno Beach, Florida 33408-0420 Senior Resident Inspector St. Lucie Plant U.S. Nuclear Regulatory Commission P.O. Box 6090 Jensen Beach, Florida 34957 Craig Fugate, Director Division of Emergency Preparedness Department of Community Affairs 2740 Centerview Drive Tallahassee, Florida 32399-2100 M. S. Ross, Attorney Florida Power & Light Company P.O. Box 14000 Juno Beach, FL 33408-0420 John P. McElwain, Site Vice President Turkey Point Nuclear Plant Florida Power and Light Company 9760 SW. 344th Street Florida City, FL 33035 Douglas Anderson County Administrator St. Lucie County 2300 Virginia Avenue Ft. Pierce, Florida 34982 Mr. R. E. Rose Plant General Manager St. Lucie Nuclear Plant 6351 South Ocean Drive Jensen Beach, Florida 34957 Walter Parker Licensing Manager Turkey Point Nuclear Plant 9760 SW. 344th Street Florida City, FL 33035 Mr. William A. Passetti, Chief Department of Health Bureau of Radiation Control 2020 Capital Circle, SE, Bin #C21 Tallahassee, Florida 32399-1741 Mr. Donald E. Jernigan Site Vice President St. Lucie Nuclear Plant 6351 South Ocean Drive Jensen Beach, Florida 34957 Attorney General Department of Legal Affairs The Capitol Tallahassee, Florida 32304 Senior Resident Inspector Turkey Point Nuclear Plant U.S. Nuclear Regulatory Commission 9762 SW. 344th Street Florida City, Florida 33035 T. O. Jones, Plant General Manager Turkey Point Nuclear Plant Florida Power and Light Company 9760 SW. 344th Street Florida City, FL 33035 County Manager Miami-Dade County 111 NW 1 Street, 29th Floor Miami, Florida 33128 Mr. Kelly J. Korth Licensing Manager St. Lucie Nuclear Plant 6351 South Ocean Drive Jensen Beach, Florida 34957 Mr. William Jefferson Vice President, Nuclear Operations Support P.O. Box 14000 Juno Beach, FL 33408-0420 Mr. Rajiv S. Kundalkar Vice President - Nuclear Engineering Florida Power & Light Company P.O. Box 14000 Juno Beach, FL 33408-0420 Mr. J. Kammel Radiological Emergency Planning Administrator Department of Public Safety 6000 SE.

Tower DriveStuart, Florida 34997