MEntergy Entergy Nuclear Northeast Entergy Nuclear Operations, Inc Indian Point Energy Center 295 Broadway, Suite 1 PO Box 249 Buchanan, NY 10511-0249 December 13, 2002 IPN-02-094 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Mail Stop O-P1-17 Washington, D.C. 20555-0001
Subject:
Indian Point 3 Nuclear Power Plant Docket No. 50-286 License No. DPR-64 Monthly Operating Report for November 2002
Dear Sir:
The attached monthly operating report, for the month of November 2002, is hereby submitted in accordance with Indian Point 3 Nuclear Power Plant Technical Specification 5.6.4.
Indian Point 3 is making no commitments in this letter.
VVery trul ur oberat.ar Vice esident, Operatrions Indi n Point 3 NuwcleraPower Plant cc: See next page c::ýi5aý4
Docket No. 50-286 IPN-02-094 Page 2 of 2 Attachment cc:
Mr. Hubert J. Miller Regional Administrator Region I U.S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, Pennsylvania 19406-1415 Resident Inspector's Office U.S. Nuclear Regulatory Commission Indian Point 3 Nuclear Power Plant P.O. Box 337 Buchanan, NY 10511-0337 U.S. Nuclear Regulatory Commission ATTN: Director, Office of Information Resource Management Washington, D.C. 20555 INPO Records Center 700 Galleria Parkway Atlanta, Georgia 30339-5957 Mr. Paul Eddy State of New York Department of Public Service 3 Empire Plaza Albany, NY 12223
DOCKET NO.
UNIT:
DATE:
COMPLETED BY:
TELEPHONE NO:
LETTER NO:
,50-286 Indian Point 3 12-04-02 T. Orlando (914) 736-8340 IPN-02-094 ATTACHMENT PAGE 1 of 4 OPERATING DATA REPORT OPERATING STATUS Unit Name:
Indian Point No. 3 Nuclear Power Plant Reporting Period:
November 2002 Licensed Thermal Power (MWt):
3025 Nameplate Rating (Gross MWe):
1013 Design Electrical Rating (Net MWe):
965 Maximum Dependable Capacity (Gross MWe):
1000 Maximum Dependable Capacity (Net MWe):
965 If Changes Occur in Capacity Ratings (Items Number 3 through 7) Since Last Report Give Reasons:
- 9.
Power Level to Which Restricted, If Any (Net MWe):
- 10.
Reasons for Restrictions, If Any:
- 11.
Hours In Reporting Period
- 12.
Number Of Hours Reactor Was Critical
- 13.
Reactor Reserve Shutdown Hours
- 14.
Hours Generator On-Line
- 15.
Unit Reserve Shutdown Hours
- 16.
Gross Thermal Energy Generated (MWH)
- 17.
Gross Electrical Energy Generated (MWH)
- 18.
Net Electrical Energy Generated (MWH)
- 19.
Unit Service Factor
- 20.
Unit Availability Factor
- 21.
Unit Capacity factor (Using MDC Net)
- 22.
Unit Capacity Factor (Using DER Net)
- 23.
Unit Forced Outage Rate This Month 720 591.05 0
571.23 0
1,703,188 572,993 534,907 79.3 79.3 79.9 79.9 20.7 Yr-to-Date 8,016 7,987.05 0
7,967.23 0
23,737,428 7,988,260 7,727,667 98.1 98.1 99.9 99.9 1.9 Cumulative 230,537 145,494.78 0
142,664.23 0
410,568,368 131,871,723 127,331,892 61.9 61.9 58.0*
57.2 23.1
- 24.
Shutdowns Scheduled Over Next 6 Months (Type, Date and Duration of Each): Refueling scheduled to commence March 28, 2003. Duration: 22 days Outaae 12 is
- 25.
If Shut Down At End Of Report Period. Estimated Date of Startup:
- 26.
Units In Test Status (Prior to Commercial Operation):
INITIAL CRITICALITY INITIAL ELECTRICITY COMMERCIAL OPERATION Weighted Average
- 1.
- 2.
- 3.
- 4.
- 5.
- 6.
- 7.
8.
Forecast Achieved Outaae 12 is
DOCKET NO.
50-286 UNIT:
Indian Point 3 DATE:
12-04-02 COMPLETED BY: T. Orlando TELEPHONE NO: (914) 736-8340 LETTER NO:
IPN-02-094 ATTACHMENT PAGE 2 of 4 AVERAGE DAILY UNIT POWER LEVEL MONTH November 2002 AVERAGE DAILY POWER DAY 986 986 986 986 986 986 987 988 988 989 988 988 988 989 410 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 AVERAGE DAILY POWER LEVEL (MWe-Net) 0 0
0 0
88 908 982 984 986 988 988 988 989 988 1
2 3
4 5
6 7
8 9
10 11 12 13 14 15 16 INSTRUCTIONS:
On this format, list the average daily unit power level in MWe-Net for each day in the reporting month. Compute to the nearest whole megawatt.
DAY 0
DOCKET NO.
UNIT:
DATE:
COMPLETED BY:
TELEPHONE NO.
LETTER NO:
ATTACHMENT PAGE 3 of 4 50-286 Indian Point 3 12-04-02 T. Orlando (914) 736-8340 IPN-02-094 UNIT SHUTDOWNS AND POWER REDUCTIONS REPORT MONTH November 2002 1
F: Forced S: Scheduled 2
3 Reason:
Method:
A-Equipment 1-Manual B-Maintenance or Test 2-Manual Scram C-Refueling 3-Automatic Scram D-Regulatory Restriction 4-Other (Explain)
E-Operator Training & Licensee Examination F-Administrative G-Operational Error H-Other (Explain) 4 5
Exhibit G - Instructions Exhibit 1 for Preparation of Data Same Source Entry Sheets for Licensee Event Report (LER) File (NUREG - 0161)
METHOD OF NO.
DATE TYPE DURATION REASON SHUTTING LICENSEE SYSTEM COMPONENT CAUSE & CORRECTIVE ACTION TO 1
(HOURS) 2 DOWN EVENT CODE CODE PREVENT RECURRENCE REACTOR 3 REPORT#
4 5
2 021115 F
148.77 A
3 2002-003-00 XX XXXXXX Automatic reactor shutdown due to a failure of 345 kv Main Output breaker No. 3 located in the Buchanan Switchyard.
DOCKET NO.
50-286 UNIT:
Indian Point 3 DATE:
12-04-02 COMPLETED BY:
T. Orlando TELEPHONE NO.:
(914) 736-8340 LETTER NO.
IPN-02-094 ATTACHMENT PAGE 4 of 4
SUMMARY
OF OPERATING EXPERIENCE November 2002 The Indian Point Unit No. 3 Nuclear Power Plant was synchronized to the bus for a total of 571.23 hours2.662037e-4 days <br />0.00639 hours <br />3.80291e-5 weeks <br />8.7515e-6 months <br />, producing a gross electrical energy generation of 572,993 MWH.
On November 15, at 0957 hours0.0111 days <br />0.266 hours <br />0.00158 weeks <br />3.641385e-4 months <br />, the unit experienced an automatic reactor shutdown due to failure of the 345 kv Main Output Breaker No. 3, and subsequent trip of remaining Main Output Breakers 1, 5 and 6, located offsite in the Buchanan switchyard. The plant was stabilized in Mode 3 (hot standby). On November 16, the reactor was brought critical (Mode 2) at 1239 hours0.0143 days <br />0.344 hours <br />0.00205 weeks <br />4.714395e-4 months <br />, in preparation for plant restart. Assessment of 345 kv Main Output Breaker No. 1, which would be relied upon to carry the plant output, determined that maintenance and inspections would take several days and the reactor was manually shutdown at 1819 hours0.0211 days <br />0.505 hours <br />0.00301 weeks <br />6.921295e-4 months <br />, and the plant re entered Mode 3.
Following successful maintenance and testing of 345 kv Main Output Breaker No. 1, the reactor was brought critical on November 21, at 0034 hours3.935185e-4 days <br />0.00944 hours <br />5.621693e-5 weeks <br />1.2937e-5 months <br />, and the unit was synchronized to the bus at 1443 hours0.0167 days <br />0.401 hours <br />0.00239 weeks <br />5.490615e-4 months <br />. The unit achieved full power on November 22, at approximately 1045 hours0.0121 days <br />0.29 hours <br />0.00173 weeks <br />3.976225e-4 months <br />, and remained on line at full power for the remainder of the reporting period.