PROPOSED AGENDA NRC LICENSE RENEWAL STEERING COMMITTEE MEETING WITH NEI AND THE LICENSE RENEWAL APPLICANTS November 4, 2002 (Times are approximate)

I. Meeting Between the NRC License Renewal Steering Committee and NEI License Renewal Working Group A. Status of applications 1:00-1:40 p.m.

(1) Surry 1 & 2 and North Anna 1 & 2 Virginia Elec. & Power (2) McGuire 1 & 2 and Catawba 1 & 2 Duke Energy (3) Peach Bottom 2 & 3 Exelon (4) St. Lucie 1 & 2 Florida Power & Light (5) Fort Calhoun Omaha Public Power District (6) H.B. Robinson 2 Progress Energy (7) R.E. Ginna Rochester Gas & Electric (8) Virgil C. Summer South Carolina Electric & Gas B. License renewal interest NRC 1:40-1:45 p.m.

C. Lessons learned and license renewal NEI/NRC 1:45-2:15p.m.

guidance development (1) NRC - NEI workshop (2) Generic renewal application format (3) Guidance document update process (4) Environmentally assisted fatigue D. Public participation Members of the public 2:15-2:30 p.m.

E. Summary NRC 2:30-2:35 p.m.

Break 2:35 - 2:45 p.m.

II. Meeting Between NRC Management and Lcense Renewal Applicants A. Status of applications 2:45-3:45 pm (1) Surry 1 & 2 and North Anna 1 & 2 Virginia Elec. & Power / NRC (2) McGuire 1 & 2 and Catawba 1 & 2 Duke Energy / NRC (3) Peach Bottom 2 & 3 Exelon / NRC (4) St. Lucie 1 & 2 Florida Power & Light / NRC (5) Fort Calhoun Omaha Public Power District/NRC (6) H.B. Robinson 2 Progress Energy (7) R.E. Ginna Rochester Gas & Electric (8) Virgil C. Summer South Carolina Electric & Gas B. Public Participation Members of the public 3:45-4:00 p.m.

C. Adjourn 4:00 p.m.

Enclosure 1

Projected Schedule of License Renewal Applications Through FY05 FY 01 FY02 FY03 FY04 FY05 Slot Plant Submit 1Q 2Q 3Q 4Q 1Q 2Q 3Q 4Q 1Q 2Q 3Q 4Q 1Q 2Q 3Q 4Q 1Q 2Q 3Q 4Q FY01 1 North Anna 1,2 May-01 2 Surry 1,2 May-01 3 Catawba 1, 2 Jun-01 4 McGuire 1,2 Jun-01 5 Peach Bottom2,3 Jul-01 FY02 1 St. Lucie 1,2 Nov-01 2 Fort Calhoun Jan-02 3 Robinson 2 Jun-02 4 Ginna Aug-02 5 Summer Aug-02 FY03 1 Dresden 2,3 Jan-03 2 Quad Cities 1,2 Jan-03 3 Unannounced Jul-03 4 Farley 1,2 Sep-03 5 ANO-2 Sep-03 FY04 1 Nine Mile Pt. 1,2 Oct-03 2 D.C. Cook 1,2 Nov-03 3 Browns Ferry 2,3 Dec-03 4 Brunswick 1,2 2Q 5 Millstone 2,3 Jan-04 6 Beaver Valley 1,2 Sep-04 FY05 1 Unannounced Oct-04 2 Davis-Besse 1 Dec-04 3 Pilgrim 1 Dec-04 4 Unannounced Dec-04 5 Susquehanna 1,2 2Q 6 Unannounced 2Q Date: October 29, 2002 Application under review - NO HEARING (22 months)

Application under review - Opportunity for HEARING PENDING (30 months)

Application under review - Opportunity for HEARING GRANTED (30 months)

Planned Applications - Schedule WITHOUT HEARING (22 months) 2

NORTH ANNA, UNITS 1 AND 2 SURRY, UNITS 1 AND 2 LICENSE RENEWAL REVIEW STATUS RECENT ACCOMPLISHMENTS Received responses to safety requests for additional information (RAIs) 2/5/02 Scoping inspection 2/8/02 Issued draft supplemental environmental impact statement (SEIS) 4/3/02 and 4/23/02 (Surry & North Anna)

Completed aging management review (AMR) inspection (Surry & North Anna) 5/17/02 Public meeting on Surry and North Anna draft SEISs 5/29/02 and 6/25/02 Issued safety evaluation report (SER) with open items 6/6/02 Advisory Committee on Reactor Safeguards (ACRS) subcommittee 7/9/02 meeting on SER with open items Received responses to SER open items 7/25/02 Completed final inspection 9/25/02 3

NORTH ANNA, UNITS 1 AND 2 SURRY, UNITS 1 AND 2 LICENSE RENEWAL REVIEW STATUS FUTURE ACTIVITIES Issue SER 11/5/02 ACRS full committee meeting on SER 12/5/02 ACRS recommendation letter 12/13/02 Issue Surry and North Anna final SEISs 12/13/02 Staff recommendation on renewed license 3/21/03 License renewal decision 3/28/03 4

MCGUIRE, UNITS 1 AND 2 CATAWBA, UNITS 1 AND 2 LICENSE RENEWAL STATUS RECENT ACCOMPLISHMENTS Public meetings to discuss McGuire and Catawba draft SEISs 6/12/02 and 6/27/02 Completed AMR inspections 7/26/02 Issued SER with open items 8/14/02 ASLB order to hold proceeding actions (discovery) in abeyance 8/28/02 Received interim responses to SER with open items 10/2/02 ACRS subcommittee meeting on SER with open items 10/8/02 ACRS full committee meeting on SER with open items 10/10/02 Receive responses to SER with open items 10/28/02 5

MCGUIRE, UNITS 1 AND 2 CATAWBA, UNITS 1 AND 2 LICENSE RENEWAL STATUS FUTURE ACTIVITIES Complete final inspection (if needed) 11/29/02 Issue SER 1/6/03 Issue McGuire and Catawba final SEISs 1/17/03 Regional Administrators letter 1/17/03 ACRS full committee meeting on SER 2/6/03 ACRS letter 2/14/03 6

PEACH BOTTOM, UNITS 2 AND 3 LICENSE RENEWAL STATUS RECENT ACCOMPLISHMENTS Safety RAIs issued 3/12/02 Scoping inspection completed 4/23/02 Safety RAI responses received 5/22/02 Draft SEIS issued 7/5/02 Public meeting to discuss draft SEIS 7/31/02 AMR inspection completed 8/15/02 SER with open items issued 9/13/02 ACRS subcommittee meeting on SER with open items 10/30/02 7

PEACH BOTTOM, UNITS 2 AND 3 LICENSE RENEWAL STATUS FUTURE ACTIVITIES ACRS full committee meeting on SER with open items 11/7/02 Receive responses to SER open items 11/29/02 Begin final inspection 12/9/02 Issue SER 2/6/03 Issue final SEIS 2/7/03 Regional Administrator letter 2/19/03 ACRS subcommittee meeting on SER 2/24/03 ACRS full committee meeting on SER 3/6/03 8

ST. LUCIE, UNITS 1 AND 2 LICENSE RENEWAL STATUS RECENT ACCOMPLISHMENTS Environmental RAIs issued 5/7/02 Environmental RAI responses received 6/25/02 Safety RAIs issued 7/29/02 Safety RAI responses received 10/11/02 Scoping inspection completed 10/25/02 Draft SEIS issued 11/1/02 9

ST. LUCIE, UNITS 1 AND 2 LICENSE RENEWAL STATUS FUTURE ACTIVITIES Public meeting on draft SEIS 12/4/02 Complete AMR inspection 2/7/03 Issue SER with open items 2/7/03 ACRS subcommittee meeting on SER with open items 3/03 ACRS full committee meeting on SER with open items 4/03 Complete final inspection 6/2/03 Issue final SEIS 6/30/03 Issue SER 7/8/03 10

FORT CALHOUN LICENSE RENEWAL STATUS RECENT ACCOMPLISHMENTS Hearing requests and petitions to intervene ended 5/22/02 Environmental scoping meeting 6/18/02 SEIS scoping period ended 7/10/02 Scoping and screening methodology audit 7/11/02 Environmental RAIs issued to applicant 7/17/02 Environmental RAI responses issued to NRC 9/18/02 Safety RAIs issued to applicant 10/11/02 11

FORT CALHOUN LICENSE RENEWAL STATUS FUTURE MILESTONES Scoping inspection 11/8/02 Responses to safety RAIs issued by applicant 12/20/02 Draft SEIS to EPA, issue notice of availability 1/17/03 AMR inspection 1/24/03 FCS LESSONS LEARNED License renewal lessons learned (including lessons from GALL/SRP demonstration project and reviews of GALL/SRP plants) shared with industry during License Renewal Workshop (October, 2002) 12

ROBINSON LICENSE RENEWAL STATUS RECENT ACCOMPLISHMENTS License renewal application received 6/17/02 Acceptance, docketing, & issuance of review schedule 8/16/02 Deadline for hearing requests and petitions to intervene 9/19/02 Scoping and screening methodology audit 9/20/02 Environmental scoping meeting 9/25/02 SEIS scoping period ended 10/25/02 13

ROBINSON LICENSE RENEWAL STATUS FUTURE ACTIVITIES Issue environmental RAIs 12/2/02 Receive environmental RAI responses 1/20/03 Issue safety RAIs 2/11/03 Receive safety RAI responses 4/11/03 Complete scoping inspection 5/03 Issue draft SEIS 5/16/03 Public meeting on draft SEIS 6/03 Complete AMR inspection 7/03 Issue SER with open items 8/25/03 14

GINNA LICENSE RENEWAL STATUS RECENT ACCOMPLISHMENTS Received license renewal application 8/1/02 Acceptance - docketing, issuance of review schedule 8/30/02 Issued FRN for hearing opportunity 9/30/02 Issued FRN for environmental scoping meeting 10/10/02 Deadline for hearing requests and petitions to intervene 10/30/02 FUTURE ACTIVITIES Environmental scoping meeting 11/6/02 SEIS scoping period ends 12/11/02 Complete scoping and screening methodology audit 12/13/02 15

GINNA LICENSE RENEWAL STATUS FUTURE ACTIVITIES (CONTINUED)

Issue environmental RAIs 1/15/03 Receive environmental RAI responses 3/14/03 Issue safety RAIs 3/28/03 Receive safety RAI responses 6/12/03 Issue draft SEIS 6/25/03 Complete scoping inspection 6/27/03 Complete AMR inspection 8/15/03 Public meeting on draft SEIS 8/03 Issue SER with open items 10/9/03 16

SUMMER LICENSE RENEWAL STATUS RECENT ACCOMPLISHMENTS FRN published for receipt & availability 10/4/02 FRN published for intent/environmental scoping meeting 10/25/02 Deadline for hearing requests and petitions to intervene 11/4/02 17

SUMMER LICENSE RENEWAL STATUS FUTURE ACTIVITIES Environmental scoping meeting 12/12/02 SEIS scoping period ends 12/27/02 Scoping and screening methodology audit 1/31/03 Issue environmental RAIs 2/14/03 Receive environmental RAI responses 3/28/03 Issue safety RAIs 4/2/03 Complete scoping inspection 5/16/03 Receive safety RAI responses 6/17/03 18