October 2002 Monthly Operating Report for R.E. Ginna
ML023190062
Person / Time
Site: Ginna Constellation icon.png
Issue date: 11/08/2002
From: Widay J
Rochester Gas & Electric Corp
To: Clark R
Document Control Desk, NRC/NRR/DLPM/LPD1
References
Download: ML023190062 (3)


Text

6S RZ An Energy East Company ROCHESTER GAS AND ELECTRIC CORPORATION

  • 89 EASTAVENUE, ROCHESTER, NY 14649-0001
  • 585 546-2700 www rge corn November 8, 2002 US Nuclear Regulatory Commission Document Control Desk Attn:

Robert Clark Project Directorate I-1 Washington, DC 20555

Subject:

Monthly Report for October, 2002 Operating Status Information R.E. Ginna Nuclear Power Plant Docket No. 50-244

Dear Mr. Clark:

Pursuantto Ginna Improved Technical Specifications Section 5.6.4, attached is the monthly operating status report for Ginna Station for the month of October, 2002.

Very truly yours,

ýsh A. Wida'y ý Plant Manager xc:

U.S. Nuclear Regulatory Commission Mr. Robert Clark (Mail Stop O-8E9)

Project Directorate I-1 Washington, D.C. 20555 U.S. Nuclear Regulatory Commission Region I 475 Allendale Road King of Prussia, PA 19406 U.S. NRC Ginna Senior Resident Inspector Attachments

OPERATING DATA REPORT 50-244 November 8, 2002 COMPLETED BY:

KiiA

/

John V. Walden TELEPHONE (585) 771-3588 OPERATING STATUS Unit Name:

R.E. GINNA NUCLEAR POWER PLANT Reporting Period:

October, 2002 Design Electric Rating (Net MWe):

470 Maximum Dependable Capacity (Net MWe):

480 Number of hours Reactor Was Critical Hours Generator On-line Unit Reserve Shutdown Hours Net Electrical Energy Generated (MWH)

This Month 745.0 745.0 0.0 366814.0 Yr.-to-Date 6530.7 6489.0 0.0 3116813.2 Cumulative**

237552.9 234395.1 8.5 106602374.0

  • CUMULATIVE TOTAL COMMENCING NOVEMBER 8,1969
    • CUMULATIVE TOTAL COMMENCING NOVEMBER 8,1969 1.
2.
3.

4.

Notes:

5.
6.
7.

8.

DOCKET NO: 50-244 UNIT NAME: R.E. GINNA NUCLEAR POWER PLANT DATE: November 8. 2002 COMPLETED BY: John V. Walden TELEPHONE: (585) 771-3588 UNIT SHUTDOWN REPORTING PERIOD:

October, 2002 (Month/Year)

II SU NO.

DATE TYPE DURATION REASONW1 )

METHOD OF CAUSE/CORRECTIVE ACTIONS F: FORCED (HOURS)

SHUTTING S: SCHEDULED DOWN(2)

COMMENTS IMMARY:

The unit operated at full power for the entire month of October. Average power for the month of October was 99 6%.

(1) Reason A - Equipment Failure (Explain)

B - Maintenance or Test C - Refueling D - Regulatory Restriction E - Operator Tralning/Ucense Examination F - Administrative G - Operational Error (Explain)

H - Other (Explain)

(2) Method 1 - Manual 2 - Manual Trip/Scram 3 - Automatic Trip/Scram 4 - Continuation 5 - Other (Explain)