ML023110231

From kanterella
Jump to navigation Jump to search
Attachment 2 - 11/06/02 Memo to C.L. Miller Frm. M.J. Ross-Lee Summary of the August 21, 2002, Meeting Between the Nuclear Regulatory Commission Staff and Dominion Virginia Power
ML023110231
Person / Time
Site: Surry, North Anna  Dominion icon.png
Issue date: 08/21/2002
From:
NRC/NMSS/SFPO
To:
Virginia Electric & Power Co (VEPCO)
Shared Package
ML023100419 List:
References
Download: ML023110231 (15)


Text

++*Dominion+

Spent Fuel Storage Update Surry and North Anna Power Stations August 21, 2002

.,Dominion Spent Fuel Storage Update

  • Surry:

- 45 Dry Storage Casks at ISFSI a 1150 Fuel Assemblies in Dry Storage

  • North Anna:

- 13 Dry Storage Casks at ISFSI

  • 416 Fuel Assemblies in Dry Storage
  • Additional TN-32 Loading This Week

I.

'ý-4JFDominion+

Spent Fuel Storage Update Corrective Actions -Seal Failure and Bolting

- Surry:

"* Conax connectors replaced on all TN-32s

"* Desiccant placed under protective covers on TN-32s

  • Silver jacket o-rings will be installed during future TN-32 loadings
  • Nine of eleven protective covers replaced and bolts re-torqued at the pad e Protective cover replacement project to be completed in 2002
  • Dominion Spent Fuel Storage Update Corrective Actions -Seal Failure and Bolting North Anna:

"* Conax connectors acceptable at North Anna

"* Desiccant will be installed during protective cover replacement project

"* Silver jacket o-rings will be installed during future TN-32 loadings

"* Four out of nine protective covers replaced and bolts re-torqued at the pad

"* Protective cover replacement project to be completed in 2003

Dominionw Spent Fuel Storage Update

  • North Anna Burnup/Enrichment TS Amendment

- Submittal May 2002

- Permit TN-32 casks at North Anna to store fuel with the following limits:

  • 4.3 initial weight percent U-235
  • 45,000 MWdIMtU burnup
  • 1.02 kW heat load

- Request approval by May 2003

+,4"Dominion Spent Fuel Storage Update Storage of Fuel With Cladding Defects

- Intend to clarify language in TN-32 SER for storage of fuel having cladding defects less than pinholes or hairline cracks

- Considering submitting an amendment for engineered storage of fuel having cladding defects greater than pinholes or hairline cracks

- Needed to increase inventory of fuel assemblies that are acceptable for dry storage

"Dominion Spent Fuel Storage Update Clarification of Surry TN-32 Cask Spacing

- Amendment to permit higher burnup, enrichment, and heat load in TN-32 casks at Surry issued in October 2000

- Spacing previous to amendment was 16-feet nominal, center-to-center

- Spacing requirement with amendment is 16 feet minimum, center-to-center (tech. spec.)

No language in October 2000 licensing basis to "grandfather" TN-32s loaded prior to amendment

- Plan to submit letter for clarification

SlDominiop TN-32 TSAR/FSAR Licensing Basis Evaluation

- The FSAR Rev. 0 requirements meet or exceed the design and fabrication requirements of TSAR Rev. 9A

- Surry and North Anna ISFSI FSARs were changed via 72.48 to reconcile differences

ominion Spent Fuel Storage Update TN-32 TSAR/FSAR Licensing Basis Evaluation

- Present description of TN-32 casks in licensing basis found in TN-32 TSAR, Rev 9A

- Current purchase of 22 TN-32 casks uses fabrication/design of TN-32 FSAR, Rev. 0

- A thorough review of the differences between TN-32s described in TSAR Rev. 9A and FSAR Rev.0 is completed

2002 DryStorage System Procurement Results A

Dominion,

Scope of Supply e Dry Storage Needed at Surry from 2005 to 2010

  • Dry Storage Needed at North Anna from 2007 to 2010
  • Option for Storage Needed at Both Stations from 2010 to 2015

..oma~nso

Domini nk Key Issues

"* Storage of High Burnup / High Heat Fuel

"* Storage of Fuel with Cladding Defects

"* Dual Purpose - Storage and Transport

"* Use of General License Vs. Site Specific License

rp.

Chosen System NUHOMS Modules and 32 PTH Canisters

"° Moving to a Canister-Based System is a New Approach at Surry and North Anna

"* Will Be Using This System under Part 72 General License

Schedule

"* Complete Construction of Pad and Delivery of Modules, Canisters and Transfer Cask in First Quarter of 2005

"* Conduct Dry Run During Summer of 2005

"* Load First Canisters in Late 2005 and Early 2006

V Do 0 0io Schedule

"* Complete Construction of Pad and Delivery of Modules, Canisters and Transfer Cask in Fourth Quarter of 2006

"* Conduct Dry Run During Second Quarter of 2007

"* Load First Canisters in Second and Fourth Quarters of 2007