MONTHYEARPMNS20211401, Meeting with Energy Harbor Nuclear Corp. (Ehnc) Regarding a Proposed Alternative to Certain Steam Generator Inspection Requirements at Davis-Besse Nuclear Power Station, Unit No. 12021-10-27027 October 2021 Meeting with Energy Harbor Nuclear Corp. (Ehnc) Regarding a Proposed Alternative to Certain Steam Generator Inspection Requirements at Davis-Besse Nuclear Power Station, Unit No. 1 ML15183A4792015-07-0101 July 2015 Ltr. 07/01/15 D.C. Cook U.S. Nuclear Regulatory Commission Region III 2015 Operator Licensing Workshop (Public Meeting)(Drm) ML15182A4412015-07-0101 July 2015 Notice and Agenda - 2015 Operator Licensing Workshop ML15183A3862015-07-0101 July 2015 Ltr. 07/01/15 Prairie Island U.S. Nuclear Regulatory Commission Region III 2015 Operator Licensing Workshop (Public Meeting) (Drm) ML15183A3992015-07-0101 July 2015 Ltr. 07/01/15 Point Beach U.S. Nuclear Regulatory Commission Region III 2015 Operator Licensing Workshop (Public Meeting) (Drm) ML15183A4632015-07-0101 July 2015 Ltr. 07/01/15 Monticello U.S. Nuclear Regulatory Commission Region III 2015 Operator Licensing Workshop (Public Meeting) (Drm) ML15183A4842015-07-0101 July 2015 Ltr. 07/01/15 Davis-Besse U.S. Nuclear Regulatory Commission Region III 2015 Operator Licensing Workshop (Public Meeting) (Drm) ML15183A4782015-07-0101 July 2015 Ltr. 07/01/15 Duane Arnold U.S. Nuclear Regulatory Commission Region III 2015 Operator Licensing Workshop (Public Meeting) (Drm) ML15183A4722015-07-0101 July 2015 Ltr. 07/01/2015 Fermi U.S. Nuclear Regulatory Commission Region III 2015 Operator Licensing Workshop (Public Meeting) (Drm) ML15183A4452015-07-0101 July 2015 Ltr. 07/01/15 Perry U.S. Nuclear Regulatory Commission Region III 2015 Operator Licensing Workshop (Public Meeting) (Drm) ML14169A4772014-06-13013 June 2014 Operator License Workshop Invitation ML14077A1052014-03-18018 March 2014 March 25, 2014, Notice of Category 3 Forthcoming Meetings to Discuss the Draft Supplemental Environmental Impact Statement for the License Renewal of Davis-Besse, Unit 1 ML13280A9062013-10-21021 October 2013 Forthcoming Meeting with Firstenergy Nuclear Operating Company (FENOC) to Discuss Voluntary Risk Informed Fire Protection Amendment for Davis-Besse ML13252A1712013-09-0909 September 2013 9/24/13 - Notice of Public Meeting - Firstenergy Nuclear Operating Company (Fenoc)(Beaver Valley, Perry, and Davis-Besse) ML12269A0612012-09-26026 September 2012 FENOC Presentation for 2012-09-26 Public Meeting ML12158A4002012-06-0808 June 2012 6/26/2012 Forthcoming Meeting Firstenergy Nuclear Operating Company (FENOC) ML12138A3312012-05-17017 May 2012 05/31/2012, Notice of Significant Licensee Meeting (non-public) Regarding Operator Licensing Workshop and Meeting ML12200A2492011-12-22022 December 2011 Presentation Slides on Shield Building /Containment Delamination ML1116400632011-06-15015 June 2011 EOC NRC Slides for Public Meeting ML1110806902011-04-20020 April 2011 Notice of Meeting with First Energy Nuclear Operating Company (FENOC) to Discuss a Proposed LAR to Delete Technical Specification 5.5.8g, Steam Generator (SG) Program Auxiliary Feedwater Header Inspections ML1028702612010-10-22022 October 2010 11/04/10 Notice of Meeting to Discuss the License Renewal Process and Environmental Scoping for Davis-Besse Nuclear Power Station License Renewal Application Review L-02-002, G20100238/EDATS: OEDO-2010-0305 - Ltr. Tom Gurdziel, 2.206 - Firstenergy - Davis-Besse2010-04-15015 April 2010 G20100238/EDATS: OEDO-2010-0305 - Ltr. Tom Gurdziel, 2.206 - Firstenergy - Davis-Besse ML1009102662010-03-31031 March 2010 Slides FENOC and NRC Senior Management Briefing, 3-31-10 ML0806705292008-03-0606 March 2008 Draft Scheduling Notes for Briefing on Reactor Materials Issues on 04/28/2008 ML0723302222007-08-28028 August 2007 09/12/2007 Notice of Meeting with Firstenergy to Discuss the August 3, 2007 License Amendment Request for Conversion to Improved Technical Specifications for Davis-Besse, Unit 1 ML0722201892007-08-0808 August 2007 NRC EOC Public Meeting Slides ML0717103462007-06-21021 June 2007 Revised Notice of Meeting with Firstenergy to Discuss Response to Nrc'S 05/14/2007, Demand for Information Regarding Fenoc'S Re-analysis of the Timeline and Root Causes for the 2002 Davis-Besse Reactor Pressure Vessel Head Degradation Event ML0716202122007-06-13013 June 2007 Notice of Meeting with Firstenergy Regarding May 14, 2007 Demand for Information Davis-Besse ML0715203432007-06-0707 June 2007 Notice of Meeting with Union of Concerned Scientists Re Davis-Besse Nuclear Power Station 10 CFR 2.206 Petition Concerning Protection Against Control Rod Drive Mechanism (CRDM) Nozzle Leakage Fast Corrosion Scenario ML0700900122007-01-11011 January 2007 Notice of Forthcoming Pre-Submittal Meeting with Firstenergy Nuclear Operating Co. (FENOC) to Discuss Proposed Davis-Besse Measurement Uncertainty Recapture (Mur) Power Update License Amendment Request ML0631104002006-11-0909 November 2006 Notice of Closed Meeting Between Fenco Security and NSIR to Discuss Fenco Fleet Security Matters ML0427401242004-09-30030 September 2004 Notice of Meeting with Firstenergy Nuclear Operating Company to Discuss the Davis-Besse License Amendment Request Dated May 5, 2004, Regarding the Safety Features Actuation System Instrumentation Setpoints ML0427400632004-09-28028 September 2004 Presentation from Firstenergy Nuclear Operating Company Meeting Davis-Besse Nuclear Power Station ML0414802832004-02-25025 February 2004 Panel Meeting, February 25, 2004 ML0414802672004-02-24024 February 2004 Panel Meeting, February 24, 2004 ML0414803762004-02-23023 February 2004 Panel Meeting, February 23, 2004 ML0414803392004-02-20020 February 2004 Panel Meeting, February 20, 2004 ML0414801932004-02-13013 February 2004 Panel Meeting, February 13, 2004 ML0333502562003-12-0101 December 2003 7 Pm Agenda for the Public Meeting of the NRC Davis-Besse Oversight Panel ML0333502232003-11-12012 November 2003 7 Pm Agenda for the Public Meeting of the NRC Davis-Besse Oversight Panel ML0327602062003-10-0303 October 2003 Notice of Meeting with Firstenergy Nuclear Operating Company to Discuss the Davis-Besse High Pressure Injection Pumps ML0326010332003-09-17017 September 2003 Notice of Public Meeting Between NRC and Firstenergy Nuclear Operating Company Discuss the Licensee'S Long-Term Plans to Address Safety Conscious Work Environment and Organizational Effectiveness at the Davis-Besse Nuclear Power Station ML0325305502003-09-11011 September 2003 Notice of Meeting with Greenpeace, Nuclear Information & Resource Service (Nirs), Union of Concerned Scientists (Ucs) & First Energy Nuclear Operating Company (FENOC) 10 CFR 2.206 Petition on Davis-Besse ML0324812782003-09-10010 September 2003 Agenda and Handout for Public Meeting Between NRC and Firstenergy Nuclear Operating Company Davis-Besse Nuclear Power Station ML0323201842003-08-12012 August 2003 Agenda for Meeting to Inform Public of Nrc'S Oversight Panel Activities for Davis-Besse Nuclear Power Station ML0323201772003-08-12012 August 2003 Agenda and Handout for Public Meeting Between NRC and Firstenergy Nuclear Operating Company Davis-Besse Nuclear Power Station ML0318903282003-06-0303 June 2003 Agenda and Handout for Public Meetings Between NRC and Firstenergy Nuclear Operating Company Davis-Besse Nuclear Power Station ML0314303902003-05-23023 May 2003 Meeting with Industry Representatives for Discussions of Actions to Address Davis-Besse Lessons Learned Task Force Recommendations ML0312604252003-04-15015 April 2003 2 Pm Agenda and Handout for Public Meeting Between NRC Oversight Panel and Firstenergy Nuclear Operating Co ML0312604422003-04-15015 April 2003 7 Pm Agenda for Public Meeting of the NRC Oversight Panel for Davis-Besse Nuclear Power Station 2021-10-27
[Table view] Category:Meeting Briefing Package/Handouts
MONTHYEARML22222A1102022-07-21021 July 2022 KM Session Final ML22178A1952022-06-27027 June 2022 2021 Davis Besse Nuclear Power Station End-of-Cycle Meeting Presentation ML22028A3922022-02-0101 February 2022 Licensee Regulatory Conference Presentation ML22028A3972022-02-0101 February 2022 NRC Regulatory Conference Presentation ML21176A1992021-06-25025 June 2021 Slideshow Presentation for 2020 End -of-Cycle Public Meeting for Davis-Besse and Perry ML20210M0712020-07-27027 July 2020 Combined End-of-Cycle 2019 Public Meeting Slide Presentation ML19249D0212019-09-0606 September 2019 End-of-Cycle Summary Handout (2018) ML18310A3802018-11-0808 November 2018 Pre-Submittal Meeting Davis-Besse Nuclear Power Station (DB) Post-Shutdown Emergency Plan (PSEP) License Amendment Request ML18180A1962018-06-29029 June 2018 Slides for Davis Besse 2017 EOC Open House ML17229B3382017-08-17017 August 2017 Presentation for 2016 Davis-Besse EOC Open House ML16174A3152016-06-21021 June 2016 Annual Assessment Meeting Open House June 21, 2016 ML15156A6962015-06-11011 June 2015 Annual Assessment Meeting Open House Handout ML14224A1112014-08-25025 August 2014 Safety Culture Presentation for Brazil, U.S. Workshop on Safety and Security Culture - August 25, 2014 ML14218A0542014-08-0707 August 2014 Handout Davis-Besse EOC Mtg ML14050A4002014-02-20020 February 2014 NRC Presentation for Davis-Besse Steam Generator Replacement Webinar ML13322B3112013-11-13013 November 2013 NFPA 805 Transition - Meeting Slides, 11/13/2013 ML13294A5972013-10-21021 October 2013 FENOC Presentation Slides for Public Meeting September 24, 2013 ML13157A0642013-06-0606 June 2013 June 11, 2013 NRC Presentation ML13159A0092013-06-0404 June 2013 Notable Failures in Nondustructive Testing - June 4, 2013 Public Meeting ML12269A0612012-09-26026 September 2012 FENOC Presentation for 2012-09-26 Public Meeting ML12227A4172012-08-15015 August 2012 NRC End-Of-Cycle Assessment 2011 Meeting Presentation ML12221A2642012-08-0909 August 2012 NRC Public Meeting NRC Presentation 8/9/12 ML12221A2682012-08-0909 August 2012 FENOC Shield Building Cracking Davis-Besse Public Meeting 8/9/12 ML12132A3442012-05-11011 May 2012 NRC-AERB Bilateral Meeting Slide Presentation (Nro/De), Aerb, India - May 16-17, 2012 ML1206901712012-02-29029 February 2012 Slides and View Graphs - Boric Acid Corrosion Testing Program: Industry Perspective ML12200A2402012-02-23023 February 2012 Presentation Slides on Davis-Besse Shield Building Crack ML1204402842012-02-16016 February 2012 Public Meeting Construction Experiences - Evaluate Impact of Concrete Degradation ML12004A0102012-01-0404 January 2012 Public Meeting NRC Slides ML12200A2492011-12-22022 December 2011 Presentation Slides on Shield Building /Containment Delamination ML11220A2542011-08-0101 August 2011 DBNPS-Info Meeting Slides ML1116400632011-06-15015 June 2011 EOC NRC Slides for Public Meeting ML1117209902011-06-15015 June 2011 Meeting Presentation NRC Annual Assessment Meeting: Davis-Besse Nuclear Power Station. ML1021501182010-07-29029 July 2010 Licensee Slides for Davis-Besse Annual Assessment Meeting ML1021501112010-07-29029 July 2010 NRC Slides for Davis-Besse; July 29, 2010; Annual Assessment Meeting L-02-002, G20100238/EDATS: OEDO-2010-0305 - Ltr. Tom Gurdziel, 2.206 - Firstenergy - Davis-Besse2010-04-15015 April 2010 G20100238/EDATS: OEDO-2010-0305 - Ltr. Tom Gurdziel, 2.206 - Firstenergy - Davis-Besse ML0920202972009-07-15015 July 2009 NRC Slides from EOC Meeting ML0920202872009-07-15015 July 2009 Meeting Slides, NRC Annual Assessment Meeting Davis-Besse Nuclear Power Station ML0725600562007-09-12012 September 2007 9/12/2007 Meeting to Discuss Davis-Besse License Amendment Request for Conversion to Improved Technical Specifications (ITS) 9/12/2007 NRC Meeting Slides ML0725600462007-09-11011 September 2007 9/11/2007-Meeting to Discuss Davis-Besse License Amendment Request for Conversion to Improved Technical Specifications (ITS) - 9/11/2007 NRC Meeting Slides ML0722201892007-08-0808 August 2007 NRC EOC Public Meeting Slides ML0717905962007-06-27027 June 2007 Slides from Public Meeting Between NRC and FENOC Regarding Response to May 14, 2007, Demand for Information ML0702603952007-01-31031 January 2007 Summary of Conference Telephone Call Regarding the Spring 2006 Steam Generator Inspections - Handouts ML0706502022007-01-23023 January 2007 Slides to Summary of Pre-Application Meeting with FENOC Proposed License Amendment Request for Measurement Uncertainty Recapture Power Uprate ML0632003672006-12-11011 December 2006 Slides, Improved Technical Specification Conversion from Category 1 Pre-submittal Meeting with Fenco to Discuss Davis-Besse's' Proposed Conversion to Improved Technical Specifications ML0612404142006-05-0202 May 2006 NRC Annual Assessment Meeting ML0601801602006-01-18018 January 2006 Industry Safety Culture Presentation for January 18, 2006 Public Meeting ML0603002272006-01-10010 January 2006 Multi-Regional NRC Public Meeting Licensee (FENOC) Slide Presentation ML0802205572005-09-12012 September 2005 NRC Commissioners Briefing by Firstenergy Nuclear Operating Co ML0525604472005-08-17017 August 2005 B&W Owners Group Reactor Vessel Working Group Summary of the Plans of the B&Wog Reactor Vessel Integrity Program ML0526600162005-08-16016 August 2005 Mantg Conference, 8/16/05 - Plenary - Keynote Speech by Samuel J. Collins, Regional Administrator, Region I, the Changing Roles of the Operators and Trainers 2022-07-21
[Table view] |
Text
PUBLIC MEETING U.S. NUCLEAR REGULATORY COMMISSION OAK HARBOR, OHIO October 16, 2002, 9:00 am EDT Purpose of Meeting Discuss preliminary findings and observations from the two NRC special inspections conducted to review the public and occupational exposure consequences of steam generator nozzle dam installations at Davis-Besse
AGENDA I. Introduction and Opening Remarks II. Summary Of Planning For And Conduct Of Steam Generator Nozzle Dam Installation III. Summary Of Release Of Contaminated Workers To The Public Domain And Consequences IV. Summary Of Dose To Workers From Internal Contamination During Work V. Summary Of Findings VI. Comments/Questions From Local Members Of The Public VII. Comments/Questions From All Members Of The Public VIII. Adjourn Meeting
U.S. NUCLEAR REGULATORY COMMISSION PUBLIC AND OCCUPATIONAL RADIATION SAFETY SPECIAL INSPECTION TEAMS (SITs) EXIT MEETING OPENING REMARKS/INTRODUCTIONS USNRC REPRESENTATIVES TOM KOZAK - TEAM LEADER, OCCUPATIONAL SIT JOHN HOUSE - TEAM LEADER, PUBLIC SIT JACK GROBE - CHAIRMAN, MC 0350 PANEL BILL DEAN - VICE CHAIRMAN, MC 0350 PANEL TONY MENDIOLA - SECTION CHIEF PDIII-2, NRR CHRISTINE LIPA - BRANCH CHIEF, RPB 4, DRP, RIII SCOTT THOMAS - SENIOR RESIDENT INSPECTOR, DB JAY COLLINS - GENERAL ENGINEER
OPENING REMARKS/INTRODUCTIONS (cont.)
- SIT DISPATCHED ON APRIL 17, 2002 TO REVIEW CONTAMINATED WORKERS IN PUBLIC DOMAIN
- 2ND SIT DISPATCHED ON SEPTEMBER 30 TO REVIEW POTENTIAL OVEREXPOSURE TO WORKERS DURING SG NOZZLE DAM INSTALLATIONS
- RESULTS WILL BE DOCUMENTED IN INSPECTION REPORT NOS. 02-06 AND 02-16 UNDER ONE COVER LETTER
- RESULTS ARE CONSIDERED AS UNRESOLVED ITEMS AND RISK ASSESSMENT AS TO BE DETERMINED UNTIL RISK ASSESSMENT IS COMPLETED
SUMMARY
OF PLANNING FOR AND CONDUCT OF STEAM GENERATOR NOZZLE DAM INSTALLATIONS
- EVALUATION OF POTENTIAL RADIOLOGICAL HAZARDS NOT ADEQUATE TO IDENTITY AND PROTECT AGAINST ALPHA EMITTING RADIATION
- MISSED OPPORTUNITIES TO IDENTIFY POTENTIAL HAZARD INCREASING ALPHA EMITTER TREND HIGHER THAN PREVIOUS IODINE LEVEL IN RCS CRUD BURST JUST PRIOR TO SG BOWL ENTRY VERY HIGH CONTAMINATION LEVEL IDENTIFIED ON SG DIAPHRAGM ALPHA PARTICLES IDENTIFIED IN SG PLATFORM AIR SAMPLE
SUMMARY
OF RELEASE OF EXTERNALLY CONTAMINATED WORKERS TO THE PUBLIC DOMAIN
- SIX WORKERS INTERNALLY AND EXTERNALLY CONTAMINATED DURING SG NOZZLE DAM INSTALLATIONS
- SEVERAL ATTEMPTS MADE TO DECONTAMINATE THE WORKERS
- CONTAMINATION SURVEYS CONDUCTED AT RRA EXIT WERE INADEQUATE DID NOT IDENTIFY ALL EXTERNAL CONTAMINATION SOME PERSONAL CLOTHING NOT SURVEYED
- FOUR WORKERS FOUND CONTAMINATED AT OTHER SITES
- 16 DRPs FOUND IN PUBLIC DOMAIN
- DOSE CALCULATIONS - NO ADVERSE HEALTH EFFECTS TO WORKERS OR PUBLIC FROM DRPs
SUMMARY
OF DOSE TO WORKERS FROM INTERNAL CONTAMINATION DURING WORK
- TWO WORKERS RECEIVED RELATIVELY LARGE INTERNAL CONTAMINATIONS
- INITIAL ASSESSMENT CONDUCTED WITH WBC WHICH IS NOT SUITABLE TO MEASURE ALPHAS
- CONCENTRATIONS OF RADIOACTIVE MATERIAL IN AIR IN WORK AREAS NOT MEASURED
- DOSE ASSIGNED PRIMARILY BASED ON GAMMA EMITTING RADIATION
- CONTAMINATION IDENTIFIED TO CONTAIN HIGH ALPHA EMITTER CONCENTRATIONS IN AUGUST
- DOSE RECALCULATED USING SCALING FACTORS, RESULTS UNCERTAIN
- MULTIPLE BIOASSAY SAMPLES OBTAINED FROM WORKERS
- SAMPLES WERE NOT TIMELY - AWAITING RESULTS
SUMMARY
OF PRELIMINARY FINDINGS
- FAILURE TO CONDUCT TIMELY AND SUITABLE MEASUREMENTS OF CONCENTRATIONS OF RADIOACTIVE MATERIAL IN AIR IN WORK AREAS OR OF CONCENTRATIONS OF RADIONUCLIDES EXCRETED FROM THE BODY - COMPROMISED THE ABILITY TO ASSESS DOSE
- FAILURE TO ADEQUATELY SURVEY WORKERS PRIOR TO RELEASE FROM SITE - RESULTED IN THE RELEASE OF RADIOACTIVE MATERIAL OUTSIDE CONTROLLED AREA INTO THE PUBLIC DOMAIN
- THE FINDINGS ARE UNRESOLVED ITEMS WHOSE SIGNIFICANCE IS TO BE DETERMINED - EACH FINDING MAY INVOLVE VIOLATIONS OF NRC REQUIREMENTS