September 2002 Monthly Operating Report for Indian Point 3
ML022910041
Person / Time
Site: Indian Point Entergy icon.png
Issue date: 10/11/2002
From: Barrett R
Entergy Nuclear Northeast, Entergy Nuclear Operations
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
IPN-02-084
Download: ML022910041 (6)


Text

S-Entergy Entergy Nuclear Northeast Entergy Nuclear Operations, Inc Indian Point Energy Center RO Box 308 Buchanan, NY 10511 Tel 914 736 8001 Fax 914 736 8012 Robert J. Barrett Vioe President, Operations Indian Point 3 October 11, 2002 IPN-02-084 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Mail Stop O-P1-17 Washington, D.C. 20555-0001

Subject:

Indian Point 3 Nuclear Power Plant Docket No. 50-286 License No. DPR-64 Monthly Operating Report for September 2002

Dear Sir:

The attached monthly operating report, for the month of September 2002, is hereby submitted in accordance with Indian Point 3 Nuclear Power Plant Technical Specification 5.6.4.

Indian Point 3 is making no commitments in this letter.

Vice-President, Operations Indian Point 3 Nuclear Power Plant cc: See next page C

Docket No. 50-286 IPN-02-084 Page 2 of 2 Attachment cc:

Mr. Hubert J. Miller Regional Administrator Region I U.S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, Pennsylvania 19406-1415 Resident Inspector's Office U.S. Nuclear Regulatory Commission Indian Point 3 Nuclear Power Plant P.O. Box 337 Buchanan, NY 10511-0337 U.S. Nuclear Regulatory Commission ATTN: Director, Office of Information Resource Management Washington, D.C. 20555 INPO Records Center 700 Galleria Parkway Atlanta, Georgia 30339-5957

DOCKET NO.

UNIT:

DATE:

COMPLETED BY:

TELEPHONE NO:

LETTER NO:

50-286 Indian Point 31 10-08-02 T. Orlando (914) 736-8340 IPN-02-084 ATTACHMENT PAGE 1 of 4 OPERATING DATA REPORT OPERATING STATUS Unit Name:

Indian Point No. 3 Nuclear Power Plant Reporting Period:

September 2002 Licensed Thermal Power (MWt):

3025 Nameplate Rating (Gross MWe):

1013 Design Electrical Rating (Net MWe):

965 Maximum Dependable Capacity (Gross MWe):

1000 Maximum Dependable Capacity (Net MWe):

965 If Changes Occur in Capacity Ratings (Items Number 3 through 7) Since Last Report Give Reasons:

9.

Power Level to Which Restricted, If Any (Net MWe):

10.

Reasons for Restrictions, If Any:

11.

Hours In Reporting Period

12.

Number Of Hours Reactor Was Critical

13.

Reactor Reserve Shutdown Hours

14.

Hours Generator On-Line

15.

Unit Reserve Shutdown Hours

16.

Gross Thermal Energy Generated (MWH)

17.

Gross Electrical Energy Generated (MWH)

18.

Net Electrical Energy Generated (MWH)

19.

Unit Service Factor

20.

Unit Availability Factor

21.

Unit Capacity factor (Using MDC Net)

22.

Unit Capacity Factor (Using DER Net)

23.

Unit Forced Outage Rate This Month 720 720 0

720 0

2,176,339 730,678 705,178 100 100 101.5 101.5 0

Yr-to-Date 6,651 6,651 0

6,651 0

19,785,384 6,656,493 6,439,971 100 100 101.9 101.9 0

Cumulative 229,072 144,158.73 0

141,348 0

406,616,324 130,539,956 126,044,196 61.7 61.7 57.8*

57.0 23.2

24.

Shutdowns Scheduled Over Next 6 Months (Type, Date and Duration of Each):

25.

If Shut Down At End Of Report Period. Estimated Date of Startup:

26.

Units In Test Status (Prior to Commercial Operation):

INITIAL CRITICALITY INITIAL ELECTRICITY COMMERCIAL OPERATION Weighted Average

1.
2.
3.
4.
5.
6.
7.

8.

Forecast Achieved

DOCKET NO.

UNIT:

DATE:

COMPLETED BY:

TELEPHONE NO:

LETTER NO:

50-286 Indian Point 3 10-08-02 T. Orlando (914) 736-8340 IPN-02-084 ATTACHMENT PAGE 2 of 4 AVERAGE DAILY UNIT POWER LEVEL MONTH September 2001 AVERAGE DAILY POWER 973 978 979 979 980 981 980 980 978 979 978 980 980 980 980 980 DAY 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 AVERAGE DAILY POWER LEVEL (MWe-Net) 979 980 980 978 979 978 980 980 979 980 980 979 982 983 INSTRUCTIONS:

On this format, list the average daily unit power level in MWe-Net for each day in the reporting month. Compute to the nearest whole megawatt.

DAY 1

2 3

4 5

6 7

8 9

10 11 12 13 14 15 16

DOCKET NO.

UNIT:

DATE:

COMPLETED BY:

TELEPHONE NO.

LETTER NO:

50-286 Indian Point 3 10-08-02 T. Orlando (914) 736-8340 IPN-02-084 ATTACHMENT PAGE 3 of 4 UNIT SHUTDOWNS AND POWER REDUCTIONS REPORT MONTH September 2002 METHOD OF NO.

DATE TYPE DURATION REASON SHUTTING LICENSEE SYSTEM COMPONENT CAUSE & CORRECTIVE ACTION TO 1

(HOURS) 2 DOWN EVENT CODE CODE PREVENT RECURRENCE REACTOR 3 REPORT#

4 5

NONE 1

F: Forced S: Scheduled 2

3 Reason:

Method:

A-Equipment 1-Manual B-Maintenance or Test 2-Manual Scram C-Refueling 3-Automatic Scram D-Regulatory Restriction 4-Other (Explain)

E-Operator Training & Licensee Examination F-Administrative G-Operational Error H-Other (Explain) 4 5

Exhibit G - Instructions Exhibit 1 for Preparation of Data Same Source Entry Sheets for Licensee Event Report (LER) File (NUREG - 0161)

DOCKET NO.

UNIT:

DATE:

COMPLETED BY:

TELEPHONE NO.:

LETTER NO.

50-286 Indian Point 3 10-08-02 T. Orlando (914) 736-8340 IPN-02-084 ATTACHMENT PAGE 4 of 4

SUMMARY

OF OPERATING EXPERIENCE September 2002 The Indian Point Unit No. 3 Nuclear Power Plant was synchronized to the bus for a total of 720 hours0.00833 days <br />0.2 hours <br />0.00119 weeks <br />2.7396e-4 months <br />, producing a gross electrical energy generation of 730,678 MWH.