September 2002 Monthly Operating Report for Turkey Point, Units 3 and 4
ML022900271
Person / Time
Site: Turkey Point  
(DPR-031, DPR-041)
Issue date: 10/08/2002
From: Mcelwain J
Florida Power & Light Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
GL-97-002, L-2002-203
Download: ML022900271 (3)


Text

FPL U. S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, D. C. 20555 Re:

Turkey Point Units 3 and 4 Docket Nos. 50-250 and 50-251 Monthly Operating Report - September 2002 In accordance with the requirements of Turkey Point Units 3 and 4 Technical Specification 6.9.1.5, and the guidance of Generic Letter 97-02, attached are the September 2002 Operating Data Reports and Summaries of Operating Experience for Turkey Point Units 3 and 4.

Very truly yours,

(-oh P Mwlain Vice President Turkey Point Plant OIH Attachments NRC Regulatory Issue Summary 2001-05 waived the requirements that multiple copies of documents be submitted to the NRC.

an FPL Group company OCT 0 8 2002 L-2002-203 10 CFR 50.36

DOCKET NO.:

UNIT:

DATE:

COMPLETED BY:

TELEPHONE:

50-250 Turkey Point Unit 3 10/2/2002 Olga Hanek (305) 246-6607 Reporting Period September. 2002 OPERATING DATA REPORT Design Electrical Rating (MWe-Net) 720 Maximum Dependable Capacity (MWe-Net) 693

___ ÷.....

Month Year-to-date Cumulative No. of hours reactor was critical 720 6551 192330.8 No. of hours generator was on line (service hours) 720 6551 189999.5 Unit reserve shutdown hours 0

0 121.8 Net Electrical Energy (MWH) 507214 4634265 123777912 UNIT SHUTDOWNS (1) Reason (2) Method A - Equipment Failure (Explain)

B - Maintenance or Test C - Refueling D - Regulatory Restriction E - Operator Training/License Examination F - Administrative G - Operational Error (Explain)

H - Other 1 - Manual 2 - Manual Trip/Scram 3 -Automatic Trip/Scram 4 - Continuation 5 - Other (Explain)

Summary Of Monthly Operating Experience Unit 3 operated at essentially 100% for the month of September 2002.

DOCKET NO.:

UNIT:

DATE:

COMPLETED BY:

TELEPHONE:

50-251 Turkey Point Unit 4 10/2/2002 Olga Hanek (305) 246-6607 Reporting Period September. 2002 UNIT SHUTDOWNS (1) Reason (2) Method A - Equipment Failure (Explain)

B - Maintenance or Test C - Refueling D - Regulatory Restriction E - Operator Training/License Examination F - Administrative G - Operational Error (Explain)

H - Other 1 - Manual 2 - Manual Trip/Scram 3 - Automatic Trip/Scram 4 - Continuation 5 - Other (Explain)

Summary Of Monthly Operating Experience Unit 4 operated at essentially 100% until 9/13/02, when power was reduced to 20% to perform turbine valve testing and containment entry. Power was returned to 100% on 9/15/02 and remained at essentially 100% for the rest of the month.

Design Electrical Rating (MWe-Net) 720 Maximum Dependable Capacity (MWe-Net) 693

__÷______

Month Year-to-date Cumulative No. of hours reactor was critical 720 6184.2 189153.7 No. of hours generator was on line (service hours) 720 6175.5 184750.6 Unit reserve shutdown hours 0

0 577.2 Net Electrical Energy (MWH) 488621 4293301 121398312