Revision to Schedule for Conduct of Review of St. Lucie, Units 1 & 2, License Renewal Application
ML022900065
Person / Time
Site: Saint Lucie  
Issue date: 10/10/2002
From: Dudley N
NRC/NRR/DRIP/RLEP
To: Stall J
Florida Power & Light Co
Dudley N, NRR/DRIP/RLEP, 415-1154
References
Download: ML022900065 (6)


Text

October 10, 2002 Mr. J. A. Stall Senior Vice President, Nuclear and Chief Nuclear Officer Florida Power and Light Company P.O. Box 14000 Juno Beach, FL 33408-0420

SUBJECT:

REVISION TO SCHEDULE FOR THE CONDUCT OF REVIEW OF THE ST. LUCIE, UNITS 1 AND 2, LICENSE RENEWAL APPLICATION

Dear Mr. Stall:

Enclosed is the revised schedule for the staffs review of the St. Lucie, Units 1 and 2, license renewal application. This schedule has been revised to reflect a 22 month review with approval by the Director, Office of Nuclear Reactor Regulation. The staff also revised the dates for completion of environmental review activities and safety review inspections. If you have any questions regarding this matter, please contact me at 301-415-1154.

Sincerely,

/RA/

Noel F. Dudley, Project Manager License Renewal Section License Renewal and Environmental Impacts Program Division of Regulatory Improvement Programs Office of Nuclear Reactor Regulation Docket Nos. 50-335 and 50-389

Enclosure:

As stated cc w/enclosure: See next page

Mr. J. A. Stall Senior Vice President, Nuclear and Chief Nuclear Officer Florida Power and Light Company P.O. Box 14000 Juno Beach, FL 33408-0420

SUBJECT:

REVISION TO SCHEDULE FOR THE CONDUCT OF REVIEW OF THE ST. LUCIE, UNITS 1 AND 2, LICENSE RENEWAL APPLICATION

Dear Mr. Stall:

Enclosed is the revised schedule for the staffs review of the St. Lucie, Units 1 and 2, license renewal application. This schedule has been revised to reflect a 22 month review with approval by the Director, Office of Nuclear Reactor Regulation. The staff also revised the dates for completion of environmental review activities and safety review inspections. If you have any questions regarding this matter, please contact me at 301-415-1154.

Sincerely,

/RA/

Noel F. Dudley, Project Manager License Renewal Section License Renewal and Environmental Impacts Program Division of Regulatory Improvement Programs Office of Nuclear Reactor Regulation Docket Nos. 50-335 and 50-389

Enclosure:

As stated cc w/enclosure: See next page DISTRIBUTION:

See next page

  • See attached sheets for original concurrence pages C:\\MYFILES\\Copies\\revised schedule 2.wpd.

OFFICE PM:RLEP:DRIP*

LA:RLEP:DRIP*

SC:RLEP:DRIP*

NAME NDudley HBerilla SLee DATE 10/9/02 10/9/02 10/10/02 OFFICIAL RECORD COPY

DISTRIBUTION: Letter to Mr. J. A. Stall, dated: October 10, 2002, ML022900065 HARD COPY RLEP RF N. Dudley E-MAIL:

PUBLIC J. Johnson W. Borchardt D. Matthews F. Gillespie RidsNrrDe R. Barrett E. Imbro G. Bagchi K. Manoly W. Bateman J. Calvo C. Holden P. Shemanski H. Nieh G. Holahan H. Walker S. Black B. Boger D. Thatcher G. Galletti C. Li J. Moore R. Weisman M. Mayfield A. Murphy W. McDowell S. Smith (srs3)

T. Kobetz C. Munson RLEP Staff R. McIntyre B. Moroney T. Ross (RII)

C. Julian (RII)

K. Rico

Mr. J. A. Stall ST. LUCIE PLANT Florida Power and Light Company cc:

Senior Resident Inspector St. Lucie Plant U.S. Nuclear Regulatory Commission P.O. Box 6090 Jensen Beach, Florida 34957 Craig Fugate, Director Division of Emergency Preparedness Department of Community Affairs 2740 Centerview Drive Tallahassee, Florida 32399-2100 M. S. Ross, Attorney Florida Power & Light Company P.O. Box 14000 Juno Beach, FL 33408-0420 Mr. Douglas Anderson County Administrator St. Lucie County 2300 Virginia Avenue Fort Pierce, Florida 34982 Mr. William A. Passetti, Chief Department of Health Bureau of Radiation Control 2020 Capital Circle, SE, Bin #C21 Tallahassee, Florida 32399-1741 Mr. Donald E. Jernigan, Site Vice President St. Lucie Nuclear Plant 6501 South Ocean Drive Jensen Beach, Florida 34957 Mr. R. E. Rose Plant General Manager St. Lucie Nuclear Plant 6501 South Ocean Drive Jensen Beach, Florida 34957 Mr. J. T. Voorhees Acting Licensing Manager St. Lucie Nuclear Plant 6501 South Ocean Drive Jensen Beach, Florida 34957 Mr. Don Mothena Manager, Nuclear Plant Support Services Florida Power & Light Company P.O. Box 14000 Juno Beach, FL 33408-0420 Mr. Rajiv S. Kundalkar Vice President - Nuclear Engineering Florida Power & Light Company P.O. Box 14000 Juno Beach, FL 33408-0420 Mr. J. Kammel Radiological Emergency Planning Administrator Department of Public Safety 6000 SE. Tower Drive Stuart, Florida 34997 Attorney General Department of Legal Affairs The Capitol Tallahassee, Florida 32304 Mr. Steve Hale St. Lucie Nuclear Plant Florida Power and Light Company 6351 South Ocean Drive Jensen Beach, Florida 34957-2000 Mr. Alan P. Nelson Nuclear Energy Institute 1776 I Street, N.W., Suite 400 Washington, DC 20006-3708 APN@NEI.ORG David Lewis Shaw Pittman, LLP 2300 N Street, N.W.

Washington, D.C. 20037

Division of Regulatory Improvement Programs COVER PAGE DATE:

October 10, 2002

SUBJECT:

REVISION TO SCHEDULE FOR THE CONDUCT OF REVIEW OF THE ST. LUCIE, UNITS 1 AND 2, LICENSE RENEWAL APPLICATION ORIGINATOR:

N. Dudley SECRETARY:

S. Chey

!!!DRIP ROUTING LIST!!!

NAME DATE 1.

N. Dudley 10/9/02 2.

H. Berilla 10/9/02 4.

S. Lee 10/10/02 DOCUMENT NAME:

C:\\MYFILES\\Copies\\revised schedule 2.wpd ADAMS ACCESSION NUMBER:

DATE ENTERED: 10/ /02 FORM 665 ATTACHED and filled out:

YES NO COMMITMENT FORM ATTACHED:

YES NO

St. Lucie, Units 1 & 2 License Renewal Application Review Schedule Revision 2 SCHEDULE ACTUAL MILESTONE DATE DATE Receive license renewal application 11/30/01 1/30/01 Fed. Register Notice (FRN) published for receipt & acceptability 12/28/01 12/27/01 FRN published for acceptance/rejection/opportunity hearing 1/29/02 1/29/02 Deadline for filing hearing requests and petitions for intervention 2/28/02 2/28/02 FRN published for intent/environmental scoping meeting 3/1/02 2/28/02 Environmental scoping meeting 4/3/02 4/3/02 Environmental scoping period ends 5/6/02 5/6/02 Environmental requests for additional information (RAIs) issued 5/20/02 5/7/02 Scoping and screening methodology audit complete 6/4/02 4/18/02 Environmental RAIs responses received 7/19/02 6/25/02 Safety RAIs issued 7/29/02 7/29/02 Safety RAIs received 10/11/02 10/11/02

 Scoping inspection complete 10/25/02

 Draft supplemental environmental impact statement (SEIS) issued 11/1/02

 Public meeting to discuss draft SEIS 12/3/02 End of draft SEIS comment period 1/15/03

 Aging management review inspection complete 2/7/03 Safety evaluation report (SER) with open items issued 2/7/03 ACRS Subcommittee meeting SER with open items 3/03 ACRS Full Committee meeting on SER with open item 4/03 SER open item responses received 4/24/03 Optional final inspection complete 6/2/03 Final SEIS issued 6/30/03 SER issued 7/8/03 Regional Administrator's letter issued 7/21/03 ACRS Subcommittee meeting on SER 8/03 ACRS Full Committee meeting on SER 9/03 SER issued as NUREG 8/22/03 ACRS letter issued 9/03

 Staff recommendation to Director, NRR 9/26/03

 Decision - Director, NRR (license issued, if approved) 10/3/03 Revised 10/15/02 Enclosure