ML022890165

From kanterella
Jump to navigation Jump to search
Comment (7) Submitted by Firstenergy, Perry Nuclear Power, Kristi Mcconnell on PR-Chapter 1 (Dfr) Regarding Electronic Maintenance & Submission of Information
ML022890165
Person / Time
Site: Perry  
(CPPR-0149, NPF-058)
Issue date: 10/14/2002
From: Mcconnell K
FirstEnergy Nuclear Operating Co
To:
NRC/SECY/RAS
Ngbea E S
References
+adjud/ruledam200505, 67FR57084 00007, 67FR57120, Chapter 1
Download: ML022890165 (1)


Text

DOCKET FirstEnergy, Perry Nuclear Power Plant comm

  • ops E-rule Currently, the Perry Plant does not submit our USAR and other licensing material via electronic means. Perry recognizes this to be an expense to the utilities in the industry, as well as a "step backward" for the electronic advancement of the industry.

However, at this time, this proposed rule would be a reduction of hard copy expenses for the Perry Plant as we are currently sending the 11 copies originally required. Perry, overall, finds the proposal acceptable, but recognizes that eventually, we would like to see all hard copy submittal requirements eliminated.

Plant

Contact:

Kristi McConnell, Procedures and Records Supervisor Perry Nuclear Power Plant, MZ R265 P.O. Box 97 Perry, Ohio 44081 440-280-5398 DOCKETED USNRC October 15,2002 (11:49AM)

OFFICE OF SECRETARY RULEMAKINGS AND ADJUDICATIONS STAFF 1rmeol=. -- $

00-L