ML022820233

From kanterella
Jump to navigation Jump to search
Emergency Response Activation Implementing Procedures
ML022820233
Person / Time
Site: Indian Point Entergy icon.png
Issue date: 09/23/2002
From:
Entergy Nuclear Northeast, Entergy Nuclear Operations
To:
Document Control Desk, Office of Nuclear Security and Incident Response
References
Download: ML022820233 (6)


Text

29-AUG-02 Page: 1 DISTRIBUTION CONTROL LIST S

Document Name: EMER PLAN CC-NAME NAME DEPT LOCATION 1 PLANT MANAGER'S OFFICE UNIT 3(UNIT 3/IPEC ONLY) 45-3-B 2 EP/TRAINING ADMINISTRATOR TRAINING (ALL EP'S) #48 3 RES DEPARTMENT MANAGER RES (UNIT 3/IPEC ONLY) 45-4-A 4 REFERENCE LIBRARY REC/TRN(UNT 3/IPEC ONLY) #48 9 JOINT NEWS CENTER EMER PLN (ALL EP'S) EOF 10 SHIFT MGR. (LUB-001-GEN) OPS (UNIT 3/IPEC ONLY) IP3 11 CONTROL ROOM & MASTER OPS (3PT-DO01/6 (U3/IPEC) IP3 (ONLY) 14 EOF E-PLAN (ALL EP'S) EOF 16 AEOF/A.GROSJEAN(ALL EP'S) E-PLAN (EOP'S ONLY) WPO-12D 19 NUC ENGINEERING LIBRARY DOC (UNIT 3/IPEC ONLY) WPO/7A 22 RESIDENT INSPECTOR US NRC(UNIT 3/IPEC ONLY) 45-2-B 23 MCNAMARA N NRC (ALL EP'S) OFFSITE 24 MCNAMARA N NRC (ALL EP'S) OFFSITE

. 31 BARANSKI J(VOLUME I ONLY) 32 MURPHY L -(VOLUME 33 I ONLY)

LONGO N (VOLUME I ONLY)

ST. EMERG. MGMT. OFFICE DISASTER & EMERGENCY EMERGENCY SERVICES OFFSITE WESTCHESTR ROCKLAND 34 GREENE D (VOLUME I ONLY) DISASTER & CIVIL DEFENSE ORANGE 35 RAMPOLLA M(VOLUME I ONLY) OFFICE OF EMERG MANAGE PUTNAM 41 SIMULATOR TRAIN(UNIT 3/IPEC ONLY) 48-2-A 107 QA MANAGER QA (UNIT 3/IPEC) TRL #2A 319 C.STELLATO(NRQ-OPS TRN) NRQ (UNIT 3/IPEC ONLY) #48 354 L.GRANT(LRQ-OPS/TRAIN) LRQ (UNIT 3/IPEC ONLY) #48 376 E-PLAN STAFF E-PLAN (ALL EP'S) EOF 424 J.CHIUSANO(OPS INSTR) (UNIT 3/IPEC ONLY) #48 510 L.GRANT (LRQ-OPS/TRAIN) LRQ (UNIT 3/IPEC ONLY) #48 511 L.GRANT(LRQ-OPS/TRAIN) LRQ (UNIT 3/IPEC ONLY) #48 512 C.STELLATO(NRQ-OPS TRN) NRQ (UNIT 3/IPEC ONLY) #48 513 C.STELLATO(NRQ-OPS TRN) NRQ (UNIT 3/IPEC ONLY) #48 517 PLANT MANAGER'S OFFICE ADMIN/(UNIT 2/IPEC ONLY) IP2 518 TSC UNIT 2(UNIT 2/IPEC ONLY) IP2 520 CONTROL ROOM (UNIT 2) OPS (UNIT 2 & IPEC ONLY) IP2 521 SIMULATOR TRAIN (UNIT 2/IPEC ONLY) IP2 522 NRC RESIDENT US NRC(UNIT 2/IPEC ONLY) IP2 523 ROBERT VOGLE (UNIT 2) TRAIN/LIB (ALL EP'S) OFFSITE 524 JOHN MCCANN (UNIT 2) NUC SAFETY/LIC(ALL EP'S) IP2 4rkckA5

Entergy Indian Point 3 CONTROLLED DOCUMENT TRANSMITTAL FORM TO: DISTRIBUTION DATE 9/25/2002 TRANSMITTAL NO: 27275 FROM:IP3 DOCUMENT CONTROL GROUP EXTENSION: 2038 The Document(s) identified below are forwarded for use. In accordance with AP-18.2, please review to verify receipt, incorporate the document(s) into your controlled document file, properly disposition superseded, void, or inactive document(s). Sign and return the receipt acknowledgement below within fifteen (15) working days.

AFFECTED DOCUMENT EMERGENCY PLAN PROCEDURES: UNIT 3 DOC # REV # TITLE INSTRUCTIONS

                    • FOLLOW ATTACHED INSTRUCTIONS********************
  • PLEASE NOTE EFFECTIVE DATES**

RECEIPT OF THE ABOVE LISTED DOCUMENT(S) IS HEREBY ACKNOWLEDGED. I CERTIFY THAT ALL SUPERSEDED, VOID, OR INACTIVE COPIES OF THE ABOVE LISTED DOCUMENT(S) IN MY POSSESSION HAVE BEEN REMOVED FROM USE AND ALL UPDATES HAVE BEEN PERFORMED IN ACCORDANCE WITH EFFECTIVE DATE(S) (IF APPLICABLE) AS SHOWN ON THE DOCUMENT(S).

NAME (PRINT) SIGNATURE DATE CC# .

Entergy Nuclear Northeast Entergy Nuclear Operations, Inc.

Indian Point 3 NPP SEntfrgy P0 Box 308 Buchanan, NY 10511 Tel 914 736 8000 767 NRC CONTROL COPY NO.:_

FROM: EMERGENCY PLANNING DATE: 09/23/02

SUBJECT:

Emergency Response Activation Implementing Procedures Please discard The enclosed revisions are for your controlled copy of the IP-3 Emergency Plan. to the IP-3 old sheets, insert new sheets, initial/date this transmittal and return it call Emergency DOCUMENTS DEPARTMENT. If you have any questions regarding these changes, Planning (x8318).

Thank you.

Volume II - Emergency Response Activation Implementing Procedures OLD NEW 06/02 Appendix C 09/02 Appendix C Table of Contents 09/02 Table of Contents 08/30/02 I acknowledge the receipt of these revisions to the IP-3 Emergency Plan.

(Signature) (Date)

VOLUME II APPENDIX 'C' 09/02 This page is being substituted for this Appendix in the NRC Volume II controlled copies due to the contents being personal and confidential, and not applicable for distribution to the public.

Appendix 'C" of the IP-3 Emergency Plan Volume II lists IP-3 emergency facility telephone numbers.

VOLUME II TABLE OF CONTENTS 09/02 ENTERGY NUCLEAR NORTHEAST INDIAN POINT NO. 3 NUCLEAR POWER PLANT EMERGENCY PLAN - VOLUME II EMERGENCY RESPONSE ACTIVATION TABLE OF CONTENTS REV. # / DATE IC/EAL'S INITIATING CONDITIONS AND EMERGENCY ACTION LEVELS 9 - 07/02 CONTROL ROOM IP-2000 Emergency Activation of the Control Room (CR) 4 - 09/98 IP-2001 Emergency Director (ED), Plant Operations Manager 16 - 08/02 (POM), Shift Manager (SM) Procedure IP-2002 CR Health Physics Technician 3 - 02/99 IP-2003 CR Watch Chemist 6 - 07/02 IP-2004 CR Clerk 3 - 09/00 IP-2005 CR Offsite Communicator 2 - 06/01 IP-2006 CR Direct-Line Communicator 4 - 10/99 TECHNICAL SUPPORT CENTER (TSC)

IP-2100 Emergency Activation of the Technical Support 4 - 11/00 Center (TSC)

IP-2101 Technical Support Center (TSC) Manager 9 - 02/01 IP-2102 TSC Communicator(s) 3 - 12/98 IP-2103 TSC SPDS Computer Operator 4 - 08/99 IP-2104 TSC Video Operator 2 - 06/01 IP-2105 TSC Accountability Officer VOID - N/A IP-2106 TSC Clerk 5 - 06/99 OPERATIONS SUPPORT CENTER (OSC)

IP-2200 Emergency Activation of the Operations 7 - 8/02 Support Center (OSC)

IP-2201 Operations Support Center (OSC) Manager 9 - 08/02 IP-2202 OSC Direct-Line Communicator 2 - 12/98 IP-2203 OSC Dispatcher 3 - 07/02 IP-2204 OSC Team Leaders 3 - 06/02 IP-2205 OSC H.P. Team Leader 8 - 10/99 IP-2206 OSC Accountability Officer VOID - N/A IP-2207 OSC Clerk 5 - 06/99 IP-2208 OSC Security Team Leader 4 - 03/02 IP-2209 OSC H.P. Technician 4 - 12/97 IP-2210 OSC Dosimetry Technician 3 - 06/98 IP-2211 OSC Chemistry Team Leader 2 - 03/00 I

I

VOLUME II TABLE OF CONTENTS 09/02 ENTERGY NUCLEAR NORTHEAST INDIAN POINT NO. 3 NUCLEAR POWER PLANT EMERGENCY PLAN - VOLUME II EMERGENCY RESPONSE ACTIVATION TABLE OF CONTENTS EMERGENCY OPERATIONS FACILITY (EOF) REV. # / DATE IP-2300 Emergency Activation of the Emergency 5 - 11/00 Operations Facility (EOF)

IP-2301 Emergency Director VOID - N/A Replaced by IP-EP-255 IP-2302 EOF Technical Advisor and Information Liaison 10 07/02 IP-2303 EOF Radiological Assessment Team Leader (RATL) 5 11/00 IP-2304 EOF Dose Assessment Health Physicist 5 07/02 IP-2305 EOF MIDAS Operator 4 03/00 IP-2306 EOF Security Officer 7 12 /98 IP-2307 EOF Clerk 5 10/99 IP-2308 EOF Direct-Line Communicator 4 03/00 IP-2309 EOF Offsite Communicator 4 09/00 IP-2310 EOF Onsite Radiological Communicator 4 08/02 IP-2311 EOF Offsite Radiological Communicator 4 06/99 IP-2312 EOF Public Relations Liaison VOID N/A IP-2313 EOF Public Relations Technical Advisor VOID N/A IP-2314 EOF Radiological Assessment Monitor VOID N/A ALTERNATE EMERGENCY OPERATIONS FACILITY (AEOF)

IP-2400 Emergency Activation of the Alternate Emergency VOID - N/A Operations Facility (AEOF)

Replaced by IP-EP-251 SECURITY ACTIVATION IP-2500 Security Emergency Activation Responsibilities 12 - 08/02 RECOVERY/TERMINATION IP-2600 Emergency Termination and Transition to Recovery VOID - N/A Replaced by IP-EP-610 IP-2601 Recovery Manager VOID - N/A Replaced by IP-EP-610 IP-2602 Development of a Recovery Action Plan VOID - N/A Replaced by IP-EP-610 IP-2603 Recovery Support Group Manager 1 - 07/02 EP-FORMS SECTION - Index 07/02 APPENDIX 'A' ROSTER I 07/02 ROSTER II 07/02 ROSTER III 06/02 APPENDIX 'B' - Emergency Offsite Telephone List 06/02 APPENDIX 'C' - Emergency Response Facility Telephone List 09/02