Schedule for Review of Measurement Uncertainty Recapture Power Uprate
ML022670572
Person / Time
Site: Point Beach  NextEra Energy icon.png
Issue date: 09/26/2002
From: Raghavan L
NRC/NRR/DLPM/LPD3
To: Cayia F
Nuclear Management Co
References
Download: ML022670572 (4)


Text

September 26, 2002 Mr. Fred J. Cayia Acting Site Vice President Point Beach Nuclear Plant Nuclear Management Company, LLC 6610 Nuclear Road Two Rivers, WI 54241

SUBJECT:

POINT BEACH NUCLEAR PLANT, UNITS 1 AND 2 - SCHEDULE FOR REVIEW OF MEASUREMENT UNCERTAINTY RECAPTURE POWER UPRATE APPLICATION

Dear Mr. Cayia:

By application dated April 30, 2002, you submitted an amendment request for a measurement uncertainty recapture power uprate for the Point Beach Nuclear Plant, Units 1 and 2. Our review of your application, which is in progress, was originally scheduled to be complete in October 2002.

On September 19, 2002, in a telephone conference, your staff indicated that you have pursued other changes which would result in supplemental submittals to the April 30, 2002, application.

Additionally, you plan to submit a revised Westinghouse report (WCAP) in mid October 2002 in support of the power uprate application.

We have assigned power uprate reviews a high priority. The April 30, 2002, application involves several unique features that have significantly expanded the scope of the our review.

While we have assigned sufficient resources to complete the review consistent with the established schedule, the new proposed changes and the timing of the submittal of the revised WCAP are likely to have an adverse impact on our schedule for completing the review.

To expedite the review of the new material, we request that you submit a summary of the changes to the WCAP along with the WCAP. We are endeavoring to complete our review by the original established schedule. However, any new questions that arise as a result of the new submittal would most certainly lead to delays in the completion of the review.

F. Cayia We face significant challenges in balancing our workload, available resources, and budget constraints to achieve our performance goals. Accordingly, it is imperative that the quality and timeliness of submittals are such that we can perform our review in an efficient and effective manner consistent with our performance goals.

Sincerely,

/RA/

L. Raghavan, Chief, Section 1 Project Directorate III Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket Nos. 50-266 and 50-301 cc: See next page

ML022670572 OFFICE PDIII-1/PM PDIII-1/LA PDIII-1/SC NAME DSpaulding RBouling LRaghavan DATE 09/27/02 09/27/02 09/27/02

Point Beach Nuclear Plant, Units 1 and 2 cc:

Mr. John H. ONeill, Jr.

Shaw, Pittman, Potts & Trowbridge 2300 N Street, NW Washington, DC 20037-1128 Mr. Richard R. Grigg President and Chief Operating Officer Wisconsin Electric Power Company 231 West Michigan Street Milwaukee, WI 53201 Site Licensing Manager Point Beach Nuclear Plant Nuclear Management Company, LLC 6610 Nuclear Road Two Rivers, WI 54241 Mr. Ken Duveneck Town Chairman Town of Two Creeks 13017 State Highway 42 Mishicot, WI 54228 Chairman Public Service Commission of Wisconsin P.O. Box 7854 Madison, WI 53707-7854 Regional Administrator, Region III U.S. Nuclear Regulatory Commission 801 Warrenville Road Lisle, IL 60532-4351 Resident Inspector's Office U.S. Nuclear Regulatory Commission 6612 Nuclear Road Two Rivers, WI 54241 Ms. Sarah Jenkins Electric Division Public Service Commission of Wisconsin P.O. Box 7854 Madison, WI 53707-7854 Mr. Roy A. Anderson Executive Vice President and Chief Nuclear Officer Nuclear Management Company, LLC 700 First Street Hudson, WI 54016 Nuclear Asset Manager Wisconsin Electric Power Company 231 West Michigan Street Milwaukee, WI 53201 March 2002