August 2002 Monthly Operating Report for Browns Ferry, Units 1, 2 & 3
ML022660262
Person / Time
Site: Browns Ferry  Tennessee Valley Authority icon.png
Issue date: 09/12/2002
From: Abney T
Tennessee Valley Authority
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
R08 020912 679
Download: ML022660262 (9)


Text

R08 020912 679 September 12, 2002 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Mail Stop OWFN, P1-35 Washington, D.C. 20555-0001 Gentlemen:

In the Matter of

)

Docket Nos. 50-259 Tennessee Valley Authority

)

50-260 50-296 BROWNS FERRY NUCLEAR PLANT (BFN) - AUGUST 2002 MONTHLY OPERATING REPORT The enclosure provides the August 2002 Monthly Operating Report (MOR) as required by BFN Technical Specifications Section 5.6.4.

If you have any questions concerning this report, please call me at (256) 729-2636.

Sincerely, ORIGINAL SIGNED BY T. E. Abney Manager of Licensing and Industry Affairs Enclosure cc: See page 2

U.S. Nuclear Regulatory Commission Page 2 September 12, 2002 Enclosure cc (Enclosure):

(Via NRC Electronic Distribution)

Mr. Kahtan N. Jabbour, Senior Project Manager U.S. Nuclear Regulatory Commission One White Flint, North (MS 08G9)

Office of Nuclear Reactor Regulation 11555 Rockville Pike Rockville, Maryland 20852-2738 NRC Resident Inspector Browns Ferry Nuclear Plant P.O. Box 149 Athens, Alabama 35611 Regional Administrator U.S. Nuclear Regulatory Commission Region II Sam Nunn Atlanta Federal Center 61 Forsyth Street, S.W., Suite 23T85 Atlanta, Georgia 30303-8931

U.S. Nuclear Regulatory Commission Page 3 September 12, 2002 DTL:JEW:BAB Enclosure cc (Enclosure):

D. K. Baker, BR 3H-C A. S. Bhatnagar, PAB 1E-BFN M. J. Burzynski, BR 4X-C R. G. Jones, POB 2C-BFN J. E. Maddox, LP 6A-C D. C. Olcsvary, LP 6A-C C. M. Root, PAB 1G-BFN J. R. Rupert, LP 6A-C K. W. Singer, LP 6A-C E. J. Vigluicci ET 11A-K R. E. Wiggall, PEC 2A-BFN NSRB Support, LP 5M-C EDMS-K S:lic/submit/subs/MORAUGUST2002.doc

ENCLOSURE TENNESSEE VALLEY AUTHORITY BROWNS FERRY NUCLEAR PLANT (BFN)

MONTHLY OPERATING REPORT AUGUST 2002 UNIT 1 DOCKET NUMBER 50-259 LICENSE NUMBER DPR-33 UNIT 2 DOCKET NUMBER 50-260 LICENSE NUMBER DPR-52 UNIT 3 DOCKET NUMBER 50-296 LICENSE NUMBER DPR-68

E-2 OPERATING DATA REPORT Docket No.

50-259 Unit Name BFN Unit 1 Date September 6, 2002 Completed By J. E. Wallace Telephone (256) 729-7874 Reporting Period August 2002 1.

Design Electrical Rating (Net MWe):

1065 2.

Maximum Dependable Capacity (MWe-Net) 0 Month Yr-to-Date Cumulative*

3.

Number of Hours Reactor was Critical 0

0 59521 4.

Hours Generator On-Line 0

0 58267 5.

Unit Reserve Shutdown Hours 0

0 0

6.

Net Electrical Energy Generated (MWh) 0 0

53,796,427

  • Excludes hours under Administration Hold (June 1, 1985 to Present)

OPERATING DATA REPORT Docket No.

50-260 Unit Name BFN Unit 2 Date September 6, 2002 Completed By J. E. Wallace Telephone (256) 729-7874 Reporting Period August 2002 1.

Design Electrical Rating (Net MWe):

1120 2.

Maximum Dependable Capacity (MWe-Net) 1118 Month Yr-to-Date Cumulative 3.

Number of Hours Reactor was Critical 744 5,597 145,706 4.

Hours Generator On-Line 744 5,577 143,068 5.

Unit Reserve Shutdown Hours 0

0 0

6.

Net Electrical Energy Generated (MWh) 807,883 6,174,436 142,415,900

E-3 OPERATING DATA REPORT Docket No.

50-296 Unit Name BFN Unit 3 Date September 6, 2002 Completed By J. E. Wallace Telephone (256) 729-7874 Reporting Period August 2002 1.

Design Electrical Rating (Net MWe):

1120 2.

Maximum Dependable Capacity (MWe-Net) 1118 Month Yr-to-Date Cumulative 3.

Number of Hours Reactor was Critical 744 5,489 102,319 4.

Hours Generator On-Line 744 5,478 100,895 5.

Unit Reserve Shutdown Hours 0

0 0

6.

Net Electrical Energy Generated (MWh) 812,462 5,965,204 102,687,996

E-4 UNIT SHUTDOWNS AND POWER REDUCTIONS REPORT MONTH: AUGUST 2002 DOCKET NO:

50-259 UNIT NAME:

BFN-1 DATE:

September 6, 2002 COMPLETED BY: J. E. Wallace TELEPHONE:

(256) 729-7874 No.

Date Type1 Duration (Hours)

Reason2 Method of Shutting Down Reactor3 Licensee Event Report No.

System Code4 Component Code4 Cause and Corrective Action to Prevent Recurrence 1

06/01/85 S

744 F

4 N/A N/A N/A Administrative hold to resolve various TVA and NRC concerns.

1 F: Forced 2 Reason:

3 Method 4 Instructions for Preparation of S: Scheduled A-Equipment Failure (Explain) 1-Manual Data Entry sheets for Licensee B-Maintenance or Test 2-Manual Scram Event Report (LER)

C-Refueling 3-Automatic Scram (NUREG - 1022)

D-Regulatory Restriction E-Operator Training and License 4-Continuation of Existing Outage Examination 5-Reduction F-Administrative 9-Other G-Operational Error (Explain)

H-Other (Explain)

SUMMARY

Unit 1 has been on administrative hold since June 1, 1985.

E-5 UNIT SHUTDOWNS AND POWER REDUCTIONS REPORT MONTH: AUGUST 2002 DOCKET NO:

50-260 UNIT NAME:

BFN-2 DATE:

September 6, 2002 COMPLETED BY:

J. E. Wallace TELEPHONE:

(256) 729-7874 No.

Date Type Duration (Hours)

Reason2 Method of Shutting Down Reactor3 Licensee Event Report No.

System Code4 Component Code4 Cause and Corrective Action to Prevent Recurrence N/A 1 F: Forced 2 Reason:

3 Method 4 Instructions for Preparation of S: Scheduled A-Equipment Failure (Explain) 1-Manual Data Entry sheets for Licensee B-Maintenance or Test 2-Manual Scram Event Report (LER)

C-Refueling 3-Automatic Scram (NUREG - 1022)

D-Regulatory Restriction E-Operator Training and License 4-Continuation of Existing Outage Examination 5-Reduction F-Administrative 9-Other G-Operational Error (Explain)

H-Other (Explain)

SUMMARY

Unit 2 has operated at or near 100 percent available power without any significant events.

E-6 UNIT SHUTDOWNS AND POWER REDUCTIONS REPORT MONTH: AUGUST 2002 DOCKET NO:

50-296 UNIT NAME:

BFN-3 DATE:

September 6, 2002 COMPLETED BY: J. E. Wallace TELEPHONE:

(256) 729-7874 No.

Date Type1 Duration (Hours)

Reason2 Method of Shutting Down Reactor3 Licensee Event Report No.

System Code4 Component Code4 Cause and Corrective Action to Prevent Recurrence N/A 1 F: Forced 2 Reason:

3 Method 4 Instructions for Preparation of S: Scheduled A-Equipment Failure (Explain) 1-Manual Data Entry sheets for Licensee B-Maintenance or Test 2-Manual Scram Event Report (LER)

C-Refueling 3-Automatic Scram (NUREG - 1022)

D-Regulatory Restriction E-Operator Training and License 4-Continuation of Existing Outage Examination 5-Reduction F-Administrative 9-Other G-Operational Error (Explain)

H-Other (Explain)

SUMMARY

Unit 3 has operated at or near 100 percent available power without any significant events.