0 0 V.C. SUMMER NUCLEAR STATION NRC JOB PERFORMANCE MEASURE JPS-006 Pressurizer Level Malfunction (NRC)
Revision No. 3
0 O PAGE 0 iI Pressurizer Level Malfunction (NRC)
IIi III I
II EVALUATOR li TRAINEE DATE il EVALUATOR SIGNATURE Ii il EVALUATION METHOD: PERFORM EVALUATION LOCATION: SIMULATOR. iI 15.0 MINUTES TIME STARTED: ____
ESTIMATED TIME:
10CFR55.45(a)4 IDENTIFY THE INSTRUMENTATION SYSTEMS AND THE SIGNIFICANCE OF FACILITY INSTRUMENT READINGS ii II TIME CRITICAL: No II FAULTED JPM: No II UNSATISFACTORY i_
TRAINEE PERFORMANCE: SATISFACTORY II II ItI I,
I READ TO OPERATOR:
ACTIONS AS DIRECTED IN THE WHEN I TELL YOU TO BEGIN, YOU ARE TO PERFORM THE TASK Ii II INITIATING CUES. I WILL DESCRIBE GENERAL CONDITIONS UNDER WHICHTO THIS PERFORM THIS TOOLS WITH WHICH IS TO BE PERFORMED AND PROVIDE THE NECESSARY INITIAL CONDITIONS, WHICH STEPS TASK. BEFORE STARTING, I WILL EXPLAIN THE TO SIMULATE OR DISCUSS, AND PROVIDE INITIATING CUES.
II FOR THIS WHEN YOU COMPLETE THE TASK SUCCESSFULLY, THE OBJECTIVE SJOB PERFORMANCE MEASURE WILL BE SATISFIED. i INITIAL CONDITIONS:
Plant is operating at 100% power with all conditions stable.
1.
TOOLS AND EQUIPMENT NEEDED:
NONE REFERENCED DOCUMENTS: REV DATE PRESSURIZER LEVEL CONTROL AND 08/22/95
- 1. AOP*401.6 PROTECTION CHANNEL FAILURE CHEMICAL AND VOLUME CONTROL SYSTEM 10/22/97
- 2. SOP*102 TASK STANDARDS:
- 1. PZR HTRS and letdown re-established.
- 2. Letdown relief is not lifted.
PAGE 1
!i I' Pressurizer Level Malfunction (NRC) I INITIATING CUES:
- 1. Respond to pressurizer annunciators.
TERMINATING CUES:
- 1. Operable channel selected.
- 2. Bistable tripped.
- 3. Letdown restored.
SAFETY CONSIDERATIONS:
NONE
JOB PERFORMANCE MEASURE CHECKLIST PAGE 2 (S) DENOTES SEQUENCED ELEMENT
(*) DENOTES CRITICAL ELEMENT PERFORMANCE CHECKLIST: SAT. UNSAT.
actions.
iNOTE 1: Steps 1 and 2 are izmediate operator STEP STANDARD Compares LI-459 to LI-460 and LI-461 and S 1. Verify instrument failure by recognizes that LI-459 has failed to 0%
comparing suspect channel level.
level indication and level recorder to other two channels.
STEP STANDARD Positions the PZR level control switch S*2. On pressurizer level control switch, select the position to the 460 - 461 position.
which has two operable channels.
COMMENTS:
STEP STANDARD Verifies the pressurizer level recorder
- 3. Select operable channel on the position switch channel 460.
pressurizer level recorder.
iNOTE 4: Critical if FCV-122 not full closed.
STEP STANDARD
- 4. Ensure FCV-122 is in ianual Positions FCV-122 in MANUAL and reduces the demand signal to zero. Observes and closed. (SOP-102. IV L)
FI-122 charging flow goes to zero.
COMMENTS:
0 0 JOB PERFORMANCE MEASURE CHECKLIST PAGE 3 (S) DENOTES SEQUENCED ELEMENT
(*) DENOTES CRITICAL ELEMENT PERFORMANCE CHECKLIST: SAT. UNSAT.
STEP STANDARD
- 5. Ensure PZR level is greater Checks LI-460 & LI-461 to verify PZR than 18%. level is greater than 18%.
iNOTE 6: Only critical if valve is not opened enough to prevent letdown relief from lifting.
STEP STANDARD
- 6 Place PCV-145 in manual and Positions PCV-145, controller to MANUAL open to 70%. and increases the demand signal to 70%.
COMM=NTS:
STEP STANDARD
- 7. Open TCV-144 for maximum CCW Places TCV-144, CC TO LTDN HX, in MAN flow to Letdown HX. and adjusts to 100% demand.
STEP STANDARD
STEP STANDARD 9 Open PVT-8152 letdown line Verifies PVT-8152, LETDOWN LINE ISOL, isolation indicates red light ON green light OFF.
iNOTE 10: LCV-460 should already be open.
STEP STANDARD
- 10. Open LCV-459 and LCV-460 LCV-459 and LCV-460 indicate red light letdown line isolation valve ON, green light OFF.
JOB PERFORMANCE MEASURE CHECKLIST PAGE 4 (S) DENOTES SEQUENCED ELEMENT
(*) DENOTES CRITICAL ELEMENT PERFORMANCE CHECKLIST: SAT. UNSAT.
COMMENTS:
STEP STANDARD
- 11. Ensure Charging Line Isolation MVG-8107 and MVG-8108 indicate red ligth Valves are open. ON, green light OFF.
iNOTE 12: Cue examinee to establish 105 gpm letdown flow.
c d//
STEP STANDARD S*12. Establishes 60 gpm charging Slowly opens FCV-122, CHG FLOE flow establish 60 gpm flow on FI-122 COMETS:
STEP STANDARD
"-13. Open PVT-8149A and one of the PVT-8149A and PVT-8149B or C indicate following PVT-8149B or red light ON green light OFF.
PVT-8149C.
COMMENTS:
0 JOB PERFORMANCE MEASURE CHECKLIST 0 PAGE 5 (S) DENOTES SEQUENCED ELEMENT
(*) DENOTES CRITICAL ELEMENT PERFORMANCE CHECKLIST: SAT. UNSAT.
STEP STANDARD
"*14. Open FCV-122 charging flow, as Increases or decreases the demand signal needed to maintain on the FCV-122 controller to maintain Regenerative Hx outlet between Regenerative Hx outlet between 2 5 0 *F and 250*F and 350*F and maintain 350*F and Pzr level at program without Pzr level. lifting letdown line relief.
COMMENTS:
STEP STANDARD
"-15. Close PCV-145 to maintain Decreases the demand signal on the letdown pressure between 300 PCV-145 controller to close PCV-145 and and 400 psig. observes pressure indication to maintain letdown pressure between 300 and 400 psig without lifting letdown line relief.
COMMENTS:
STEP STANDARD 16 Places PCV-145, LO PRESSURE PCV-145, LO PRESS LTDN controller, AUTO LETDOWN in AUTO. pushbutton lit.
STEP STANDARD
iNOTE 18: Operator may delay returning FCV-122 to Auto if PZR level is above program to prevent excessive reduction of charging by PZR LCS.
0 0 JOB PERFORMANCE MEASURE CHECKLIST PAGE 6 (S) DENOTES SEQUENCED ELEMENT
(-) DENOTES CRITICAL ELEMENT PERFORMANCE CHECKLIST: SAT. UNSAT.
STEP STANDARD Places FCV-122 controlled in AUTO by
- 18. Places FCV-122, charging flow depressing AUTO pushbutton when levels in AUTO when pressurizer level matches reference level.
matched per Section III.E of SOP-102. P'rrAc "D STEP STANDARD Momentarily positions TCV-143 to the
- 19. Places TCV-143, LTDN to VCT or DEMIN/AUTO position after letdown DEMIN, in DEMIN/AUTO.
temperatures have stabilized.
STEP STANDARD Observes that the Pressurizer Level
- 20. Ensure that pressurizer level Master Controller is responding master controller is properly.
responding correctly.
STEP STANDARD Momentarily places CNTRL GRP heater
"-21. Align the pressurizer heaters switch to CLOSE with RED flag for existing plant conditions.
indication Clears amber trip light on BU GRP1 heaters.
COMMENTS:
RO ONLY: Protection bistables are tripped by I&C. Examiner hands iNOTE 22:
I operator Attachment 1 of AOP-401.6 and directs him to ensure I I appropriate bistables are tripped. Ask him to identify correct I bistable.
STEP STANDARD Verifies proper bistable tripped per
- 22. Ensure bistables tripped per Attachment 1.
Attachment 1.
0 0 JOB PERFORMANCE MEASURE CHECKLIST PAGE 7 (S) DENOTES SEQUENCED ELEMENT
(-) DENOTES CRITICAL ELEMENT SAT. UNSAT.
PERFORMANCE CHECKLIST:
jNOTE 23: SRO ONLY: Examiner hands operator Attachment II of SOP-401 and asks him to explain how it is filled out.
STEP STANDARD
- 23. Directs I&C to trip Explains how Attachment II of SOP-401 is appropriate bistables and used and verifies proper bistable ensure bistables tripped per tripped per Attachment I of SOP-401.
Attachment 1.
Examiner Stops JPM At This Point TIME STOPPED:
GENERAL COMMENT
S:
NRC KA
REFERENCES:
KA NUMBER IMPORTANCE FACTOR RO SRO 3.5 3.6 011000 .AI. 01 Ability to stay predict and/or monitor changes in PZR level and pressure when operating PZR LCS controls. 3.8 3.9 011000 .A2.03 Ability to predict and mitigate the consequences of loss of PZR level.