ML022560042

From kanterella
Jump to navigation Jump to search
Completion of Security Compensatory Measures
ML022560042
Person / Time
Site: Perry 
Issue date: 09/04/2002
From: Kanda W
FirstEnergy Nuclear Operating Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
PY-CEI/NRR-2658L
Download: ML022560042 (1)


Text

FENOC FirstEnergy Nuclear Operating Company Perry Nuclear Power Plant 10 Center Road Perry, Ohio 44081 Willam R. Kanda Vice President - Nuclear 440-280-5579 Fax 440-280-8029 September 4, 2002 PY-CEI/NRR-2658L U. S. Nuclear Regulatory Commission Attention: Document Control Desk Washington, DC 20555

Subject:

Perry Nuclear Power Plant, Unit No. 1 Docket No. 50-440, License No. NPF-58 Completion of Security Compensatory Measures Ladies and Gentlemen:

On March 18, 2002, the FirstEnergy Nuclear Operating Company (FENOC) submitted a response (PY-CEI/NRR-2622L) for the Perry Nuclear Power Plant (PNPP) to the NRC Order for Interim Safeguards and Security Compensatory Measures issued on February 25, 2002. A supplemental response to address PNPP actions taken in response to the order was provided on June 6, 2002 (PY-CEI/NRR-2644L).

This letter provides notification that actions taken by PNPP to comply with the Interim Compensatory Measures, as described in the PNPP submittals identified above, were completed by August 31, 2002, as required by the Order.

There are no new regulatory commitments contained in this letter. If there are any questions concerning this matter, please contact Mr. Thomas E. Mahon, Manager - Site Protection Section, at 440-280-5314.

I declare under penalty of perjury that the foregoing is true and correct. Executed on September 3, 2002.

Sincerely, William R. Kanda Vice President - Nuclear KS) cc: Mr. Stephen P. Sands, Senior Project Manager Mr. Raymond J. Powell, Senior Resident Inspector Mr. James E. Dyer, Administrator - NRC Region III Mr. Glenn M. Tracy, Chief, Reactor Safeguards, USNRC Mr. Samuel J. Collins, Director, Office of Nuclear Reactor Regulation