September 10, 2002 Mr. John L. Skolds, President and Chief Nuclear Officer Exelon Nuclear Exelon Generation Company, LLC 4300 Winfield Road Warrenville, IL 60555
SUBJECT:
REQUEST TO WITHHOLD DYNAMIC SIMULATOR SCENARIOS AND JOB PERFORMANCE MEASURES FROM PUBLIC DISCLOSURE
Dear Mr. Skolds:
By letter dated August 13, 2002, Mr. W. Iliff, Regulatory Assurance Manager from your Clinton Power Station, requested that the NRC withhold from public disclosure certain material from a recently administered initial license exam. Specifically, Mr. Iliff requested that dynamic scenarios 6 and 7 as well as reactor operator job performance measures A.1.A.3, A.1.B.3, A.2.3, A.3.3, and A.4.3, submitted to the NRC on May 28, 2002, be withheld from public disclosure. An affidavit (pursuant to 10 CFR 2.790) signed by Thomas J. Shortell, Operations Training Manager, was provided.
We have reviewed Mr Iliffs request and concluded that this material was not used during the July/August, 2002 initial license examination administered at your Clinton Power Station.
Therefore, we see no regulatory need to maintain these documents or to make these documents publically available. In a telephone conversation between myself and Mr. T.
Shortell, Operations Training Director from your Clinton Power Station, we agreed to destroy all documentation of the above examination material.
If you have any questions regarding this matter, please contact me at 630-829-9732.
In accordance with 10 CFR Part 2.790 of the NRC's "Rules of Practice," a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Sincerely,
/RA/
David L. Pelton, Acting Chief Operations Branch Division of Reactor Safety Docket No. 50-461 License No. NPF-62 See Attached Distribution
J. Skolds cc:
Site Vice President - Clinton Power Station Clinton Power Station Plant Manager Regulatory Assurance Manager - Clinton Chief Operating Officer Senior Vice President - Nuclear Services Senior Vice President - Mid-West Regional Operating Group Vice President - Mid-West Operations Support Vice President - Licensing and Regulatory Affairs Director Licensing - Mid-West Regional Operating Group Manager Licensing - Clinton and LaSalle Senior Counsel, Nuclear, Mid-West Regional Operating Group Document Control Desk - Licensing
Mr. John L. Skolds, President and Chief Nuclear Officer Exelon Nuclear Exelon Generation Company, LLC 4300 Winfield Road Warrenville, IL 60555
SUBJECT:
REQUEST TO WITHHOLD DYNAMIC SIMULATOR SCENARIOS AND JOB PERFORMANCE MEASURES FROM PUBLIC DISCLOSURE
Dear Mr. Skolds:
By letter dated August 13, 2002, Mr. W. Iliff, Regulatory Assurance Manager from your Clinton Power Station, requested that the NRC withhold from public disclosure certain material from a recently administered initial license exam. Specifically, Mr. Iliff requested that dynamic scenarios 6 and 7 as well as reactor operator job performance measures A.1.A.3, A.1.B.3, A.2.3, A.3.3, and A.4.3, submitted to the NRC on May 28, 2002, be withheld from public disclosure. An affidavit (pursuant to 10 CFR 2.790) signed by Thomas J. Shortell, Operations Training Manager, was provided.
We have reviewed Mr Iliffs request and concluded that this material was not used during the July/August, 2002 initial license examination administered at your Clinton Power Station.
Therefore, we see no regulatory need to maintain these documents or to make these documents publically available. In a telephone conversation between myself and Mr. T.
Shortell, Operations Training Director from your Clinton Power Station, we agreed to destroy all documentation of the above examination material.
If you have any questions regarding this matter, please contact me at 630-829-9732.
In accordance with 10 CFR Part 2.790 of the NRC's "Rules of Practice," a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Sincerely,
/RA/
David L. Pelton, Acting Chief Operations Branch Division of Reactor Safety Docket No. 50-461 License No. NPF-62 See Attached Distribution DOCUMENT NAME:C:\\ORPCheckout\\FileNET\\ML022540672.wpd
- See Previous Concurrence To receive a copy of this document, indicate in the box: "C" = Copy without attachment/enclosure "E" = Copy with attachment/enclosure "N" = No copy OFFICE RIII
- RIII
- RIII
- RIII NAME DPelton:jb AMStone BBerson DPelton DATE 08/29/02 08/29/02 09/09/02 09/10/02 OFFICIAL RECORD COPY
J. Skolds cc:
Site Vice President - Clinton Power Station Clinton Power Station Plant Manager Regulatory Assurance Manager - Clinton Chief Operating Officer Senior Vice President - Nuclear Services Senior Vice President - Mid-West Regional Operating Group Vice President - Mid-West Operations Support Vice President - Licensing and Regulatory Affairs Director Licensing - Mid-West Regional Operating Group Manager Licensing - Clinton and LaSalle Senior Counsel, Nuclear, Mid-West Regional Operating Group Document Control Desk - Licensing ADAMS Distribution:
AJM DFT JBH1 RidsNrrDipmIipb GEG HBC PLL C. Ariano (hard copy)
DRPIII DRSIII PLB1 JRK1