Letter to NEI Steam Generator Generic License Change Package - Technical Specifications - Revision 6 of Steam Generator Examination Guidelines
ML022520414
Person / Time
Issue date: 09/09/2002
From: Lund A
NRC/NRR/DE/EMCB
To: Jeffrey Riley
Nuclear Energy Institute
Murphy E
Shared Package
ML022520413 List:
References
Download: ML022520414 (3)


Text

September 9, 2002 Mr. James Riley Nuclear Energy Institute 1776 I street, NW Suite 400 Washington, DC 20006-3708

SUBJECT:

NEI STEAM GENERATOR GENERIC LICENSE CHANGE PACKAGE -

TECHNICAL SPECIFICATIONS - REVISION 6 OF STEAM GENERATOR EXAMINATION GUIDELINES

Dear Mr. Riley:

This letter encloses a number of staff documents relating to the NEI Steam Generator (SG)

Generic License Change Package (GLCP) and Revision 6 (draft) of the EPRI PWR Steam Generator Examination Guidelines. We are providing you these documents as background for our upcoming public meeting on September 11, 2002. provides a sample draft of administrative technical specification 5.5.9, Steam Generator Program, which the staff believes may constitute an acceptable approach for the GLCP. documents the staffs review of industry responses, dated August 13, 20021, to staff comments dated September 18, 20012 on the draft version of Revision 6 of the examination guidelines that were presented to the staff on August 29, 20013 dealing with sampling requirements for prescriptive based inspections.

NEI enclosed a revised draft of Revision 6 of the examination guidelines with its August 13, 2002 letter. This draft includes a number of additional guideline changes relative to the earlier version that the staff commented on in its September 18, 2001 letter. Enclosure 3 provides staff comments concerning the additional changes in Section 2, Sampling Requirements for Prescriptive Based Examinations, of the guidelines.

The staff acknowledges that the guidelines are outside plant licensing bases and are not subject to NRC review and approval. However, the availability of effective industry guidelines 1

NEI letter dated August 13, 2002, Steam Generator Inspection Intervals and Non Destructive Examination Requirements Accession No. ML022390399 2

NRC memorandum dated September 18, 2001, NRC Staff Comments on Steam Generator Inspection Intervals Accession No. ML0112610664.

3 NRC memorandum dated September 21, 2001, Summary of August 29, 2001 Public Meeting with the Nuclear Energy Institute Regarding NEI 97-06 Accession No. ML012690666.

for development of SG programs for ensuring tube integrity is an important element of the industrys NEI 97-06 initiative for managing tube integrity. The staff is relying on the industry's initiative to maintain the improvements in tube integrity performance that have been gained through the years and to ensure the frequency for meeting the tube performance criteria increases with time. The staff requests that the industry consider the staffs comments when finalizing Revision 6 of the examination guidelines and/or when issuing future revisions to the guidelines.

However, the staff wishes to highlight some of comments raised in enclosures 2 and 3 as priority issues which the staff believes should be resolved concurrent with submittal of a final GLCP. These issues are identified in enclosure 4. It would be highly desirable for the industry to address these issues in Revision 6 of the guidelines or in a supplemental guideline pending the next formal revision to the guidelines.

Sincerely, Louise Lund, Chief /RA/

Component Integrity & Chemical Engineering Section Materials and Chemical Engineering Branch

for development of SG programs for ensuring tube integrity is an important element of the industrys NEI 97-06 initiative for managing tube integrity. The staff is relying on the industry's initiative to maintain the improvements in tube integrity performance that have been gained through the years and to ensure the frequency for meeting the tube performance criteria increases with time. The staff requests that the industry consider the staffs comments when finalizing Revision 6 of the examination guidelines and/or when issuing future revisions to the guidelines.

However, the staff wishes to highlight some of comments raised in enclosures 2 and 3 as priority issues which the staff believes should be resolved concurrent with submittal of a final GLCP. These issues are identified in enclosure 4. It would be highly desirable for the industry to address these issues in Revision 6 of the guidelines or in a supplemental guideline pending the next formal revision to the guidelines.

Sincerely, Louise Lund, Chief Component Integrity & Chemical Engineering Section Materials and Chemical Engineering Branch Distribution CKhan KKarwoski WBateman SG Service List EMCB RF Package ML Number: ML022520413 Letter ML022520414 ML022520415 ML022520416 ML022520419 ML022520420 DOCUMENT NAME: C:\ORPCheckout\FileNET\ML022520414.wpd OFFICE EMCB:DE EMCB:DE NAME Emurphy LLund DATE 09/09/02 09/09/02 OFFICIAL RECORD COPY