ML022520353

From kanterella
Jump to navigation Jump to search
IR 05000285-02-010, on 08/26/2002 - 08/28/2002, Fort Calhoun Station, Supplemental Inspection
ML022520353
Person / Time
Site: Fort Calhoun Omaha Public Power District icon.png
Issue date: 09/06/2002
From: Collins E
Division of Nuclear Materials Safety IV
To: Ridenoure R
Omaha Public Power District
References
EA-02-123 IR-02-010
Download: ML022520353 (11)


See also: IR 05000285/2002010

Text

September 6, 2002

EA-02-123

R. T. Ridenoure

Division Manager - Nuclear Operations

Omaha Public Power District

Fort Calhoun Station FC-2-4 Adm.

P.O. Box 550

Fort Calhoun, Nebraska 68023-0550

SUBJECT:

FORT CALHOUN STATION - NRC SUPPLEMENTAL INSPECTION

REPORT 50-285/02-10

Dear Mr. Ridenoure:

On May 17, 2002, the NRC completed a supplemental inspection at your Fort Calhoun Station.

The enclosed report documents the inspection findings, which were discussed on August 28,

2002, with Mr. Phelps, Division Manager, Engineering, and other members of your staff at the

completion of the inspection.

NRC Inspection Report 50-285/02-08 documented a preliminary White finding and apparent

violation that involved the failure to prevent radiation levels from exceeding the Department of

Transportation limits at any point on the external surface of a radioactive waste shipment

package. On July 30, 2002, the NRC issued its Final Significance Determination and Notice of

Violation for NRC Inspection Report 50-285/02-08. The significance of the violation was

determined to have low to moderate (White) importance to safety when processed through the

public radiation safety significance determination process.

This supplemental inspection was conducted to provide assurance that the root cause and

contributing causes of the White finding were understood, the extent of conditions was

identified, and the corrective actions for risk significant performance issues were sufficient to

address the cause and prevent recurrence. To accomplish these objectives, the inspector

reviewed your root cause analysis, evaluation of extent of condition, and corrective actions.

Based on the results of this inspection, the NRC determined that the identification of the root

causes, contributing causes, and corrective actions associated with the White finding were

comprehensive and broad-based.

In accordance with 10 CFR 2.790 of the NRCs "Rules of Practice," a copy of this letter and its

enclosure will be available electronically for public inspection in the NRC Public Document

Room or from the Publicly Available Records (PARS) component of NRCs document system

(ADAMS). ADAMS is accessible from the NRC Web site at

http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Omaha Public Power District

-2-

Should you have any questions concerning this inspection, we will be pleased to discuss them

with you.

Sincerely,

/RA/

Elmo E. Collins, Director

Division of Reactor Safety

Docket: 50-285

License: DPR-40

Enclosure:

NRC Inspection Report No.

50-285/02-10

cc w/enclosure:

Mark T. Frans, Manager

Nuclear Licensing

Omaha Public Power District

Fort Calhoun Station FC-2-4 Adm.

P.O. Box 550

Fort Calhoun, Nebraska 68023-0550

James W. Chase, Division Manager

Nuclear Assessments

Fort Calhoun Station

P.O. Box 550

Fort Calhoun, Nebraska 68023-0550

David J. Bannister, Manager - Fort Calhoun Station

Omaha Public Power District

Fort Calhoun Station FC-1-1 Plant

P.O. Box 550

Fort Calhoun, Nebraska 68023-0550

James R. Curtiss

Winston & Strawn

1400 L. Street, N.W.

Washington, D.C. 20005-3502

Omaha Public Power District

-3-

Chairman

Washington County Board of Supervisors

Washington County Courthouse

P.O. Box 466

Blair, Nebraska 68008

Sue Semerena, Section Administrator

Nebraska Health and Human Services System

Division of Public Health Assurance

Consumer Services Section

301 Centennial Mall, South

P.O. Box 95007

Lincoln, Nebraska 68509-5007

Daniel K. McGhee

Bureau of Radiological Health

Iowa Department of Public Health

401 SW 7th Street, Suite D

Des Moines, Iowa 50309

Omaha Public Power District

-4-

Electronic distribution from ADAMS by RIV:

Regional Administrator (EWM)

DRP Director (KEB)

DRS Director (ATH)

Sanborn (GFS)

Senior Resident Inspector (JGK)

Branch Chief, DRP/C (CEJ1)

Plant Support Chief (GMG)

Senior Project Engineer, DRP/C (WCW)

Staff Chief, DRP/TSS (PHH)

RITS Coordinator (NBH)

RidsNrrDipmLipb

Scott Morris (SAM1)

FCS Site Secretary (NJC)

Dixon-Herrity (JLD)

OEMAIL

DOCUMENT NAME: R:\\FCS\\FCS2002-10-95001-DRC.wpd

RIV:DRS\\PSB

PEER Review

C:PSB

DRP/C

D:DRS

DRCarter:jlh

LTRicketson

GMGood

CEJohnson

EECollins

/RA/

/RA/

MPShannon for

/RA/

/RA/

09/04/02

09/04/02

09/05/02

09/05/02

09/06/02

OFFICIAL RECORD COPY T=Telephone E=E-mail F=Fax

  • Previously concurred.

ENCLOSURE

U.S. NUCLEAR REGULATORY COMMISSION

REGION IV

Docket:

50-285

License:

DPR-40

EA No.

EA-02-123

Report No:

50-285/02-10

Licensee:

Omaha Public Power District

Facility:

Fort Calhoun Station

Location:

Fort Calhoun Station FC-2-4 Adm

P.O. Box 399, Hwy. 75 - North of Fort Calhoun

Fort Calhoun, Nebraska

Dates:

August 26-28, 2002

Inspector:

Daniel R. Carter, Health Physicist

Approved By:

Elmo E. Collins, Director

Division of Reactor Safety

SUMMARY OF FINDINGS

Fort Calhoun Station

NRC Inspection Report 50-285/02-10

IR 05000285-02-10; Omaha Public Power District; on August 26-28, 2002; Fort Calhoun

Station; IP 95001; Supplemental Report.

The inspection was conducted by a regional health physics inspector. The inspection identified

no findings of significance. The NRCs program for overseeing the safe operation of

commercial nuclear power reactors is described in NUREG-1649, Reactor Oversight Process,

Revision 3, dated July 2000.

Cornerstone: Public Radiation Safety

This supplemental inspection was performed by the NRC to assess the licensees

evaluation of a finding involving processing and transportation of radioactive material.

A finding previously characterized as having low to moderate safety significance

(White) was documented in the Final Significance Determination for NRC Inspection

Report 50-285/02-08. During this supplemental inspection performed in accordance

with Inspection Procedure 95001, the inspector determined that the licensee performed

a thorough, broad-based evaluation of the causes of the radioactive material

processing and transportation issue and correctly identified the extent of the conditions

that led to the shipping problem. The licensees evaluation identified one root cause

and two contributing causes. Corrective actions included: (1) procedural revisions that

implement a formal radioactive waste load plan that is commensurate with the

susceptibility of the material shifting during transport; (2) implementation of a formal

method of tracking and controlling the location within the container commensurate with

the radiological risk (dose rate) of radioactive materials being packaged for shipment;

(3) the requirement that the Manager-Radiation Protection will approve all radioactive

waste shipment releases excluding limited quantity shipments; (4) the requirement that

all shipments, except limited quantity shipments, have two independent exit surveys

performed; and, (5) the performance of an effectiveness review of implemented

corrective actions to be completed by December 15, 2002.

Because of the licensees acceptable performance in addressing the processing and

transportation of radioactive material, the White finding associated with this issue will

only be considered in assessing plant performance for a total of four quarters, in

accordance with the guidance in IMC 0305, Operating Reactor Assessment Program.

Report Details

01

Inspection Scope

This supplemental inspection was performed to assess the licensees evaluation of the

root causes, contributing causes, and corrective actions associated with the White

radioactive material processing and transportation finding. This performance issue was

previously characterized as White in the Final Significance Determination for NRC

Inspection Report 50-285/02-08 and is related to the public radiation safety cornerstone

in the radiation safety strategic performance area.

The inspector interviewed radiation workers and reviewed the following documents and

compared them to regulatory and licensee requirements:

Condition Report 2002-01009 and associated root cause evaluation which

documented the radioactive material processing and transportation issue

identified in NRC inspection report 50-285/02-08,

Station Procedures RW-300, Shipping Radwaste and Radioactive Materials,

Revision 7; RW-304, Radwaste Shipments to Barnwell, Revision 7, and RW-315,

Shipments to Vendor Processing Facility of Radioactive Materials, Revision 4,

Standing Order SO-R-2, Condition Reporting and Corrective Action, Revision 20;

Nuclear Operations Division Procedure NOD-QP-19, Cause Analysis Program,

Revision 22; and Corrective Action Group Root Cause Analysis Guideline,

Revision 0,

Radiation Protection Cycle 2 continuing training Industry Events.

02

Evaluation of Inspection Requirements

02.01 Problem Identification

a.

Determine that the evaluation identifies who (i.e. licensee, self revealing, or

NRC), and under what conditions the issue was identified.

The licensee documented the event; however, the event was self revealing in that the

licensee received a phone message from its waste processing vender stating that

shipment FCS-NW-02-08 exceeded regulatory limits. The NRC was notified of the

event by the State of Tennessee after the state was contacted by the waste processing

vendor.

b.

Determine that the evaluation documents how long the issue existed, and prior

opportunities for identification.

The evaluation documented that the licensee was notified of the event on April 24, 2002,

the day the shipment arrived at the waste processing vendor. The shipment departed

the licensees facility on April 22, 2002. The evaluation determined that this was the first

time this type of event had happened.

-2-

c.

Determine that the evaluation documents the plant specific risk consequences

(as applicable) and compliance concerns associated with the issue.

A plant specific probabilistic risk assessment is not applicable to this radioactive material

transportation finding. However, the evaluation did determine that nuclear safety was

not impacted by the event and that neither the drivers safety nor public safety were

compromised during the shipment due to the location of the radiation source. The

evaluation identified that the licensees procedures incorporated regulatory

requirements, and in some cases implemented procedural limits more restrictive to

ensure that regulatory limits are not exceeded.

02.02 Root Cause and Extent of Condition Evaluations

a.

Determine that the problems were evaluated using a systematic method(s) to

identify root cause(s) and contributing cause(s).

The inspector concluded that the root cause analysis was performed in a systematic

manner which correctly and completely determined the root cause and contributing

factors. The evaluation team performed the root cause analysis using an industry

accepted methodology which employed the following techniques: records review,

personnel interviews, and barrier analysis.

The licensees root cause evaluation identified one root cause and two contributing

causes. The evaluation determined that the root cause was the failure to package

radioactive material within the sea/land container in such a manner that it could not shift

during transport. Contributing causes were failures to: (1) establish a formal loading

plan that requires an increasing level of management oversight for materials that have a

higher risk of shifting during transport, and (2) implement a formal method of

documenting the location of more highly radioactive materials within the container.

The inspector determined that the above root cause evaluation was performed in

accordance with Station Procedure NOD-QP-19, Cause Analysis Program, Revision 22,

and Root Cause Analysis Guideline, Revision 0.

b.

Determine that the root cause evaluation was conducted to a level of detail

commensurate with the significance of the problem.

The root cause evaluation detailed the performance of a safety evaluation of the event.

The safety evaluation determined neither the shipment driver nor public safety were

compromised during the shipment. The inspector determined that the root cause

evaluation focused on the overall event and was conducted to the appropriate level of

detail commensurate with the significance of the problem. The evaluation was

thorough, broad-based, and conducted to a sufficient level of detail to enhance the

radioactive material processing and transportation program.

c.

Determine that the root cause evaluation included a consideration of prior

occurrences of the problem and knowledge of prior operating experience.

The inspector concluded that the root cause evaluation considered similar events

associated with the problem of radioactive material processing and transportation for the

past two years. From a review of the evaluation and discussions with the licensees

-3-

staff the inspector determined that industry experience was reviewed to help improve

their program.

d.

Determine that the root cause evaluation included consideration of potential

common cause(s) and extent of condition of the problem.

The licensees evaluation considered the potential common causes and extent on the

conditions associated with the processing and transportation of radioactive material.

Common causes included no formal loading plan for the loading of elevated dose rate

items in a sea/land container, and the tracking of radioactive material placed in the

sea/land container was informal and not diligently maintained.

The root cause evaluation extent of condition identified that the problem was a unique

event. The licensee determined that no similar transportation events had occurred in

the past. The inspector determined that the evaluation did not detail the applicability of

the root cause across other disciplines or departments, of similar programmatic activities

or human performance issues. The inspector interviewed the root cause evaluator and

determined that an evaluation of these issues was conducted in accordance with the

licensees Root Cause Analysis Guideline; however, the evaluator did not document this

fact in the evaluation. The licensee initiated Condition Report 2002-03028 to address

this issue.

02.03 Corrective Actions

a.

Determine that appropriate corrective action(s) are specified for each

root/contributing cause or that there is an evaluation that no actions are

necessary.

The inspector concluded that the corrective actions appropriately addressed the

associated root/contributing causes. Corrective actions included: (1) procedural

revisions that implement a formal radioactive waste load plan that is commensurate with

the susceptibility of the material shifting during transport; (2) implementation of a formal

method of tracking and controlling the location within the container commensurate with

the radiological risk (dose rate) of radioactive materials being packaged for shipment;

(3) the requirement that the Manager-Radiation Protection will approve all radioactive

waste shipment releases excluding limited quantity shipments; (4) the requirement that

all shipments, except limited quantity shipments, have two independent exit surveys

performed; and, (5) the performance of an effectiveness review of implemented

corrective actions.

The inspector determined that the corrective actions appeared to be appropriate to

prevent similar occurrences.

b.

Determine that the corrective actions have been prioritized with consideration of

the risk significance and regulatory compliance.

The inspector concluded that the corrective actions were properly prioritized. A

completion date and priority were assigned for each corrective action.

-4-

c.

Determine that a schedule has been established for implementing and

completing the corrective actions.

From a review of the root cause evaluation, the inspector determined that a schedule

had been developed for the completion of each corrective action. As of June 30, 2002

all corrective actions were completed with the exception of the effectiveness review that

has a due date of December 15, 2002.

d.

Determine that quantitative or qualitative measures of success have been

developed for determining the effectiveness of the corrective actions to prevent

recurrence.

An effectiveness review evaluation of the corrective actions implemented to prevent

recurrence of the event is scheduled to be completed by December 15, 2002. The

effectiveness review will include the following:

Review implemented requirements to ensure radioactive material will not shift

during shipment.

Review of shipping container load plans to verify sufficient detail and quality such

that field personnel have clear direction on the proper loading of materials.

Field observations to determine the quality of preparing material for shipment.

Interview personnel whose tasks support the shipment of radioactive material to

ensure an understanding of the requirements that must be adhered to.

Review the process implemented to track radioactive material placed into a

sea/land container for completeness and accuracy.

The inspector concluded that the proposed effectiveness review will adequately assess

the corrective actions implemented to prevent recurrence.

4.

OTHER ACTIVITIES

4OA3 Event Followup

(Closed) Violation (VIO) 50-285/0208-01

The Final Significance Determination for NRC Inspection Report 50-285/02-08

documented a violation of NRC and Department of Transportation requirements. The

inspector reviewed the licensees root cause evaluation, associated corrective action

document, and reply to a notice of violation, dated August 26, 2002, pertaining to the

10 CFR 71.5 violation. The licensees evaluation identified corrective actions taken to

correct the violation and prevent recurrence. The licensee is currently in full

compliance.

The inspector concluded that the licensees corrective actions adequately addressed the

root cause and two contributing causes.

-5-

4OA6 Management Meetings

Exit Meeting Summary

The inspector presented the inspection results to Mr. R. Phelps, Division Manager,

Nuclear Engineering, and other members of licensee management at the conclusion of

the inspection on August 28, 2002. The licensee acknowledged the findings presented.

This meeting constituted the regulatory performance meeting specified in the Inspection

Manual Chapter 0305 action matrix.

The inspector asked the licensee whether any materials examined during the inspection

should be considered proprietary. No proprietary information was identified.

ATTACHMENT

Supplementary Information

Licensee Contacts :

R. Clemens, Division Manager, Nuclear Assessments

D. Dryden, Licensing Engineer

M. Fans, Assistant, Plant Manager

R. Haug, Manager, Chemistry

J. Mattice, Supervisor, Radwaste

E. Matzke, Licensing Engineer

R. Phelps, Division Manager, Engineering

M. Puckett, Manager, Radiation Protection

R. Reno, Supervisor, Radiation Protection

R. Westcott, Manager, Training

NRC:

J. Kramer, Senior Resident Inspector

ITEMS OPENED AND CLOSED

Closed

50-285/0208-01

VIO

Failure to prevent radiation levels from exceeding regulatory

requirements on the external surface of a shipment package

(EA-02-123)